Section 52 — Building Act 2004: Lapse of building consent

Text of the provision Official document

52 Lapse of building consent A building consent lapses and is of no effect if the building work to which it relates does not commence within— (a) 12 months after the date of issue of the building consent; or (b) any further period that the building consent authority may allow. Compare: 1991 No 150 s 41(1)