VadeLab
DismissedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Dismisses Claimant's Breach of Covenant Claim Against Tenants

Case No.

📌 In brief

In a recent case, a landlord claimed that tenants had breached certain covenants in their lease by allowing balconies to fall into disrepair. However, the First-tier Tribunal ruled that the tenants were not responsible for these repairs, as they fell within the landlord's repairing responsibilities.

⚖️ Legal holding

A tenant is not liable for breaches of covenant that fall within the landlord's repairing responsibilities.

Topics

balcony repairsbreach of covenant

Provisions

Commonhold and Leasehold Reform Act 2002 s.168(4)

📖 Technical summary

The Tribunal dismissed the claimant's application alleging breach of covenant by the respondents.

📜 Headnote Official document

The claimant, the registered owner of the freehold and landlord of a block of flats, applied for an order that the respondents had breached certain covenants in the lease. The Tribunal found that the respondents had not breached the covenants numbered 2(xvi) or 3(1) of the Lease for the purpose of section 168(4) of the Commonhold and Leasehold Reform Act 2002. The decision was made by Tribunal Judge H Lederman on 12 September 2025.

📚 Full judgment Official document

OUTCOME: Dismissed

1

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

Case Reference : HAV/00HR/LBC/2025/0603

Property : Flat 11 [NAME], 442 [APPELLANT],

Ferndown, Dorset, [POSTCODE]

(“the property”) Applicant: [redacted] : [COUNSEL]

Respondent : [redacted] : None;

Type of Application : Application for an order that a breach of

covenant has occurred – Section 168(4) of the Commonhold and Leasehold Reform Act 2002 Tribunal member : Tribunal Judge [NAME]

Tribunal member [NAME]

Tribunal member [NAME] of Hearing : 8 July 2025

Date of Decision : 12 September 2025

DECISION AND REASONS

© CROWN COPYRIGHT

2

DECISION

The Respondent has not breached the covenants numbered 2(xvi) or 3(1) of the Lease dated 24th November 2008 (incorporating an earlier Lease of the property dated 9th November 1981) (“the Lease”) for the purpose of section 168(4) of the Commonhold and Leasehold Reform Act 2002.

REASONS 1. The Applicant is the registered owner of the freehold and landlord of a block of 12 flats and development known as [NAME], 442 [APPELLANT], Ferndown Dorset. All of the flats are held on the terms of materially identical leases. At the hearing the Applicant was represented by [APPELLANT] who was described as a managing agent and also appeared to be the [NAME] of Flat 5 [NAME].

2. The Respondents are two of the three leaseholders of the property and have been resident at the property a second floor flat for some years now. The third [NAME] [NAME] was not represented and was not joined as a party to this application. The Second Respondent Mrs. [RESPONDENT] gave written authority for the First Respondent Mr. [RESPONDENT] to represent her. The Lease was granted for a term of 999 years from the 1st January 1980.

3. The Applicant alleges the Respondents have breached covenant at clause 3(1) of the Lease which (in summary) prohibits a [NAME] from doing or permitting or suffering to be done “in or upon “the Demised Premises” anything which may be or become a nuisance annoyance or cause damage or inconvenience to the Lessor or the occupiers of the other flats in the Building or neighbouring owners and occupiers or whereby any insurance for the time being effected on the Building and the garages or any contents thereof may be rendered void or voidable or whereby the rate of premium may be increased”.

4. The application was received on the 19th January 2025 and the Tribunal issued directions in April 2025.

5. Mr [NAME] attended the hearing remotely from the offices of East Dorset and Purbeck Citizens Advice Bureau with the assistance of [NAME] [NAME] an adviser at that Bureau. Mr [NAME] appeared to have difficulty in hearing all of the proceedings at the hearing. The Tribunal allowed and encouraged Mr [NAME] to assist Mr [NAME] by explaining and repeating to Mr [NAME] the gist of what had been said. The Tribunal ensured that there were appropriate breaks in the proceedings at the hearing to enable that to occur. Fortunately Mr [NAME] objections had been helpfully summarised in a letter prepared by Mr [NAME] on 10th June 2025 at pages 70-72 of the hearing bundle. Ultimately the Tribunal was satisfied that Mr [NAME] had a good understanding of the issues and evidence debated at the hearing. As Mr [NAME] case had been fully set out in correspondence in the hearing bundle before the hearing, the Tribunal was confident that any difficulty he had in hearing or understanding had been fully compensated by the adjustments made in the course of the hearing.

