First-tier Tribunal Approves Garage Rebuilding but Caps Costs
📌 In brief
The tribunal allowed the rebuilding of the garage block but capped the costs at £224,800 including VAT, rejecting certain improvements as unreasonable.
⚖️ Legal holding
The costs of rebuilding the garage block must be reasonable and not constitute improvements.
📖 Technical summary
The tribunal approved the rebuilding of the garage block but limited the allowable costs.
📜 Headnote Official document
The tribunal approved the rebuilding of the garage block but limited the allowable costs to £224,800 including VAT, rejecting certain improvements as unreasonable.
📚 Full judgment Official document
OUTCOME: Allowed in Part
© CROWN COPYRIGHT
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
Case Reference
:
CHI/00HP/LIS/2020/0025
Property
:
[APPELLANT], 3 [ADDRESS] [POSTCODE]
Applicant: [redacted]
:
Mr [COUNSEL], [COMPANY] and Mr [RESPONDENT]
Respondent: [redacted]
[COMPANY] & 14 additional Respondents
Representative
:
Mr [COUNSEL] (representing [COMPANY] only)
Type of Application
:
Reasonableness of service charges – Section 27A Landlord and Tenant Act 1985
Tribunal Member(s)
:
Judge P [NAME] [NAME] of Directions
:
9 February 2021
DECISION WITH REASONS
2
Introduction
1. By application dated 18 May 2020 the Applicant sought a determination of liability to pay and reasonableness of service charge expenditure in respect of Major Works – the demolition and rebuild of a garage block - £232,600 –and the demolition and rebuild of a bin store and cycle store - £19,400. Both figures have been rounded to the nearest £100 as the figures are estimated, not actual figures.
2. Given the Coronavirus pandemic and considerations of health and the resulting suspension of all inspections and hearings in person, on 25 June 2020 the tribunal directed that the application be determined on the papers, unless within 28 days any party objected. No objection having been raised the tribunal received the Hearing bundle as directed. References to pages in the bundle are shown as [ ].
3. However, on examining the bundle and the statements of case from each party with expert evidence, the tribunal decided that it was not appropriate for this matter to be determined on the papers and that, in the interests of justice, a hearing should be fixed. In the circumstances the tribunal duly made directions for a hearing which took place virtually on 5 January 2021.
4. Unfortunately, thereafter one of the tribunal members tested positive and became unwell with [NAME], for which reason regrettably there has been a short further delay in the preparation of this decision, for which the tribunal extends its apologies.
Background
5. [APPELLANT] is a purpose-built block of flats dating back to the late 1950’s. It originally comprised 12 flats over 3 floors with a separate block of 12 [NAME] and surrounding areas. In or about 2010/2011 4 new flats (numbers 13 to 16) were developed by the addition of a further storey to the building. Following completion of these 4 new flats each was sold off on a long lease. In December 2013 [APPELLANT[COMPANY] ([COMPANY]), which is owned by 12 of the 16 long leaseholders, acquired the freehold of [APPELLANT] from the developer of the new flats.
6. Under the original 12 leases each [NAME] was to contribute a rateable proportion of the service charge (see clause 1(c)(ii)) as specified in each lease. The service charge under the original leases (with which this application is concerned) comprises the expenditure incurred by the lessor incidental to the performance of its covenants under clause 6. By that clause the lessor covenants, amongst other things, to ‘maintain, repair, redecorate and renew … the main structure and in particular the roofs chimneys .. etc.’ of [APPELLANT].
7. Under each of the 4 new leases as originally entered (rather than using rateable values) it was provided that each [NAME] would pay 1/16th of the
3 annual service charge expenditure incurred in the performance of clause 6 except in relation to the costs (incurred under clause 6(4) of each lease) of maintaining the lifts, in respect of which the [NAME] each specifically covenanted to pay an equal share divided by the number of flats entitled to use the lifts (see clause 1(c) of these new leases).
8. In addition, by deeds of variation made in early 2013 between the then freeholder and each of the [NAME] of flats 13 to 16, their leases were varied to provide, amongst other things, that for the avoidance of doubt the [NAME] should not be required to contribute towards the maintenance and repair of the 12 [NAME] already constructed at [APPELLANT]. This was done by (clause 1.3 of the deeds of variation) inserting into clause 1(c) of each of the new leases the words ‘other than the main structure the roofs the chimney stacks gutters and rainwater pipes of the 12 existing [NAME] constructed prior to the date hereof.’
