First-tier Tribunal Decision on Service Charges for Major Works and Repairs
📌 In brief
The First-tier Tribunal ruled on whether service charges for major works and responsive repairs were legal under lease agreements. The tribunal found that the charges were reasonable and met statutory requirements.
⚖️ Legal holding
Service charges for major works and responsive repairs are recoverable under lease provisions if they are reasonably incurred and comply with statutory consultation requirements.
📖 What the law says
This rule limits the recovery of service charges based on costs incurred more than 18 months prior to the demand for payment. However, if the tenant was notified in writing within 18 months of the costs being incurred, then the tenant remains liable to pay the service charge.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The tribunal ruled on the legality of service charges for major works and responsive repairs under lease provisions.
📜 Headnote Official document
The First-tier Tribunal ruled on the legality of service charges for major works and responsive repairs under lease provisions. The tribunal determined that the service charges were demanded in accordance with the lease and statutory consultation requirements were met.
📚 Full judgment Official document
OUTCOME: Dismissed
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case reference : LON/00BE/LSC/2019/0169 Property : 18 [NAME], [ADDRESS] [POSTCODE] Applicant : [redacted] : In person Respondent: [redacted] London Borough of [NAME] : In person Type of [NAME] :
Liability to pay service charges
Tribunal members :
Judge Angus [NAME] [NAME] and venue of hearing : 10 & 11 [ADDRESS] [POSTCODE] Date of decision : 19 November 2019
DECISION
Note: In this decision figures in [] are references to pages numbers in the document bundles. Decisions 1. The service charges for the first major works project were demanded in accordance with the lease provisions.
2. The on-account payment in respect of the second major works was demanded before the last quarter day of the year (1 January 2018).
3. The notices issued on 4 May 2012 complied with Section 20B (2) of the 1985 Act.
4. In respect of both major works [NAME] did comply with the statutory consultation requirements imposed under section 20 of the 1985 Act.
5. In respect of the installation of the fire breaks in the roof void [NAME] did comply with the statutory consultation requirements imposed under section 20 of the 1985 Act.
6. The disputed itemised costs incurred in the first major works were reasonably incurred and were recoverable under the terms of the lease.
7. The disputed costs incurred as responsive repairs in 2016/2017 were reasonably incurred and were recoverable under the terms of the lease. The applications and hearing 8. On 2 May 2019 the tribunal received Mr [APPELLANT] [NAME] under section 27A of the Landlord and Tenant Act 1985 (“the 1985 Act”) for a determination of his liability to pay service charges in respect of the years 2010/2011, 2011/2012, 2012/2013, 2016/2017 and 2017/2018. In addition, Mr [NAME] applied for orders under section 20C of the 1985 Act and under paragraph 5A of schedule 11 to the Commonhold and Leasehold Reform Act 2002. By these applications Mr [NAME] sought orders limiting [NAME]’s ability to recover the cost of these proceedings either through the service charge or as an administration charge under the terms of his lease.
9. At the hearing Mr [NAME] appeared in person and [NAME] was represented by [COUNSEL]. Mr [COUNSEL] is a solicitor although he does not specialise in landlord and tenant work. Mr [COUNSEL] is a barrister.
10. Mr [COUNSEL] did not give evidence and consequently he was not subject to cross examination. On Mr [NAME] behalf we heard oral evidence from [NAME]. On behalf of [NAME] we heard oral evidence from [NAME], [NAME] and [NAME]. Mr [NAME] is employed as a Chartered Quantity Surveyor at [NAME], consultants to [NAME]: Mr [NAME] is employed as a Senior Building Surveyor at the same firm: Ms [NAME] is employed as a Revenue Service Charge
officer by [NAME]: Ms [NAME] is employed as a Project Manager by [NAME]: Mr [NAME] is employed as a Capital Works Consultation Manager by [NAME]. 11. [NAME] also attended the hearing. She is an enforcement officer with [NAME]. During the hearing Ms [NAME] provided Mr [NAME] with instructions that enabled him to answer some of our questions although she did not formally give evidence. As with Mr [NAME] she was not therefore subject to cross examination.
12. At the start of the hearing Mr [NAME] requested that we admit a small additional bundle of documents comprising (a) replacements of the photographs annexed to Mr [NAME] technical report of 15 August 2019 (b) a replacement of a calculation sheet annexed to the witness statement of Mr [NAME] (c) replacements of two plans annexed to the witness statement of Ms [NAME] and (d) recent inter partes correspondence. The replacement photographs, calculations sheet and plans were of better quality than those included in the bundles.
13. Mr [NAME] objected to the request, although the only ground that he gave for his objection was that the replacement photographs could not be verified because the originals had not been taken by Mr [NAME]. The same objection could be taken to the original photographs in the hearing bundle. Furthermore, we could consider any challenge to the authenticity of the photographs when weighing Mr [NAME] evidence. We could see no logical objection to admitting replacement copy documents that were of better quality than those included in the original hearing bundle. Equally there was no prejudice to Mr [NAME] because he was aware of both the original documents and the inter partes correspondence. Consequently, and for each of these reasons we admitted the additional bundle of documents.
14. We granted Mr [NAME] request that we should defer consideration of the section 20C and paragraph 5A applications until after this decision is issued. Directions for the disposal of those applications are to be found at the end of this decision. Mr [NAME] also indicated that [NAME] would apply for its costs under rule 13 although it is not an [NAME] that we would encourage. Background 15. [NAME] and Harbledown House are two similar four storey blocks of flats build in the late 1920s. They form part of [NAME]’s [ADDRESS] estate. There are 42 flats in [NAME] and 38 in Harbledown House. As constructed, access to the flat is via stairwells at both ends of each block with external walkways. Both blocks are of a mixed tenure. Some flats have been acquired under the Right to Buy legislation whilst others are occupied by [NAME]’s rental tenants.