3

6. Mr [NAME] attended the hearing at the Tribunal Centre in Havant in the company of other leaseholders including Mrs [APPELLANT] of Flat 9.

7. One part of the Applicant’s case is that Mr and Mrs [APPELLANT] have allowed the balcony of the property to fall into such a state of disrepair over a 10 year period, which has led to water damage being caused to the balcony of flat 9 and internal water damage to flat 7 at [NAME]. Mr [NAME] also contended that Mr [APPELLANT] in his capacity as director of the Applicant owed a “duty of care” or a duty under clause 3(1) of the Lease to direct or require managing agents to carry out certain works of repair to parts of the development.

8. The Tribunal was referred to a survey report of the south elevation balcony areas and guttering arrangements prepared by [NAME], a building surveyor following an inspection of the development on 16th August 2024. The report was accompanied by 23 (unnumbered) coloured photographs, mainly of the exterior, showing various degrees of disrepair and deterioration.

9. The application also refers to paragraph (xvi) of the lease of the property. Mr [NAME] confirmed this was a reference to the [NAME]’s covenant in clause 2(xvi) of the Lease to yield up the demised premises with the lessor’s fixtures and additions thereto at the expiration or sooner determination of the term of the Lease in good and substantial repair order and condition. The Tribunal determined at an early stage that the allegation of breach this covenant did not add anything to the alleged breach of clause 3(1) of the Lease. As the expiry of the Lease was hundreds of years away, this allegation could safely be left to one side and as having no substance.

10. Mr. [NAME] said that he was a specialist roofing contractor by trade. He prepared a detailed letter of 18th May 2025 at pages 73 – 81 of the hearing bundle. That letter explains some of the history and his experience as a roofing contractor. It also explains his belief that disrepair of the balcony to the property has led to water penetrating the left hand cavity wall of the balcony of Flat 9 and into internal parts of Flat 7.

11. Mr. [NAME] said in his letter and in his explanation at the hearing he believed water damage had been caused by the serious neglect of the leaseholders of the property in not informing the managing agents NMC. It was also part of Mr. [APPELLANT] explanation and the Applicant’s case that Mr [APPELLANT] as a director of the Applicant had “neglected” his duties by “suppressing” repair work or failing to instruct works of repair. Mr. [NAME] also alleged that Mr [NAME] inhibited or delayed repair works by failing to pay service charge invoices raised by the Applicant.

12. The Tribunal explained its provisional view that a covenant of the kind in clause 3(1) of the Lease was common in residential leases and was usually directed to positive acts, or omissions “done in or upon the Demised Premises”. The emphasised words are usually taken to refer to activities or omissions related to the use or occupation of the property. The Tribunal indicated that words “nuisance annoyance or cause damage or inconvenience” were usually directed towards activities or use of leasehold premises (here the property) permitted or suffered by the [NAME] which interfered with the use or enjoyment of nearby or adjacent leasehold properties. The Tribunal invited Mr. [APPELLANT] and the Applicant to draw attention to any acts or omissions by the Respondents in their capacity as leaseholders which could be argued to fall within the activities or omissions prohibited by this clause.

13. The Tribunal bears in mind the guidance in the Supreme Court from decisions such as Arnold v Britton [2015] A.C. 1619 that interpretation of a contract such as a lease involves identifying what the parties had meant through the eyes of a reasonable reader. It has been stressed that this is a single exercise, which considers

4

the practical consequences of possible readings:

"This unitary exercise involves an iterative process by which each suggested interpretation is checked against the provisions of the contract and its commercial consequences are investigated." ([NAME] v [COMPANY] [2017] A.C. 1173

14. It would be inherently unlikely that a clause such as 3(1) would embrace a duty to carry out repairs or organise repairs when such a duty was also required of individual [NAME] by covenants in other parts of the Lease.

