First-tier Tribunal: Freeholder Bears Structural Balcony Repairs
📌 In brief
In this case, the First-tier Tribunal decided that the freeholder must repair any structural issues with a balcony, but the lessee is responsible for maintaining any decorative elements like tiles. This ruling clarifies who should pay for repairs in similar situations involving balconies.
⚖️ Legal holding
A freeholder must repair the structural elements of a balcony while a lessee maintains any decorative tiling installed on it.
📖 Technical summary
The Tribunal ruled that the lessee is not responsible for repairing defects in the balcony's structural slab, but they are responsible for maintaining the tiling.
📜 Headnote Official document
The First-tier Tribunal ruled that a freeholder is responsible for repairing structural defects in a balcony, while the lessee maintains any decorative tiling installed on it. The decision was based on the lease terms and expert evidence.
📚 Full judgment Official document
OUTCOME: Dismissed
© CROWN COPYRIGHT
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
Case Reference
:
CHI/00HN/LBC/2023/0008
Property
:
[ADDRESS], [POSTCODE]
Applicant
:
[redacted]
Representative
:
Mrs [COUNSEL] (Director)
Respondent: [redacted]
[NAME] [NAME] [COUNSEL]
:
----
Type of Application
:
Breach of Covenant S168(4) Commonhold and Leasehold Reform Act 2002
Tribunal Members
:
Mr [NAME], Regional Surveyor Mr [NAME] Mr [NAME] and place of hearing
Date of Decision
:
:
12 October 2023 at Havant Justice Centre
18 October 2023
DECISION
The Tribunal finds that the Respondents are not in breach of their repairing covenants under the lease.
2 Background
1. This is an application by the Freeholder seeking an Order under S168 (4) of the Commonhold and Leasehold Reform Act 2002 that the Respondent has breached covenants in their lease.
2. The issue is in respect of where responsibility lies for repairs to the balcony to Flat 7.
3. Judge Dobson ordered a joint expert’s report to be provided as to the condition of the balcony and this has been provided.
4. Mediation was offered but not taken up by the parties.
5. A hearing was held at Havant Justice Centre on 12 October 2023 attended by [NAME] a Director of the [COMPANY] and the Respondents [APPELLANT] and [APPELLANT]. Also in attendance were [NAME] a Director of the [COMPANY] and [NAME] an observer.
6. A number of issues of disagreement had been referred to in the bundle and at the commencement of the hearing the Tribunal said that the sole matters it would be considering were the defects identified in the expert’s report and the terms of the lease in respect of liability for repairs.
7. In accordance with directions an electronic bundle had been provided and reference to page numbers therein are indicated by [*]. Mrs [NAME] had not brought the electronic bundle but had paper copies of the relevant extracts she wished to refer to.
The Lease
8. The Second Schedule [108] defines “The Reserved Property” as including “All those the main structural parts of the buildings forming part of the Property including the roofs foundations and external parts thereof (but not the glass of the windows of the Flats nor the interior faces of such external walls as bound the Flats and garages) ……”
9. The Third Schedule [108] defines The Premises” (i.e. the flat) and excludes “the main structural parts of the building of which the said Flat and garage form part including the roofs foundations and external parts thereof but not the glass ………………”
10. “The Sixth Schedule” [110] contains the Lessee’s covenants including “3. The Lessee shall to the satisfaction in all respects of the Lessor’s Surveyor for the time being keep the Premises and all parts thereof and all fixtures and fittings therein and all additions thereto in a good substantial and tenantable state of repair decoration and condition ………………..”
3 11. “The Seventh Schedule [116] contains the Lessor’s responsibilities which include at clause 4 “keep the Reserved Property and all fixtures and fittings therein and additions thereto in a good and tenantable state of repair …………..”