9. On 29 September 2016 the Applicant herein together with 12 leaseholders made an application to the tribunal, opposed by the same Respondent (then owner of flats 3, 8 and 10) to vary the leases of the 16 flats pursuant to section 35 of the Landlord and Tenant Act 1987. The Applicant proposed, amongst other changes, that all the leases be varied to require all of the flats to pay 1/16th toward the service charges save in respect of the [NAME] to which the 12 original flats would contribute equally (i.e. 1/12th).
10. By a decision dated 3 April 2017 the tribunal ordered that the new leases of flats 13-16 be varied so that the words of clause 1(b) (insurance) and clause 1(c) (annual service charge) [189] were altered from ‘one sixteenth’ to ‘a rateable proportion being such proportion as the rateable value of the demised premises bears to the rateable value of the whole of [APPELLANT]…’. The tribunal left untouched in these leases the exclusion of the [NAME] and ‘equal share divided’ provision in relation those legally entitled to use the lift.
11. Yet further, by a second application dated 26 February 2020 the Applicant together with a number of [NAME] applied again to the tribunal to vary the original 12 leases to take account of the unintended shortfall in recovery of any maintenance or repair costs of the existing [NAME], resulting from the introduction by the decision above of rateable values for flats 13-16 coupled with the continuing exclusion of any contribution to such costs by those flats.
12. By a further decision dated 8 December 2020 the tribunal accepted that the leases were defective and determined that the leases of flats 1 to 12 should be varied by the addition of the following words to clause 8(1): ‘save and except that the expression ‘rateable proportion’ shall in relation to the 12 [NAME] belonging to Flats 1 to 12 inclusive of [APPELLANT] mean such proportion as the rateable value of the demised premises bears to the total of the rateable values of Flats 1 to 12 inclusive.’
13. The said variation secures that the costs of any maintenance, repair, redecoration and renewal works to the original garage block are met in full
4 by the [NAME] of the original 12 flats according to their rateable proportions.
The Hearing
14. As referred to above, due to the current pandemic and consequent lockdown there has been no opportunity for an inspection in this matter and the hearing of the application on 5 January 2020 necessarily took place remotely. At the hearing the Applicant was represented primarily by Mr [APPELLANT], with additional contributions from Mr [NAME] both of whom attended by video on the [NAME].
15. Mr [NAME] was able to attend by telephone and represented the First Respondent (for ease referred to herein as the Respondent). The remaining respondents have taken no part in the proceedings; though they are properly joined to ensure they are bound by the tribunal’s determination. The tribunal is grateful to the parties’ representatives for their able, clear and constructive submissions.
The Parties’ Submissions
16. By its application the Applicant seeks prior approval under and in accordance with section 19(2) of the Landlord and Tenant Act 1985 (the terms of which are set out in full at Annex A hereto) of its proposed works to rebuild the original block of 12 [NAME] at a cost of some £232,600. Thus, the tribunal is only concerned in this case with whether the proposed costs are within the scope of the express repairing covenant and whether the proposed costs ‘are no greater amount than is reasonable.’
17. At the hearing before this tribunal the Applicant confirmed that the proposed works to the garage block, so called Phase 1 works, are as appears in the drawing from [NAME] dated 19 July 2019, entitled Option 3 and numbered 3 WA/KC/010 – Option 3 [428] .(It is not clear this is the scheme permitted under the existing planning permission.) However, the Applicant also stated that it no longer intended to carry out the Phase 2 works for rebuilding the bike store and that its application in this regard was not pursued.
18. As to the costs for Phase 1, the Applicant further made clear that these are to be accordance with the tender submitted by [COMPANY] (Phase 1 price) in the sum of £180,078.31 excluding VAT [223] plus the additional costs set out in the Applicant’s Section 20 Notice Summary Tender Sheet [307]. The latter costs therefore comprise the following:
[COMPANY]
£180,078.31 [NAME] (s.20 fee)
£ 5,000.00 Surveyor/Contract Administrator
£ 4,820.83 Building Regs
£ 695.00 [NAME]
£ 480.00 [NAME] [NAME] Consultant
£ 1,770.00
5 Sub-total
£192,844.14 VAT @ 20%
£38,568.83 Sub-total
£231,412.97 Architects Fees
£ 690.00 Planning Application Fee
£ 480.00
Grand total
£232,582.97
19. By way of justification for these works the Applicant relies in particular upon a report dated 7 June 2017 by [COMPANY], which states that it would not be a viable option to repair the structure from garage unit 7 through to 12 due to the extent of the defects observed. Whilst in relation to units 1 through to 6, although commenting that these would be considered structurally viable, the report recommended a costs/benefit exercise be carried out to determine the benefit of repair to rebuilding. In relation to the latter 6 [NAME] the Applicant relies upon the advice of [NAME], who having considered the repairs necessary to [NAME] 1-6, recommend that the most cost-effective solution is to replace all [NAME] together, including new suitably designed foundations (their advice letter of 21 April 2020 refers [303]).