15. The Tribunal noted and drew the Applicant's attention to the fact that the upper horizontal surface of the balcony exclusively serving the flat was demised to each flat by clause 1(viii) of the Lease, on the assumption that all the leases of the development were in a similar form. In other words, some of the repairing liability for those parts of the balcony might not fall within the Applicant’s repairing responsibility as landlord within clause 4(c) of each lease. This point was made on behalf of Mr [NAME] in a letter from the Citizen’s Advice Bureau in a slightly different way.

16. Mr [COUNSEL] and his representative made the point that most of the balcony falls within the repairing responsibility of the Applicant as a reserved part or structural parts reserved to the landlord referred to in clause 1 of the Lease. In other words, the responsibility under the Lease for repairs to the balcony primarily lay with the Applicant and could not fall within the terms of clause 3(1) which referred to acts or omissions done in or on the demised premises.

17. Mr. [APPELLANT] and the Applicant also complained the Respondent had failed to satisfy a Court order or judgement in respect of monies owed under the Lease as service charges. They drew attention to the fact that a warrant was issued against Mr [NAME] to enforce a judgment on the 14th April 2025. They also referred to the fact that Mr [NAME] had entered into a “Breathing space” arrangement in respect of a debt of £3540 owed to the Applicant referred to at pages 114-115 of the hearing bundle. It was explained to the Applicant and Mr. [APPELLANT] that the application under section 168 of the 2002 Act could not deal with service charges as this was outside the scope of that section .

18. After a prolonged exchange between the Tribunal and Mr. [NAME] and other leaseholders attending on behalf of the Applicant, the Applicant was unable to identify any act or omission on the part of the respondents which might have fallen within the scope of clause 3(1) of the Lease.

19. This application is dismissed.

This has been a remote hearing in part, and partly face to face to which none of the parties objected and was particularly appropriate to the First Respondent’s circumstances and health. The form of remote hearing was video. All the issues could be determined in a remote hearing. The documents that the Tribunal was referred   to are in a bundle of 115 pages

[NAME] Tribunal Judge

12th September 2025

5

RIGHTS OF APPEAL 1. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber) then a written application for permission must be made to the First-tier Tribunal at the Regional office which has been dealing with the case.

2. The application for permission to appeal must arrive at the Regional office within 28 days after the Tribunal sends written reasons for the decision to the person making the application.

3. If the application is not made within the 28 day time limit, such application must include a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed despite not being within the time limit.

4. The application for permission to appeal must identify the decision of the Tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal, and state the result the party making the application is seeking.

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The tenant was not responsible for repairs to the balcony because most of it fell under the landlord's repairing responsibility.
  • The lease covenant about nuisance or damage usually applies to how a tenant uses the property, not to repair duties.
  • The landlord could not identify any specific action or inaction by the tenants that would breach the lease clause.

❌ Tends to be rejected

  • The landlord's claim that the tenant failed to pay service charges was not relevant to this specific application.
  • The landlord's argument that the tenant, as a director, neglected duties by suppressing repair work was not accepted.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The Tribunal decided that the tenants had not breached the covenants in the lease regarding balcony repairs.

Who was involved?

The case involved a landlord claiming that tenants had breached certain covenants in their lease.

How did the court decide, and why?

The court decided that the tenants were not responsible for the repairs because they fell within the landlord's repairing responsibilities.

Which laws or rules were applied?

The Commonhold and Leasehold Reform Act 2002, specifically section 168(4), was applied.

What was the argument that mattered most?

The argument that mattered most was that the repairing responsibilities for the balconies primarily lay with the landlord.

Was the decision for or against the person who brought the case?

The decision was against the person who brought the case.

What does this mean for someone in a similar situation?

For someone in a similar situation, it means that they may not be responsible for repairs that fall within the landlord's repairing responsibilities.

What evidence or documents mattered?

Evidence included a survey report and a detailed letter explaining the history and experience of the landlord.

Can a decision like this be appealed?

Yes, a party wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must apply for permission to the First-tier Tribunal within 28 days of receiving the written reasons for the decision.

Is it worth getting a solicitor for a case like this?

It is always recommended to seek advice from a qualified solicitor for cases involving leasehold disputes.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.