The Expert’s Report
12. [NAME] expert report [87] confirms that the first and second floors have reinforced concrete floor slabs which cantilever out to form a balcony for each flat [91]. It is pertinent to note that the flat (Flat 3) occupied by the Applicant’s representative is situated directly below the flat (and therefore also the balcony) occupied by the Respondents (Flat 7).
13. In its conclusion the following findings are made;
• Flat 7’s tiled finish is in very good condition with no visible defects. Nevertheless, there is evidence the balcony is leaking in one visible location and there is evidence of similar leaks on other balconies. I cannot say for certain that the leak is ongoing, however even if it is not currently leaking, there are obvious defects in the design and installation of the balustrading stanchion bases which tells me that leaks are very likely to reoccur. • I strongly suspect evidence of leaks to other balconies I looked at are caused by the same problem. • The lead flashings on the outside edge of the balcony have inadequate overlap and this may also be a contributory factor. • The Flat 3’s living room is at risk of water penetration from Flat 7’s balcony because the cavity tray and waterproof upstand serving Flat 7’s balcony is missing / too low. However I am not aware of any issues at the moment.
The Hearing
14. Mrs [NAME] said the issue had been going on for 30 years ever since the balconies were fitted with flashing and gutters. She disagreed with the expert report in that no other balconies suffered from leaks. Mrs [NAME] said that the balcony refurbishment work conducted in 2009 cured the leak for a period of time and that the installation of stanchions in 2016 had nothing to do with the crack in the slab. The company had paid to replace tiles where damaged by the stanchion installation. The company had also funded the increase in height of the flashing where it proved to be inadequate.
15. Mrs [NAME] accepted that the slab and its repair was the responsibility of the company but as the tiles had been installed by a lessee she considered that they were the lessees’ responsibility to repair. She said that the crack had been in existence for a number of years but had been filled and was no longer visible. Mrs [COUNSEL] referred to the solicitor’s
4 advice received [34] which stated, “There is no specific provision in the lease as to who is responsible for the maintenance and repair of the balcony.”
16. In her statement dated 30/08/23 [28] Mrs [NAME] said that “All owners of their flats have since 1975 assumed the responsibility for the upkeep of their balconies” and “Other residents over the many years have all tiled their balconies and been responsible for any cost”.
17. Mrs [NAME] said that all she required was a definitive decision as to the party responsible for repairing the balconies to enable certainty to be given to existing and prospective lessees.
18. Mr [NAME] said that he agreed with the expert survey and that there was a crack in the balcony slab – he said the filled crack was visible in a photograph [98]. Previous surveys also referred to the existence of the crack. He says that the tiles are decorative and not part of the waterproofing system.
19. Mr [NAME] said that where tiles are removed to effect a repair to the underlying slab then it would be the Applicant’s responsibility to replace them. He referred to two First-tier Tribunal decisions which supported this assertion.
DECISION
20. Although this dispute appears to have generated considerable disagreement between the parties at essence it is the construction of the lease which is the determining factor in the Tribunal’s decision. The Applicant accepts that the slab is the freeholder’s responsibility to maintain and both parties agree that there is a longstanding crack in the balcony floor slab.
21. Mrs [NAME] says that the balcony tiling is the responsibility of the lessee and the Tribunal agrees as far as that relates to the choice of tiling or indeed whether any tiling is provided or the original bare slab being left unadorned.
22. The expert report refers to the tiling as being “in very good condition with no visible defects.” The Tribunal accepts this opinion and in the absence of any identified defect there are no repairs required to be undertaken by the Respondent lessee.
23. The expert report indicates that whilst there are no current leaks such an occurrence is “very likely to reoccur.” The likely cause is said to be the installation of the balustrading stanchion into the structural slab and as such the Tribunal determines that this forms part of the structure and any repair thereof is the responsibility of the Freeholder. Although the report does not refer to a crack in the slab it is agreed by both parties that one exists and that it is of long standing. Being located
5 in the slab the Tribunal confirms that any repairs undertaken will be the responsibility of the Freeholder.
