Supreme Court Denies Late Appeal Extensions in RMA Case
📌 In brief
In this case, the Supreme Court refused to allow late appeals against convictions related to building work in floodable areas. The applicants had been convicted of contravening the District Plan and non-compliance with an abatement notice under the Resource Management Act. Despite their arguments, the court found no reason to extend time for filing leave to appeal.
⚖️ Legal holding
A court will not extend time to file leave to appeal where there is a lengthy delay and no compelling reason.
📖 Technical summary
The Supreme Court dismissed applications for an extension of time to appeal convictions under the Resource Management Act.
📜 Headnote Official document
The Supreme Court dismissed applications for an extension to appeal convictions under the Resource Management Act, finding no compelling reason after a lengthy delay.
📚 Full judgment Official document
OUTCOME: [APPELLANT] v R [2026] NZSC 59 [21 May 2026]
IN THE SUPREME COURT OF NEW ZEALAND I TE KŌTI MANA NUI O AOTEAROA SC 6/2026 [2026] NZSC 59
[APPELLANT] Applicant AND [RESPONDENT] Respondent
SC 24/2026 [APPELLANT] Applicant AND [RESPONDENT] Respondent
SC 25/2026 [APPELLANT] Applicant AND [RESPONDENT] [ADDRESS]: [COUNSEL], [NAME] and [NAME] JJ Counsel: [redacted] SC 6/2026 Applicants in SC 24/2026 and SC 25/2026 in person [NAME] [RESPONDENT] for Respondent Judgment: 21 May 2026
JUDGMENT OF THE COURT
The applications for an extension of time to file the applications for leave to appeal are dismissed. ____________________________________________________________________
REASONS Introduction [1] The applicants, [APPELLANT[COMPANY]; its director, Mr [APPELLANT]; and its manager, Mr [APPELLANT]; were found guilty after a jury trial of charges brought under the Resource Management Act 1991 (the RMA). [2] All three applicants were convicted of an offence under s 338(1)(a) of the RMA for contravening the District Plan. This charge related to the construction of a retaining wall or closed board fence in a floodable area. [APPELLANT] and Mr [APPELLANT] were convicted of a second s 338(1)(a) offence relating to the construction of earthworks over 5 m3 in a floodable area. Finally, all three applicants were convicted of a s 338(1)(c) offence arising from non-compliance with an abatement notice. Their appeals against conviction were dismissed by the Court of Appeal.1 [3] Now, some four years later, the applicants seek an extension of time to appeal against their convictions. Background [4] The facts are set out in the Court of Appeal judgment.2 Relevantly, [APPELLANT] engaged a company to build a retaining wall on its property [APPELLANT] an open drain on the property and the western boundary line. After the building began, neighbours complained to the Council that the modifications to the drain were adversely impacting downstream properties. [5] Council officers visited [APPELLANT]’s property on 22 July 2015. They saw about 70 posts (3.6 m long) had been placed at 1.2 m centres. The posts were up to 1.5 m in height and had butted edges which created a solid face. A further 11 posts had also been installed along the northern boundary.
1 [APPELLANT[COMPANY] v R [2021] NZCA 200 (Courtney, Woolford and Mander JJ). [ADDRESS] allowed Mr [APPELLANT]’s appeal against sentence on the first charge. The sentence appeals by [APPELLANT] and Mr [APPELLANT] were dismissed. 2 At [1]–[18].
[6] The Council, later in July 2015, served an abatement notice on the applicants and the construction company requiring them to stop building “a closed board fence, retaining wall or structure in a floodable area”. The construction company advised the Council that it would be carrying out no further work. After heavy rainfall in August 2015, a large amount of water was conveyed through a gully. The partially built wall blocked the natural flow path of the water and this exacerbated flooding and ponding. Subsequently, the Council learned that further boards had been put up closing the gap [APPELLANT] the bottom of the wall and the ground. Some 100 cement bags had been placed against the wall and in the drain. With further rainfall on 1 September 2015, the works again impeded the natural flow of the path of water. The Council told the applicants they had breached the abatement notice. [7] Council officers visited the property again in mid-September 2015. They saw that the works undertaken by the applicants had caused erosion and slope instability. Some 220 cement bags had been put in the drain and against the retaining wall. Later that month, the Council found out that the applicants had engaged an earthworks company to undertake some further work — filling in the drain with soil. Further abatement notices were issued and ultimately charges laid. As was noted by the Court of Appeal, the main focus at trial was whether the property in issue was a floodable area. The proposed grounds of appeal [8] The proposed grounds of appeal are helpfully summarised in the respondent’s submissions as follows:3 24.1 exclusion of defence evidence directed at “Council’s admission of stormwater diversion” and the “defensive nature” of the structure; 24.2 absence of [NAME] expert evidence establishing whether the structure was a retaining wall; 24.3 absence of evidence about the “personal authorisation, knowledge, or intentional participation” of Mr [APPELLANT] and Mr [APPELLANT]; 24.4 the liability of landowners for flooding within a “Council controlled easement corridor”.