20. The principal objection initially raised by the Respondent to the planned works is to the proposal to replace all [NAME], rather than repair 6 and rebuild the rest. However, upon it being clarified at the hearing that the total costs of these works would be pooled for the purposes of recovery from the [NAME] of the 12 [NAME], the Respondent decided that the benefit to him of insisting on repair of 6 [NAME] (including his own) would be marginal. In the premises the Respondent expressly withdrew his objection to the rebuilding of the entire garage block, save that it is for the subsidiary points referred to below.
21. One continuing point of concern for the Respondent in relation to the proposed rebuilding, is the slight relocation of each garage as a result of the rebuild. This results from the fact that the existing [NAME] are 2771mm wide, whereas the new [NAME] are intended to be 2823mm wide in accordance, so it was explained by the Applicant to the tribunal, with current recommended dimensions. The Respondent queried the effect on the current leases and the registered titles of each flat of the consequent migration (eastwards) of the rebuilt [NAME].
22. Although this is plainly a matter outside the scope of section 27A and equally the jurisdiction of the tribunal, the tribunal accepts there may be substance in this concern. Indeed, members of the tribunal have experience of the kind of difficulties that can arise, including conveyancing complications on any sale, where there is a material deviation between the position of any property on the ground and that shown by its title documents.
23. In discussions before the tribunal, however, [NAME] helpfully confirmed that the Applicant was mindful of these potential complications and was able expressly to assure the Respondent that if any such issues did arise in
6 relation to his premises, or for that matter any other flat, the Applicant could and would at no cost to the affected [NAME] take such steps as may be required to resolve them.
24. Otherwise, and certainly within the tribunal’s jurisdiction, the Applicant took issue only with the [NAME] costs as priced by [NAME] [223], comprising the following:
[NAME] on existing supply by NICEIC approved contractor £ 250.00 Provisional sum to supply and fit new electrical supply
£7000.00 Supply and fit internal garage lights, power and sockets £3,960.00 Supply and fit external light fittings and sockets
£ 850.00 Total (excluding VAT)
£12,060.00
25. Apart from the replacement of the 3 existing external lights (visible in the photos, for example, at pages [228] and [500]) which the Applicant accepts come within the scope of clause 6 [55], his case is that the balance of the proposed works are improvements for which the leases of the 12 original flats make no provision. As he points out, presently the [NAME] do not have electricity, lights or sockets internally, nor are there sockets or 5 lights externally, or twin car charging points (page 8 of the Respondent’s case refers [318]).
26. The Applicant accepts the facts set out above but disputes that the new supply, sockets and internal and external lighting are improvements. Its case is that the new electrical supply is necessary for the proper provision of the external lighting as well as the other items. As for the internal lighting Mr [NAME] explained that this was necessary because the new [NAME] are designed without any rear window. Further, the Applicant contends that the additional electrical services accord with current standards and should therefore be included in any such rebuild; although the Applicant accepted that it could not point to any specific Building Regulation or Code of Practice in support.
Discussion
27. In light of the foregoing the only live issue remaining for determination by the tribunal is in relation to the [NAME] and the extent to which these constitute improvements outside the scope of clause 6. Given that presently there are 3 external lights to the garage block, it is clearly the case as conceded by the Respondent that the replacement of these lights as part of the rebuild is not an improvement. Thus, where the cost of 5 lights and 3 external sockets is priced by [NAME] at £850, the tribunal is satisfied that for 3 lights a cost of £450 would be reasonable provision in accordance with section 19(2) of the 1985 Act (above).
28. Equally, it is clear that any necessary works associated with the provision of these 3 lights will not be an improvement either. In this regard the tribunal accepts, and is fortified by the technical expertise of its two surveyor members in so doing, that such necessary associated works will
7 include the report cost and cost of a new supply. As to the latter cost, if the services extended to the full specification the provisional sum of £7,000 might be appropriate. However, if the supply is only to support the 3 external lights, the tribunal would expect a reduced cable requirement and a reduction in cost in the order of 30%.