16. Mr [NAME] owns flat 18 in [NAME] under a lease dated 7 May 1990 for a term of 125 years from that date [B3-B34].
17. In 2007 [NAME] decided to refurbish both blocks as they were in need of repair. It is apparent that the decision was informed by a number of reports. Mr [NAME] told us that with one exception all the reports had been destroyed under [NAME]’s destruction policy. The exception was a Condition and Decent Homes Report [F10-F28], based on a survey undertaken over two days on 28 November and 7 December 2006. The final paragraph of page 25 of the report [F26] confirms that the authors are waiting for “the mechanical and electrical reports to make their respective recommendations”: a phrase that confirms the existence of other reports that Mr [NAME] told us had been destroyed. The report contains much helpful background information that has assisted us in this decision. 18. [NAME] gave notice of its intention to complete the refurbishment of the two blocks on 27 June 2007 [F1]. A specification of works was prepared and put out to tender. [NAME] issued proposal notices on 31 July 2009 [F42] informing the [NAME] that the contract would be let to [COMPANY] at an estimated cost of £1,679,489. Work commenced on 22 March 2010 and was completed by 1 April 2011. There was then a long delay until 28 February 2014 when [NAME] issued a final account calculation sheet that effectively crystallised the liability of the [NAME] [G2-4].
19. It seems that whilst the refurbishment works were being completed [NAME] discovered that the roof voids in both blocks were not compartmentalised. This represented a fire risk, in that that any fire could spread quickly along the roof voids. Consequently, [NAME] decided to install fire breaks in the roof voids. On 28 March 2011 (just three days before the works were completed) [NAME] issued what purported to be both section 20B notices and consultation proposal notices [E193] informing the [NAME] that the cost of completing the additional work would be £29,150 per block or £58,300, and invited the leaseholders’ comments. This cost was also the actual cost and as we were told that all the work was completed by 1 April 2011 the inescapable conclusion is that this work had largely been completed when the notices were issued. 20. [NAME] demanded £12,884.88 from Mr [NAME] in respect of the first major works project that included his share of the cost of installing the fire breaks in the roof voids. Although the position is unclear, [NAME] appear to have conceded that costs incurred before 4 November 2010 are not recoverable because they were caught by section 20B. Consequently, [NAME] have limited their claim. On the basis of [E218] [NAME] appear to have limited their claim to £6,248.30 although that figure is not consistent with the figure of £6,297.41 given at the hearing and contained in [NAME]’s letter of 18 April 2019 [E205].
21. In October 2015 [NAME] ballotted its residents on the possibility of installing new door entry systems “to improve safety and security”. The extent of the ballot is still not clear to us. We do not know if [NAME] ballotted all the residents or only those in selected blocks. In any event they ballotted the residents of [NAME]. The letter enclosing the ballot paper states that [NAME] seeks “to obtain over a 50% approval from the residents” [F138]. Mr [NAME] returned his ballot paper stating that he did not accept the proposal. The ballot results are at [H230] although it is not clear to us when, if at all, the results were communicated to Mr
[NAME]. For [NAME] as a whole 35 ballot papers were issued and 20 were returned. Of the 20 returned 13 supported the proposal whilst 7 objected to it. [NAME] treated non-returned ballots as objections with the result that the 50% threshold was not met for [NAME] as a whole.
22. Two separate entrances and walkways serve [NAME]: one serves flats 1, 2, 6–21 and the other serves flats 25–42. The 50% threshold was met in respect of the former but not the latter. On that basis [NAME] decided to proceed with the installation of a new door entry system serving flats 1, 2, 6–21, which included Mr [NAME] flat.
23. On 20 July 2016 [NAME] gave notice of its intention to install the new door entry system [F143]. A specification of the proposed works was put out to tender, and on 6 March 2017 [NAME] gave notice of its proposal to let the tender to [COMPANY] at an estimated cost of £88,399 [F152], which would result in a rechargeable block of cost of £13,594.52 and an estimated service charge of £1,037.43 However, the proposal notice sent to Mr [NAME] records the ballot results not for [NAME] but for [NAME] although it records that “only those blocks with over 50% in favour have been selected for the new door entry system”.
24. It is apparent that the new door entry system has been installed and the work completed although a final account calculation sheet has not yet been issued. Thus, the only service charges in issue at the hearing related to the on-account demand.
25. The first day of the hearing was largely spent in establishing the chronology of statutory notices, demands, invoices and notifications issued by [NAME] in connection with these two major works projects. Despite our initial misgivings we concluded that [NAME] had not deliberately attempted to obfuscate the chronology. The reason for the confusion was more prosaic: [NAME] had introduced procedures of such complexity that, as Mr [NAME] observed, some of its own employees do not understand them.
26. In an effort to assist our understanding of the documents in the hearing bundle we prepared our own chronology tables and we include them in the reasons section of this decision. For the avoidance of doubt, we find the contents of those tables as facts. The delay in issuing this decision results in large measure from the time that we have taken in establishing these chronologies: time that could have been saved if [NAME] had prepared its case in a more coherent manner. The London Borough of [NAME] v Woelke [2013] UK UT 0349 (LC)
27. In the above case the Upper Tribunal considered the terms of Mr [NAME] lease in the context of the [NAME]’s demands for service charges in connection with a previous major works project. We now refer to the Deputy President’s decision in that case as the “previous decision”.
28. The previous decision contains a helpful description of the relevant lease terms in paragraphs 4-10. As the Deputy President points out in paragraph 10 the lease provisions “follow a conventional pattern of charging for services by reference to defined years, with equal quarterly payments based on an estimate of expenditure for the forthcoming year followed by a balancing payment or credit once a final year end account has been prepared”.
29. However, as with many local authorities [NAME] collected major works service charges separately from these annual “conventional” provisions. Before commencing a major works project, [NAME] issued invoices to cover the total estimated cost of the work. After the work was completed and the final account calculated, it than issued either invoices in respect of any shortfall or credit notes in respect of any overpayment. In summary the Deputy President decided that the invoices did not comply with the requirements of the lease. As such, they did not create a liability on the part of the leaseholder to pay the sums demanded. [NAME] had to provide revised or additional notifications compliant with the terms of the lease before the sums claimed would become payable.
30. The previous decision created formidable problems not just for [NAME] but for other local authorities. In effect the central issue in this case is the extent to which the procedures subsequently adopted by [NAME] adequately deal with the problem identified in the previous decision.
