Section 77 — Building Act 2004: Building consent must not be granted until condition is imposed under section 75
Text of the provision Official document
77 Building consent must not be granted until condition is imposed under section 75 (1) A building consent authority must not grant a building consent for building work to which section 75 applies until the territorial authority has issued a certificate imposing the condition referred to in section 75(2) . (2) The territorial authority must impose that condition if the building consent authority requests it to do so. (3) The certificate must be— (a) authenticated by the territorial authority; and (b) signed by the owner. (4) The territorial authority must lodge a copy of the certificate with the Registrar-General of Land.
Official source: legislation.govt.nz
Search case law on this topic
See judgments from New Zealand courts and tribunals with a plain-English summary and legal holding.
Explore case law →