29. Turning then to the question whether the additional electrical services should be disallowed as improvement works. The tribunal accepts in principle that where betterment is a result of carrying out repair works in accordance with current building standards that work will not normally constitute an improvement outside the scope of any covenant to ‘Maintain repair redecorate and renew.’ However, in our judgement the introduction of the sockets, internal lighting and additional external lighting goes beyond these parameters so that each is properly regarded as an improvement rather than part and parcel of the accepted maintenance, repair and renewal work.
30. In relation to the internal lighting, the omission of the windows does not in our view change this conclusion. The simple fact of the matter is that presently there is no internal lighting and its introduction remains an enhancement of the existing specification, however desirable it may be. Moreover, the concession that none of these works (sockets, added internal or external lighting or charge points) is required by Building Regulations or any known Code of Practice in relation to the rebuilding of the [NAME], puts the matter in our view beyond doubt.
Decision
31. For the reasons stated above the tribunal accordingly determines under and for the purposes of section 27A, that the amount payable in accordance with section 19(2) in respect of the proposed rebuilding of the original 12 garage block is no greater than the sum of £224,800 including VAT; allowing £5,600 plus VAT (250+450+(0.7x7000)) rather than £12,060 plus VAT for the [NAME] and rounding down appropriately.
32. This does not of course mean that the Applicant cannot carry out these additional electrical works, but like the electrification of the garage doors it will need to be funded by way of individual agreements with [NAME] rather than through the service charge.
9 February 2021
8 NOTICE REGARDING APPEAL
1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application to [EMAIL]. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.
2. If the person wishing to appeal does not comply with the 28-day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28-day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.
3. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal and state the result the party making the appeal is seeking.
📊 How courts decide similar cases
Among 11 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Upholds Reasonableness of Service Charges
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges for Repairs Reasonable
- First-tier Tribunal (Property Chamber) First-tier Tribunal Determines Reasonable Service Charges for Tenant
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Brickwork Arch Repair
- First-tier Tribunal (Property Chamber) Tenant Wins Service Charge Dispute Over Major Works Notification
- First-tier Tribunal (Property Chamber) First-tier Tribunal Reduces Service Charges for Poor Grounds Maintenance
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Reasonable
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Reasonable
- First-tier Tribunal (Property Chamber) Landlord's Service Charge Claim Dismissed by First-tier Tribunal
- First-tier Tribunal (Property Chamber) Tribunal Rules Service Charge for Major Repairs Reasonable
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The tribunal accepted that replacing three existing external lights was not an improvement.
- The tribunal accepted that necessary works associated with providing the three external lights, including a new supply, were not improvements.
- The tribunal found that the total cost for rebuilding the garage block should be £224,800, including VAT.
- The Respondent withdrew his objection to rebuilding the entire garage block because the benefit of insisting on repair for six garages would be marginal.
❌ Tends to be rejected
- The tribunal rejected the argument that introducing internal lighting was necessary due to the omission of windows in the new garages.
- The tribunal rejected the argument that new electrical sockets, internal lighting, and additional external lighting were part of accepted maintenance, repair, and renewal work.
- The tribunal rejected the argument that additional electrical services should be included because they accord with current standards, as no specific Building Regulation or Code of Practice was cited.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The tribunal approved the rebuilding of the garage block but limited the allowable costs to £224,800 including VAT.
Who was involved?
The claimant sought approval for major works while the respondents opposed certain improvements.
How did the court decide, and why?
The court decided that the costs of rebuilding the garage block must be reasonable and not constitute improvements, limiting the allowable costs.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 s.27A was applied.
What was the argument that mattered most?
The argument that mattered most was whether the costs of rebuilding the garage block constituted improvements or were reasonable expenditures.
Was the decision for or against the person who brought the case?
The decision was partially for the person who brought the case, approving the rebuilding but limiting the costs.
What does this mean for someone in a similar situation?
Someone in a similar situation should ensure that the costs of major works are reasonable and do not constitute improvements.
What evidence or documents mattered?
Evidence and documents related to the costs of rebuilding the garage block and expert reports on the necessity of the works mattered.
Can a decision like this be appealed?
Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
Yes, it is always recommended to get advice from a qualified solicitor for a case like this.