31. In particular Mr [NAME] on behalf of [NAME] relied on paragraph 59 of the previous decision and for ease of reference we now set out both paragraph 59 and the following paragraph 60 that, to an extent counter-balances it:
59. Subject to those essential features, however, I agree with Mr [NAME] that the requirements of notice under paragraph 4(1) should be approached in a non- technical manner. In particular, I agree that it is not necessary that all of the information be provided in a single document or even on a single occasion. If on an objective reading of two or more documents on which reliance is placed it would be clear to a reasonable recipient, familiar with the terms of the lease, that the appellant was providing notice for the purpose of paragraph 4(1), and provided that taken together the documents satisfied the minimum requirements I have referred to above, I can see no reason why a single document should be insisted on. There is no reason why service charges for major works should not be identified in a separate document if that is thought to be more convenient for the purpose of identifying charges for which loans or different payment terms are available, provided that the leaseholder is also provided with a statement of the total Service Charge and the balance due for the year. If after notice has been given of the Service Charge for the previous year an additional item of expenditure, previously overlooked, is discovered it would be sufficient for the appellant to provide a statement of the nature and amount of that additional expenditure without repeating its previous summary of the whole of the costs and expenses incurred in the year. It would be essential, however, for the relevant notification to state the total Service Charge for the year, recalculated to take the additional item into account, to identify the
method of apportionment which had been adopted and to state the new balance due. An additional notification which left leaseholders to work out for themselves that there was no overlap between the cost of major works and the sums previously demanded for revenue items, and to calculate the aggregate Service Charge for the year and the balance now due from them, would in my judgment be defective.
60. I also consider that annual accounting is essential to the validity of a notification under paragraph 4(1). Annual accounting promotes clarity and ease of comparison for leaseholders. Avoidable complexity, inconsistency and obscurity in accounting are obvious causes of confusion and dispute in relation to service charges and the parties cannot be taken to have intended that costs and expenses incurred in more than one year should be dealt with collectively outside the framework of annual accounting clearly contemplated by the Third Schedule. Issues in dispute 61. The disputed issues are helpfully summarised in the Scott Schedule at [B1- B2]. For the purpose of this decision we briefly summarise the issues as follows, by reference to Mr [NAME] case: a. The service charges for the first major works are not payable in total because they were not demanded in accordance with the lease provisions: this was the argument considered in the previous decision. b. The on-account payment demanded in respect of the second major works is not payable because it was not demanded until after the last quarter day of the year (1 January 2018). c. The notices issued on 16 March and 4 May 2012 did not comply with Section 20B(2) of the 1985 Act. d. In respect of both major works [NAME] have not complied with the statutory consultation requirements imposed under section 20 of the 1985 Act and consequently they can recover only £250 in respect of each project. e. In the alternative [NAME] had not complied with the statutory consultation requirements in respect of the installation of fire breaks in the roof void and consequently it can only recover £250. f. In the alternative itemised costs incurred in the first major works had not been reasonably incurred and/or were not recoverable under the terms of the lease.
g. Two costs incurred as responsive repairs in 2016/2017 had not been reasonably incurred and/or were not recoverable under the terms of the lease. Reasons for our decisions The service charges for the first major works project were demanded in accordance with the lease provisions 62. We set out below our chronology of the demands, invoices and notifications relating to the first major works project: -
Date Action Bundle page number 1 April 2007 [NAME] issue an invoice for an on-account payment of £13,274.45 in respect of the first major works. [NAME] accepts that this did not comply with the previous decision. E10 29 March 2010 [NAME] issue (a) a service charge estimate of £969.83 for 2010/11 and (b) an invoice for that sum. Neither refer to the cost of the first major works. E21, 22 1 April 2011 [NAME] issue (a) a service charge estimate of £924.24 for 2011/12 and (b) an invoice for that sum. Neither refer to the cost of the first major works. E48, E50 1 August 2011 Issue of final account for first major works contract recording a total contract cost of £1,777,955 of which £436,797.99 is rechargeable to the [NAME] of [NAME]. G55- G80 30 November 2011 [NAME] issue (a) the service charge account for 2010/11 and (b) a credit note for £51.07 because the actual charge was [NAME] than the estimated charge of £969.83. The account does not include any of the first major works costs. E31, E32 28 March 2012 [NAME] issue (a) a service charge estimate of £951.84 for 2012/13 and (b) an invoice for that sum. Neither refer to the cost of the first major works. E64, E66 14 August 2012 Although not apparently included in the bundle it seems that [NAME] issue a further invoice for an on-account payment of £857.24 in respect of the first major works. E7 16 October 2012 [NAME] issue (a) the service charge account for 2011/12 and (b) an invoice for £27.00 because the actual charge was more than the estimated charge of £924.24. The account does not include any of the first major works costs. E55, E56 4 October 2013 [NAME] issue (a) the service charge account for 2012/13 and (b) a credit note for £123.51 because the actual charge was [NAME] than the estimated charge of £951.84. The account does not include any of the first major works costs E77, E79 28 February 2014 Issue of Final Account calculation sheet G2-G4
28 February 2014 [NAME] issue three “revised notifications” relating to the 2010/11, 2011/12 and 2012/13 service charge accounts. These revised notifications differentiate between the revenue service charge and the major works service charge. The figures for the revenue service charge appear to restate the sums previously demanded and presumably paid. In respect of the first major works costs the notifications state that the following sums are payable within one month:- In respect of 2010/11, £10,622.64 In respect of 2011/12, £ 1,940.12 In respect of 2012/13, £ 322.12 Total: £12,884.88 Each notification states the total service charge for the year that is said to be “payable within one month”. E15. E43, E59 28 February 2014 On the same day that [NAME] issues the three “revised notifications” it also issues a credit note for £1,246.82 in respect of the first major works. This represents the difference between the sum of the invoices issued on 1 April 2007 and 14 August 2012 (£13,274.45 + £857.25 = £14,131.70) and Mr [NAME] share of the actual cost (£12,884.88). E13
63. The relevant provisions of the lease are to be found in part 1 of the Third Schedule and in particular: -
1(1) In this Schedule “year” means a year beginning on 1st April and ending on 31st March
1(2) Time shall not be of the essence for service of any notice under this Schedule
2(1) Before the commencement of each year (except the year in which the lease is granted) the Council shall make a reasonable estimate of the amount which will be payable (as hereinafter defined) in that year and shall notify the [NAME] of that estimate
2(2) The [NAME] shall pay the Council in advance on account of Service Charge the amount of such estimate by equal payments on 1st April 1st July 1st October and 1st January in each year
4(1) As soon as practicable after the end of each year the Council shall ascertain the Service Charge payable for that year and shall notify the [NAME] of the amount thereof
4(2) Such notice shall contain or be accompanied by a summary of the costs incurred by the Council of the kinds referred to in this Schedule and state the balance (if any) due under paragraph 5 of this Schedule
5(1) If the Service Charge for the year ……….. exceeds the amount paid in advance under paragraph 2 ………. Of this Schedule the [NAME] shall pay the balance thereof to the Council within one month of service of the said notice
5(2) If the amount so paid in advance by the [NAME] exceeds the Service Charge for the year …….... the balance shall be credited against the next advance payment or payments due from the [NAME] ……
64. Essentially there were three strands to Mr [NAME] case: -
a. The invoices issued by [NAME] still did not comply with the terms of the lease. [NAME] had demanded the total estimated cost at the outset and then issued a credit note for an overpayment when the final account was calculated; and
b. In paragraph 59 of the previous decision the Deputy President had in mind “an additional item of expenditure, previously overlooked” when he decided that further notifications could be given under paragraphs 2(1) and 4(2) of the lease. Mr [NAME] pointed out that in this case the cost of the major works had not been overlooked but had simply not been estimated or ascertained; and
c. It was not clear what was being demanded. Although he did not put it in these terms the “revised notifications” were not consistent with the invoices and credit notes.