24. Turning now to which party will have responsibility for reinstating the tiles following any repairs to the underlying structural slab the Tribunal is guided by but not bound by the two FtT decided cases referred to (CHI/00HP/LSC/2022/0002 and CHI/00HP/LSC/2020/0099) both of which determined that works consequential to carrying out repairs to the structure by the freeholder were the freeholder’s responsibility to reinstate.
25. The Tribunal agrees and determines that works consequential to repairs undertaken by the Applicant to satisfy its repairing obligations are the Applicant’s responsibility to make good.
26. In making its determination the Tribunal is not endorsing any particular course of repair, its responsibility being to decide whether, if any particular course of repair is undertaken, which party shall be responsible for the costs.
27. In summary therefore, the Tribunal determines that works to the structural slab forming the base of the balcony and any consequential repairs to the tiling are the responsibility of the Applicant.
28. The Tribunal finds therefore that the Respondents are not in breach of their repairing covenants under the lease.
RIGHTS OF APPEAL
1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application by email to [EMAIL] to the First-tier Tribunal at the Regional office which has been dealing with the case.
2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.
3. If the person wishing to appeal does not comply with the 28 day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.
4. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Reasonable and Payable
- First-tier Tribunal (Property Chamber) Tenant Loses Section 20C Claim to Block Legal Costs Recovery
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rejects Challenge to Parking Penalty Charges Imposed on…
- First-tier Tribunal (Property Chamber) Tribunal Rejects Claim to Enforce Lease Covenants
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rejects Tenant’s Service Charge Challenge
- First-tier Tribunal (Property Chamber) Tenant's Liability for Insurance Costs Capped at 20%
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rejects Claimant's Request for Holding Deposit Return
- First-tier Tribunal (Property Chamber) First-tier Tribunal Upholds £20,803 Penalty for Unlicenced HMO Operation
- First-tier Tribunal (Property Chamber) Emergency Prohibition Order Upheld Due to Serious Hazards
- First-tier Tribunal (Property Chamber) Tribunal Determines Payability and Reasonableness of Service Charges
- First-tier Tribunal (Property Chamber) First-tier Tribunal Denies Claimant's Cost Request in Tenancy Dispute
- First-tier Tribunal (Property Chamber) Legal Costs Incurred by Management Companies Can Be Recovered as Service Ch…
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The freeholder is responsible for maintaining the structural slab of the balcony.
- The installation of balustrading stanchions into the structural slab is part of the structure, making its repair the freeholder's responsibility.
- Repairs to the long-standing crack in the balcony slab are the freeholder's responsibility.
- The freeholder is responsible for reinstating tiles after repairing the underlying structural slab.
- The expert report found no defects in the balcony tiling, meaning no repairs were needed from the lessee.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Tribunal ruled that the freeholder must repair structural defects on a balcony, while the lessee is responsible for maintaining any decorative tiling.
Who was involved?
A freeholder and a lessee were in dispute over who should be responsible for repairing a balcony's structural issues.
How did the court decide, and why?
The Tribunal reviewed the lease terms and expert evidence to determine that structural repairs are the responsibility of the freeholder, while decorative elements like tiling are maintained by the lessee.
Which laws or rules were applied?
The decision was based on the Commonhold and Leasehold Reform Act 2002 s.168(4).
What argument mattered most?
The expert report indicating that structural repairs are the freeholder's responsibility was crucial.
Was the decision for or against the person who brought the case?
It was against the freeholder, as they were seeking to hold the lessee responsible for structural repairs.
What does this mean for someone in a similar situation?
Someone in a similar situation should consult their lease agreement and possibly seek expert advice on balcony maintenance responsibilities.
What evidence or documents mattered?
The expert report detailing the condition of the balcony was key to the decision.
Can a decision like this be appealed?
Yes, an appeal can be made within 28 days by applying for permission to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
It is advisable to seek legal advice from a qualified solicitor for such cases.