3 Footnotes omitted.
[9] Essentially, the applicants say that as a result of the matters identified, the jury did not have key defence evidence. Our assessment [10] The lengthy delay in filing the present leave applications is, as the respondent submits, unexplained. Against that background, the strength of the proposed appeal is not such as to provide a compelling reason to extend time to appeal.4 [11] In terms of the first and fourth of the proposed grounds, the Court of Appeal held that the alleged illegality of the Council’s discharge of stormwater onto the property was not relevant to the determination of the charges against the applicants. Rather, the charges required the [NAME] to prove that activities which were proscribed by the District Plan had been carried out in a floodable area without resource consent. Nothing raised by the applicants suggests that this approach was incorrect in this case. [12] In any event, the present case is not a suitable one for considering the applicants’ arguments in relation to these two grounds. The respondent makes the point that there was no evidence put before the trial court to show that the Council caused the flooding at the property. The respondent additionally submits that the claim about the need to build a “defensive” structure to mitigate the Council’s own alleged negligence is also not made out evidentially. This was raised for the first time at sentencing when the trial Judge observed that it had not been a proposition advanced at trial. [13] In terms of the second proposed ground, the respondent notes that although the applicants were represented by senior counsel on appeal, this issue was not raised by the applicants in the Court of Appeal. That does not make this a promising ground for an appeal, particularly after the lengthy and unexplained delay. In any event, in agreement with the submission for the respondent, it is not clear why expert evidence was required on the definition of “retaining wall”. That was a question of ordinary usage of the word in the absence of any definition in the District Plan or the RMA.
4 Ellis v R [2019] NZSC 83 at [15].
Further, the respondent notes that the evidence of the contractor was that he was asked by Mr [APPELLANT] to build a “retaining wall”. [14] The third proposed ground was also not a matter raised in the Court of Appeal. In any event, as the respondent submits, the jury was told they had to find that the applicants were “responsible” for the work and “permitted it” or that it was done by an “agent”. [15] In these circumstances, it is not in the interests of justice to grant an extension of time. Result [16] The applications for an extension of time to file the applications for leave to appeal are dismissed.
Solicitors: [redacted]
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- Supreme Court of New Zealand Supreme Court Denies Recall Request in a Case
- Supreme Court of New Zealand Supreme Court Rejects Appeal Over Building Defects
- Supreme Court of New Zealand Supreme Court Dismisses Appeal Over Unpaid Consultancy Work
- Supreme Court of New Zealand Supreme Court Rejects Appeal Application
- Supreme Court of New Zealand Claimant's Appeal Against Security for Costs Rejected by Supreme Court
- Supreme Court of New Zealand Supreme Court Rejects Appeals Against Minimum Imprisonment Sentences
- Supreme Court of New Zealand Supreme Court Denies Fee Waiver Application Based on Public Interest
- Supreme Court of New Zealand Supreme Court Rejects Appeal Against Resisting Police Officer Conviction
- Supreme Court of New Zealand Supreme Court Rejects Appeal Against Tenancy Decision
- Supreme Court of New Zealand Supreme Court Rejects Habeas Corpus Challenge
- Supreme Court of New Zealand Supreme Court Upholds Court of Appeal’s S 166 Order Decision
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
❌ Tends to be rejected
- There was a lengthy delay in filing the appeal.
- No compelling reason was provided for extending time to file leave to appeal.
- The party did not provide very special reasons to recall the judgment.
- The claimant could not prove the existence and terms of any contracts, including conditions attached.
- An applicant cannot be granted leave to appeal if allegations were not pleaded or decided at lower courts.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Supreme Court refused to allow late appeals against convictions related to building work in floodable areas.
Who was involved?
The case involved applicants who were convicted of contravening the District Plan and non-compliance with an abatement notice under the Resource Management Act, and the respondent representing the Crown.
How did the court decide, and why?
The court decided against extending time for filing leave to appeal due to a lengthy delay without any compelling reason.
Which laws or rules were applied?
The Resource Management Act 1991 was primarily involved in this case.
What was the argument that mattered most?
The applicants argued that key defence evidence was excluded and there was no expert evidence on whether the structure was a retaining wall, but these arguments did not overcome the delay issue.
Was the decision for or against the person who brought the case?
The decision was against the applicants who sought to appeal their convictions.
What does this mean for someone in a similar situation?
Someone seeking to appeal after a long delay must show compelling reasons why time should be extended, which may not be easy to prove.
What evidence or documents mattered?
The court considered the applicants' proposed grounds of appeal and the lengthy delay in filing leave to appeal.
Can a decision like this be appealed?
A decision on whether to extend time for an appeal is generally not subject to further appeal.
Is it worth getting a lawyer for a case like this?
It's always recommended to seek legal advice from a qualified lawyer for specific cases involving complex legal issues.