65. As explained by Mr [NAME], [NAME] has retained a system of invoicing that it accepts does not comply with the previous decision, whilst superimposing on that system a series of notifications that it believes does comply with paragraphs 2(1) and 4(1) of part 1 of the third schedule to the lease as interpreted by the previous decision.
66. In the context of the first major works project Mr [NAME] case on behalf of [NAME] was that the revised notifications issued on 28 February 2014 complied with paragraph 4(1) of the lease and any confusion did not justify Mr [NAME] refusal to pay. However, the flaw in Mr [NAME] case is that the leaseholders are now advised that if they wish to take advantage of various payment options they must make payment in accordance with the noncompliant invoices rather than the notifications.
67. With some hesitation but for each of the following reasons we consider that the service charges for the first major works project were demanded in accordance with the lease provisions and consequently they are payable by Mr [NAME]: -
(a) Although no satisfactory explanation was offered for the long delay between the issue of the final account on 1 August 2011 and the issue of the final account calculation sheet on 28 February 2014 it seems that Mr [NAME] liability in respect of each of the three service charge years was not crystallised until 28 February 2014. Consequently, the revised notifications were sent “as soon as practicable after the end of each year” as required by paragraph 4(1); and
(b) The revised notifications of 28 February 2014 comply with the requirements of paragraph 59 of the previous decision because the service charges for the major works are identified in a separate document that also states the total service charge and the balance payable for the year; and
(c) Having regard to the factual matrix that underpinned the previous decision it is apparent that the Deputy President’s use of the word “overlooked” encompassed also expenditure that had not previously crystallised; and
(d) In answer to our question Mr [NAME] said that he “recognised the notifications as demands” and he was not therefore confused.
The on-account payment in respect of the second major works was demanded before the last quarter day of the year (1 January 2018).
68. We set out below our chronology of the demands, invoices and notifications relating to the second major works project: - Date Action Bundle page number 16 February 2017 [NAME] issue (a) a service charge estimate of £1,166.39 for 2017/18 (b) an invoice for that sum and (c) a notification for the same sum. The notification includes “£0.00” in respect of the second major works. E140, E138, E136 6 March 2017 [NAME] issue (a) a further notification that now includes £1,011.50 for the second major works and (b) explanatory notes saying payment is not required now but should be made only when the invoice is received. E154, E156, F158
16 February 2018 [NAME] issue (a) an estimate of the second major works costs of £1,037.44 of which £1,011.50 is estimated to be incurred in 2017/18 and £25.94 in 2018/19 (b) an invoice for the total estimated cost of £1,037.44 that is debited to the running account. E162, 160
E8
69. Mr [NAME] case was that because the invoice for the total estimated cost was not issued until after the last quarter day of the 2017/2018 year it was not payable.
70. The invoice however relates to two years. The first for £1,011.50 in respect of costs estimated to be incurred in 2017/2018 and the second for £25.94 in respect of costs estimated to be incurred in 2018/2019. The first estimate refers back to the notification issued on 6 March 2017 that complied with paragraph 2(1) of part 1 of the third schedule to the lease and was saved by paragraph 59 the previous decision. The second estimate related to the forthcoming year commencing 1 April 2018 and was not given after the last quarter day of that year.
The notices issued on 4 May 2012 complied with Section 20B (2) of the 1985 Act. 71. We set out below our chronology of the consultation notices and section 20B notices for the first major works
Date Action Bundle page number 27 June 2007 [NAME] issue intention notice for refurbishment works F1 31 July 2009 [NAME] issue proposal notice for refurbishment works. On the basis of the winning tender (£1,679,489.00) [NAME] estimate rechargeable block costs of £489,026.44 and a service charge of £15,109.62 F42 22 March 2010 Work commences Ms [NAME] 28 March 2011 [NAME] issue combined proposal and section 20B notice for additional fire risk works at estimated cost of £29,150 per block E193 1 April 2011 Work ends Ms [NAME] 1 August 2011 Issue of Final Account G55 – G80 1 September 2011 Issue of 10th payment certificate putting costs incurred to date at £1,733,506.13 E216 16 March 2012 [NAME] issue section 20B notice covering both refurbishment works and the fire risk works recording that “The quoted estimated costs have now been incurred …… and the contract sum currently stands at £1,733,506.12”. F99 4 May 2012 [NAME] issue section 20B notice covering both refurbishment works and the fire risk works recording that “costs have now been incurred ….and the contract sum is predicted to come in at £1,970,285,000” with a revised service charge estimate of £14,131.70. E198 26 June 2012 Issue of 12th and final payment certificate putting costs incurred to date at £1,777,955.02 E217, E218 28 February 2014 Issue of Final Account calculation sheet G2 - G4
72. As explained above, [NAME] conceded that costs incurred before 4 November 2010 were not recoverable because they were caught by section 20B, and it had written off service charges of £6,636.58 leaving, on our calculation, a balance due of £6,248.30. Although not expressly conceded by Mr [NAME], the logical consequence of the first concession is that the 20B notice issued on 16 March 2012 was invalid.
73. That apart, Mr [NAME] case was that the section 20B notices issued on 4 May 2012 was invalid because it recorded not the costs actually incurred but costs estimated to have been incurred. In support of that argument Mr [NAME] relied on Brent London Borough Council v [COMPANY] (2011) 1WLR3014, a decision that is not without its critics.
74. Mr [NAME] relied on the wording of the Section 20B notice quoted in the above table in asserting that it recorded estimated rather than actual costs. Mr [NAME] evidence in this respect was however unequivocal and we accept it. He told us that [NAME] maintained a chronological table of all payments made in connection with each major works project. The cost figures shown in the 20B notice were taken from the schedule for the first major works project and record the payments actually made at the date of the notice. As Mr [NAME] pointed out, the schedule includes not only payments made to the contractors and authorised by the payment certificates issued by the supervising surveyor but also payments in respect of professional fees and the like.
75. We do not disagree with Mr [NAME] observation that there might be adjustments to these payments either authorised by variation orders or on the issue of the final account, in particular if costs are adjusted or disallowed so that the recorded sum might not ultimately be the costs actually incurred. Nevertheless, we are satisfied and find that the 20B notices record the payments actually made by [NAME] in respect of the first major works project on the date that they were issued. That is sufficient to comply with section 20B(2) and is consistent with the [NAME] decision. That interpretation is also consistent with the notice itself that refer to costs that “have now been incurred”. In respect of both major works [NAME] did comply with the statutory consultation requirements imposed under section 20 of the 1985 Act 76. Our chronology of consultation notices and section 20B notices for the first major works project is set out above. We set out below our chronology of consultation notices and section 20B notices for the second major works project: - Date Action Bundle page number 1 October 2015 [NAME] ballot residents on a proposal for new door entry system saying that it “seeks to obtain over 50% approval from residents” F138 18 October 2015 Mr [NAME] objects F139 20 July 2016 [NAME] issue intention notice for a door entry system F143 6 March 2017 [NAME] issue proposal notice for a door entry system. On the basis of the winning tender (£88,399.00) [NAME] estimates a rechargeable block cost of £13,594.52 and an estimated service charge of £1,037.43. The notice records the ballot results for [NAME] and not [NAME]. E145, F152 28 July 2017 [NAME] issue section 20B notice which records that it “has been invoiced for £4,951.00 as of June 2017” E199
14 September 2018 [NAME] issue 20B notice, which records that it “has been invoiced for £112,373.00 as of July 2018” E201
77. As far as the first major works project was concerned, Mr [NAME] asserted two breaches of the consultation requirements to be found in part 2 of schedule 4 of the Service Charges (Consultation Requirements) (England) Regulations 2003. Firstly, he said that the intention notice did not contain an accurate description of the proposed works, in that a number of items such as brickwork repairs to the boundary walls had been omitted. In the Scott Schedule Mr [NAME] identified seven items of works that were completed but omitted from the description in the intention notice.
78. Secondly, he asserted that the proposal notice failed to contain an adequate statement summarising the [NAME]’ observations in response to the intention notices.
79. Paragraph 8(a) of part 2 provides that the intention notice shall “describe, in general terms, the work proposed to be carried out or specify the place and hours at which a description of the proposed works may be inspected”.
80. The intention notice [F1] lists seven items including concrete repairs, integral window and front door renewal and brickwork repairs. The notice makes it clear that [NAME] is contemplating the refurbishment of [NAME]. Furthermore, the notice informs the reader, on page 2, that “The detailed schedule of works can be inspected at the Home Ownership Unit, [ADDRESS], Monday to Friday between the hours 10am and 4pm”.
81. We are satisfied and find as a fact that the intention notice complies with the consultation requirements in that it includes both a general description of the works and specifies a place and time where a more detailed description of the works maybe inspected.
82. Paragraph 11(5) of schedule 2 provides that where the landlord has received observations in response to the intention notice the paragraph (b) statement shall contain “a summary of the observations and his response to them”. Mr [NAME] observations are contained in his 4-page letter of 6 August 2007 [F36], which provoked extensive correspondence and a number of complaints [H171-H224]. It is apparent that observations were made by other leaseholders although copies of those observations do not seem to be included in the hearing bundles.
83. The paragraph (b) statement (referred to by [NAME] as the proposal notice) [F42] recorded only one observation: “Is this refurbishment contract a result of works not carried out in the annual service charge although leaseholders have been charged repairs”. This was followed by a two-paragraph response the gist of which appears to be that [NAME] has the option of remedying disrepair by either annual repairs or by a large-scale contract although it has to be said that the response would do justice to a politician.
84. [NAME]’s explanation was that: “While this did not detail every point of each observation, as these were seen to be too general and/or not related to
the proposed works, the summary did summarise a point of a particular concern which was relevant”.
85. We accept that where a landlord receives numerous observations Parliament cannot have intended that the paragraph (b) statement should record each and every one of them. Paragraph 11(5)(b)(ii) simply requires “a summary”. Again, with some hesitation we accept Mr [NAME] explanation and we find that the proposal notice did include a broad summary of the observations and [NAME]’s response. We are encouraged in that conclusion by the very detailed responses given to Mr [NAME] numerous observations and complaints: certainly, he cannot be said to have been prejudiced by the absence of a more detailed summary of his observations and [NAME]’s response to them.
86. Turning to the second major works project, Mr [NAME] case was based on [NAME]’s response to the ballot of residents. He pointed out that [NAME]’s decision to install a door entry system only for flats 1, 2, 6-21 was not consistent with its declared intention of only installing a door entry system in blocks in which the proposal was supported by a majority of the residents. It will be recalled that in [NAME] as a whole a majority (as defined by [NAME]) did not support the proposal.
87. However, the ballot was informal and outwith the statutory consultation process. Even though Mr [NAME] analysis was correct there was nevertheless a logic to [NAME]’s decision, such that it could not be said to be perverse or unreasonable. Consequently, and for each of these reasons we do not consider that [NAME]’s decision nullifies the consultation process or of itself renders the cost unrecoverable through the service charge. In respect of the installation of the fire breaks in the roof void, [NAME] did comply with the statutory consultation requirements imposed under section 20 of the 1985 Act 88. The background to this issue is set out in paragraph 19 above. The issue is whether the installation of the fire breaks and the first major works formed part of the same set of works. If they did no further consultation was required.
89. [NAME] had not helped its case by issuing what purported to be both a proposal notice and a section 20B notice [E193] when the installation had in all probability been completed or at least was on the verge of completion. The implication is that [NAME] thought that the installation was a separate set of works, but if that is what it thought the correct course of action would have been to make an urgent [NAME] to the tribunal for dispensation. It is regrettable that this misconceived notice led leaseholders to believe that their views were being invited when the work had effectively been completed. It was nevertheless of no effect.
90. It is certainly the case that this additional work was only identified as the first major works progressed. It is self-evident that it was not included either within
the original specification or within the summary of works contained within the intention notice.
91. Nevertheless, we consider that the following factors indicate that installation of the fire breaks and the first major works formed part of the same set of works:-
a. The installation was authorised by varying the first major works contract so that all the work including the installation was completed under one contract; and
b. The installation was carried out at the same time, to the same premises and using infrastructure such as scaffolding already in place; and
c. It was apparent from the outset that [NAME] was proposing the refurbishment of [NAME] and within that context the installation of fire breaks, required to meet current building regulations, was similar in character to that originally specified.
92. Consequently, we find that [NAME] did comply with the statutory consultation requirements imposed under section 20 of the 1985 Act
93. Although it forms no part of our reasoning, we add as an aside that following the Supreme Court decision in [COMPANY] v Benson [2013] UKSC 14 Mr [NAME] would face an uphill struggle in successfully opposing a dispensation [NAME] that Mr [NAME] indicated would follow an adverse finding on this issue.
The disputed itemised costs incurred in the first major works were reasonably incurred and were recoverable under the terms of the lease 94. We start by [NAME] four observations that are relevant to our decisions under this and the following section.
95. The first is that there is a well-established principle, which predates the 1985 Act, that reasonable cost does not equate to lowest cost. In [NAME] v [NAME] [2017]1 W.L.R.2817 Lewis LJ put it another way when he said: -
“…. it must always be born in mind that where the landlord is faced with a choice between different methods dealing with the problem in the physical fabric of a building (where the problem arises out of design defect or not) there may be many outcomes each of which is reasonable. I agree with [counsel] that the tribunal should not simply impose its own decision. If the landlord has chosen a course of action which leads to a reasonable outcome the costs of pursuing that course of action will have been reasonably incurred, even if there was another cheaper option which was also reasonable”.
96. The second relates to the replacement of obsolete, worn or damaged items by modern equivalents produced to current but superior standards. In general terms such replacement will be regarded as a repair rather than an improvement.
97. The third relates to the terms of the lease. Mr [NAME] case was largely based on his assumption that with two exceptions the lease permitted only the recovery of the cost of repairs. That assumption resulted from paragraph 7 (1) of Part I of the Third Schedule to the lease that refers back to the lessor’s covenants in clause 4 (2) to (4) of the lease, which in general terms obliges the lessor to keep [NAME] in repair and to redecorate the exterior and common parts as often as may be reasonably necessary. The two exceptions are contained in paragraph 7(9) and allow the recovery of the cost of installing “by way of improvement” double glazed windows and “an entry-phone system”.
98. However, that interpretation is unduly narrow. Clause 4(2) of the lease requires the lessor not just to repair but “to make good any defect affecting that structure”. Furthermore Paragraph 7(6) of Part I of the Third Schedule also allows the recovery of the cost of “The maintenance and management of the building and the estate…”. The term permits the recovery of costs of work that might be neither a repair nor an improvement.
99. The fourth relates to the evidence of Mr [NAME] expert, [NAME]. He acknowledged that his report had been prepared for Mr [NAME] and it did not contain an expert witness declaration, although he was not alone in that omission. However, from his answers to Mr [NAME] questions, it became apparent that he did not understand that his first duty was to the tribunal rather than, as he put it, “to the parties”. This undermined our confidence in his evidence, such that we did not feel able to give it the weight that we would normally accord to an expert.
100. With those observations in mind, we now turn briefly to the disputed costs itemised in the Scott Schedule other than those that had not in any event been recharged to the leaseholders.
New front Doors. 101. It seems that this cost accounted for about one-third of the total cost. [NAME] was built about 90 years ago. Over time many of the residents have either replaced or altered the front doors of their flats including the windows above. Many but by no means all the front doors were in disrepair and did not comply with current fire and security regulations. [NAME] decided to replace all the front doors. Mr [NAME] considered that the cost was excessive. In doing so he relied on the evidence of Mr [NAME].
102. Although Mr [NAME] now refers to the cost as “excessive” and the replacement with new hardwood windows as an improvement we note that in his initial report of 10 May 2010 [F66] he observed that “There is a valid argument for complete replacement with a high performance alternative”. This brings the cost within [NAME] and having regard to each and all of our observations the cost is recoverable.
Anti-graffiti paint 103. Mr [NAME] objected to the additional cost of anti-graffiti paint on the ground that it was an improvement although he did not quantify the additional cost, if there was one, that he felt should be disallowed.
104. Over the last few decades, graffiti has become an increasing problem. The decision to use anti-graffiti paint was reasonable. The use was both within [NAME] and was no more than the replacement of a worn part with a modern equivalent. Consequently, and for each of these reasons the cost was recoverable.
Electrical works 105. The thrust of Mr [NAME] case was that the electrical work was largely unnecessary and as such was an improvement. Mr [NAME] relied on the 2006 Decent Homes Report and a survey or summary [F33-35] that seems to have been derived from it. In that survey the Landlord’s Electrical Installation is said to be “satisfactory”. Mr [NAME] also relied on the evidence of Mr [NAME] that was at best tenuous. He had inspected the estate in May 2010 and the first page of his report [F60-71] emphasises that he did not inspect those parts “that are unexposed or inaccessible or free from view”. At [F65] he simply states that “previously the electrical trunking, fittings and presumably the wiring was replaced”. He then continues “All this work is now the subject of replacement which, if necessary, has in our opinion led to unnecessary expense as this should have been undertaken concurrently”.
106. Sadly, all those responsible for supervising the work have since died and [NAME] had to rely on the evidence of experts who had inspected [NAME] long after the completion of the work and had reviewed the available paper work. Nevertheless, we found the evidence of Mr [NAME] compelling. The 17th edition of the relevant electrical regulations was introduced in January 2008 after the Decent Homes Report. We accept his conclusion that the work would have been necessary “to bring the existing installations to the required level in the 17th edition otherwise utility providers ……may refuse to reenergise the premises for failing to meet the standards”.
107. Having regard to our observations above we are satisfied that the work amounted to a repair and that the costs was recoverable.
Lightning conductors 108. There were a number of surprising aspects to Mr [NAME] case but this was perhaps the most surprising. One of his observations in response to the intention notice was “I am shocked to read that there are no lightning conductors, nor do they seem to be any planned. They must be installed immediately”. [NAME] installed the requested lightning conductors, yet Mr
[NAME] now objects to contributing towards the cost on the ground that they are an improvement.
109. The installation of the conductors was both [NAME] good a defect in [NAME] and also formed part of its proper maintenance. Although the installation was not a repair as such it was within the contemplation of both clause 4(2) and also paragraph 7(6) of Part I of the Third Schedule. Consequently, the cost was recoverable.
Upgrading insulation (in the roof) 110. Again, Mr [NAME] argument was that the upgrading of the roof insulation amounted to an improvement. Mr [NAME] evidence, which we accept, was that the upgraded insulation was required by current Building Regulations.
111. As observed above the replacement of an obsolete component by a modern equivalent complying with current regulations is a repair rather than an improvement. In the alternative the upgrade made good a defect in [NAME] and was required for its proper maintenance. Consequently, the cost was recoverable.
Cleaning 112. This related to the steam cleaning of the chimney stacks. Mr [NAME] accepted that they were discoloured by pollution but said that they could have been left. Mr [NAME] considered that the work was unnecessary. Mr [NAME] evidence was that cleaning the brickwork is “an industry standard” after major repairs to remove dust and grime.
113. Cleaning was part and parcel of the project, as indeed were other items that were not in themselves repairs, such as the erection of scaffolding. As such cleaning was within the contemplation of the repairing covenant and was in any event undertaken for the maintenance of [NAME]. Consequently, the cost was recoverable.
Rainwater downpipe replacement 114. Mr [NAME] principal objection was that the pipes should have been replaced when the gutters were replaced “a few years earlier…….and would have saved on duplicated costs of scaffolding”.
115. It is not suggested that the replacement was unnecessary. Indeed, the Decent Homes Report notes that the downpipes were cast iron with some corrosion in places. It is not suggested that the guttering should not have been replaced “a few years earlier”. The case for a saving in scaffolding costs is simply not made out and we are satisfied that replacement fell within the repairing obligation and that the cost was recoverable.
Repair of damage due to neglect 116. In essence this was a counter claim by way of set-off for historic neglect. In his statement of case Mr [NAME] says that: “It is impossible for the leaseholder to quantify the effect of the failure to maintain the building on the amount of the works”.
117. Mr [NAME] has not quantified his claim and it must fail in these proceedings. Even had it been quantified we would have declined jurisdiction because in this case we consider that the claim would more appropriately be considered in the cost shifting jurisdiction of the County Court.
Works generally over-specified 118. In terms of the statutory framework, Mr [NAME] was asserting that the major works costs had not been reasonably incurred within the meaning of section 19(1) of the 1985 Act because they were over-specified. This was simply an assertion made by [NAME] for which there was no evidential support. In his statement of case Mr [NAME] put [NAME] to proof of “exactly what amount of each type of work was necessary”.
119. The work was identified in the Decent Homes Report: it was subject to the statutory consultation process: it was specified and put out to tender: it was supervised and payment was made against payment certificates issued by the supervising surveyor. In a major works projects of this type the relevant costs to be taken into account for the purpose of section 19(1) are the totality of the costs rather than the individual components of those costs.
120. In any event, in service charge cases there is a shifting burden of proof. In the first instance it was for Mr [NAME] to adduce evidence demonstrating that the work was over-specified and hence the costs unreasonably incurred. Had he adduced such evidence the burden would shift to [NAME]; but he had adduced none and again this aspect of his case must fail.
Electrical survey for leasehold flats 121. The cost per flat was £44.46 and was apparently applied to both tenanted and leasehold flats alike. Mr [NAME] relied on the evidence of Mr [NAME] who suggested that some but not necessarily all leaseholders were subsidising the rental tenants “where electrical work was not proposed within leasehold properties”. He said that an adjustment should be made although he offered no suggestion as to what that adjustment should be.
122. We have already observed that Mr [NAME] himself did not give evidence and we do not know if any electrical work was proposed to his flat. We again prefer the evidence of Mr [NAME] who said that it was “the industry standard” for utility providers to require Electrical Installation Condition Reports for both tenanted and leasehold flats, showing the electrical circuits and installations, before reconnecting to the electrical network. We are satisfied and find that it
is more likely than not that surveys were completed for both tenanted and leasehold flats and that it was reasonable to apply a fixed price to the cost of those surveys even if the surveys of some flats were more extensive than others. The disputed costs incurred as responsive repairs in 2016/2017 were reasonably incurred and were recoverable under the terms of the lease Repairs to flat roof 123. During the year responsive repairs were carried out to the flat roof on three occasions. Mr [NAME] case was that the roof was resurfaced as part of the first major works project: the work should have been covered by a guarantee and hence the cost was not reasonably incurred. Although he did not put it in these terms, his case was actually one of set-off based on [NAME]’s asserted failure either to obtain a guarantee for the roof work or if a guarantee existed to enforce it.
124. For [NAME] the evidence of Ms [NAME] and Ms [NAME] was consistent. Ms [NAME] said that although all the first major works were covered by a defects liability period, only the UPVC windows had the benefit of a guarantee. Ms [NAME] said that [NAME] maintained a schedule of warranties and guarantees. She consulted that schedule and there were no warranties or guarantees in place for the roof.
125. Ms [NAME] evidence was that only a section of the roof was recovered and that it would not be usual to obtain a guarantee for what was effectively a patch repair. The bill of quantities at [G33 -G35] records the roof work. The roof was not replaced but rather sections of the roof were repaired and re-asphalted. This supports Ms [NAME] evidence and we agree with her that a guarantee extending beyond the defects liability period would not normally be issued for limited work of that type. Consequently, we are satisfied and find that the cost of the repair work was reasonably incurred.
Estate charges marked as responsive repairs 126. A cross-over from the estate road to the public highway had been repaired. Mr [NAME] did not suggest that the repairs were unnecessary or that the cost, which worked out at about £5 per flat, was unreasonable. His case was based on Mr [NAME] evidence when he said that he “thought” that the highway authority would have been responsible for the work although he was unable to say whether the estate road including the cross-over was adopted.
127. Ms [NAME] evidence was more certain. Although she did not know if the cross-over formed part of the public highway she said that if the highway authority had undertaken the work it would have passed on the cost in any event. We accept her evidence. The work was undertaken for the proper management of the estate and the cost was recoverable under paragraph 7(6) of Part I of the Third Schedule to the lease.
Further directions 128. By 27 November 2019 the Mr [NAME] must send to [NAME]: - • a statement in support of the cost limitation applications containing a statement of truth; and • any legal submissions with copy authorities; and • copies of any additional documents on which he intends to rely; and 129. By 6 December 2019 [NAME] must send to Mr [NAME]: -
• a statement in reply containing a statement of truth; and
• any legal submissions with copy authorities; and
• copies of any additional documents on which it intends to rely.
130. Mr [NAME] is responsible for preparing the bundle of relevant documents (in a file, indexed at the front and numbered on each page). He must by 13 December 2019 send one copy to [NAME] and three copies to the tribunal.
131. Only those documents sent in the bundle are likely to be before the tribunal at the full hearing and parties should not send documents “piecemeal” to the case officer.
132. The bundle must contain copies of: • the applications with relevant supporting documents • this decision • Mr [NAME] statement in support • [NAME]’s statement in reply • the parties’ submissions and copy authorities • any other documents upon which either party reasonably wishes to rely.
133. Any request for an oral hearing should be made in writing and copied to the other party by 20 December 2019.
134. If neither party requests an oral hearing the tribunal will determine the matter during the week commencing 6 January 2020 on the basis of the document bundles.
135. If a hearing is requested it shall take place at 10 [ADDRESS] [POSTCODE] from 1.30 pm on 8 January 2020 with a time estimate of
one hour and the party requesting an oral hearing shall bring an additional copy of the document bundle to the hearing.
Name: [NAME]: 19 November 2019
Rights of appeal
By rule 36(2) of the Tribunal Procedure (First-tier Tribunal) (Property Chamber) Rules 2013, the tribunal is required to notify the parties about any right of appeal they may have. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber), then a written [NAME] for permission must be made to the First-tier Tribunal at the regional office which has been dealing with the case. The [NAME] for permission to appeal must arrive at the regional office within 28 days after the tribunal sends written reasons for the decision to the [NAME]. If the [NAME] is not made within the 28 day time limit, such [NAME] must include a request for an extension of time and the reason for not complying with the 28 day time limit; the tribunal will then look at such reason(s) and decide whether to allow the [NAME] for permission to appeal to proceed, despite not being within the time limit. The [NAME] for permission to appeal must identify the decision of the tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal and state the result the party [NAME] the [NAME] is seeking. If the tribunal refuses to grant permission to appeal, a further [NAME] for permission may be made to the Upper Tribunal (Lands Chamber).
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charge for Heating and Hot Water Reasonab…
- First-tier Tribunal (Property Chamber) Tenant Found Liable for Service Charges in First-tier Tribunal Ruling
- First-tier Tribunal (Property Chamber) Tenant's Service Charge Claim Rejected by First-tier Tribunal
- First-tier Tribunal (Property Chamber) Application for Costs Dismissed Due to Misconceived Proceedings
- First-tier Tribunal (Property Chamber) First-tier Tribunal Denies Claimant's Application for Costs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Payable Despite Technical Issues
- First-tier Tribunal (Property Chamber) Tenant's Application for Rent Increase Rejected Due to Lack of Jurisdiction
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Payable
- First-tier Tribunal (Property Chamber) Tenant Loses Challenge to Service Charges in First-tier Tribunal
- First-tier Tribunal (Property Chamber) First-tier Tribunal Upholds 25% Service Charge Apportionment
- First-tier Tribunal (Property Chamber) Tenant's Application Rejected for Missing Rent Increase Notice
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Against Recovery of Legal Costs Through Service C…
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- None of the provided cases show a winning pattern for the claimant.
❌ Tends to be rejected
- The claimant's application was dismissed because the service charges were deemed reasonable and compliant with lease provisions.
- The claimant failed to provide the required notice before bringing an application regarding service charges.
- The claimant did not meet the necessary notice requirements for rent increases, leading to dismissal.
- Applications were dismissed when the underlying proceedings were considered misconceived or open to being struck out.
- Claims were unsuccessful when no specific costs had been levied, preventing a determination on the reasonableness of service charges and costs.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The tribunal ruled that service charges for major works and responsive repairs were legal under lease agreements.
Who was involved?
The case involved a tenant and a local authority.
How did the court decide, and why?
The court decided that the service charges were legal because they were reasonably incurred and met statutory consultation requirements.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 sections 27A and 20B, and the Commonhold and Leasehold Reform Act 2002 section 115A were applied.
What was the argument that mattered most?
The argument that mattered most was that the service charges were reasonably incurred and met statutory consultation requirements.
Was the decision for or against the person who brought the case?
The decision was against the person who brought the case.
What does this mean for someone in a similar situation?
Someone in a similar situation should ensure that service charges meet statutory requirements and are reasonably incurred.
What evidence or documents mattered?
Evidence and documents regarding the statutory consultation process and the reasonableness of the charges were crucial.
Can a decision like this be appealed?
Yes, decisions like this can be appealed to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
Yes, it is recommended to seek advice from a qualified solicitor for cases involving service charges.
