First-tier Tribunal Grants Dispensation for Dry Rot Treatment Works
📌 In brief
The First-tier Tribunal granted permission to a landlord to bypass certain consultation requirements for treating dry rot in a building. The decision was based on the statutory conditions outlined in the Landlord and Tenant Act 1985.
⚖️ Legal holding
A landlord may seek dispensation from consultation requirements if the statutory conditions are met.
📖 What the law says
The First-tier Tribunal can grant an exemption from consultation requirements if it determines that it is reasonable to do so. Consultation requirements refer to obligations set by the Secretary of State through regulations, which may include providing details of proposed works or agreements to tenants, obtaining estimates, inviting tenants to suggest additional estimators, considering tenant feedback, and giving reasons for certain actions.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal granted dispensation from consultation requirements for dry rot treatment works.
📜 Headnote Official document
The First-tier Tribunal granted dispensation from consultation requirements for dry rot treatment works, finding that the statutory conditions for dispensation were met under the Landlord and Tenant Act 1985.
📚 Full judgment Official document
OUTCOME: Allowed
1
Case Reference
: CAM/00MD/LDC/2025/0640
HMCTS
: CVP Hearing
Property
: 1-6 [ADDRESS] [POSTCODE]
Applicant (Management Company)
: [COMPANY_1] ([NAME_2]) : [COMPANY_3]
Respondents (Leaseholders) : [NAME_4] [NAME_5] 1
[NAME_6]
[NAME_5] 2
[NAME_7]
[NAME_5] 3
[NAME_8]
[NAME_5] 4
[NAME_9]
[NAME_5] 5
[NAME_33] of Application : To dispense with the consultation
requirements referred to in Section 20 of the
Landlord and Tenant Act 1985 pursuant to
Section 20ZA
Tribunal
: Judge JR Morris
Date of Application : 29 May 2025 Date of Directions : 13 June 2025 Date of Hearing : 30 July 2025 Date of Decision : 31 July 2025
_______________________________________________
DECISION ____________________________________
© CROWN COPYRIGHT 2025
FIRST - TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
2
Decision
1. The Tribunal is satisfied that it is reasonable to dispense with compliance with all the consultation requirements of Schedule 4 Part 2 to the Service Charges (Consultation etc) (England) Regulations 2003 (SI 2003/1987) that the Applicant has not carried out with all the Leaseholders.
2. The Applicant or its Representative shall serve a copy of the Tribunal’s decision on dispensation, together with the relevant appeal rights attached, to the Leaseholders.
Reasons
The Application
3. On 29 May 2025 the Applicant applied for dispensation from the statutory consultation requirements in respect of qualifying works which are to treat dry rot and ancillary works at the Property.
4. The Property is a 1900’s detached house converted into 6 flats with brick elevations which are part rendered under a pitched tile roof.
5. Directions were issued on 13 June 2025 which stated that the Application would be determined on or after 25 July 2025 based on written representations and without an inspection, unless either party made a request for an oral hearing. [NAME_10], the Leaseholder of [NAME_5] 6, raised objections to the granting of dispensation and requested a hearing. No other objections or requests for a hearing were received.
6. The Directions required [NAME_12] to send by 23 June 2025 to each of the Respondent Leaseholders, by hand delivery or by first class post and by email, if practicable, copies of: i. The application form without the list of leaseholders’ names and addresses; ii. The Directions; iii. A clear concise description of the relevant works for which dispensation is sought; iv. an estimate of the cost of the relevant works, including any professional fees and VAT; v. Any other evidence relied upon; and To file with the tribunal confirming that this had been done and stating the date on which this was done.
7. The Tribunal agreed that delivery could be through the Leaseholders portal.
8. On 17 June 2025 [NAME_12] confirmed that this Direction had been carried out.
3
9. If the Respondent Leaseholders wished to oppose the Application the Directions required them to do so via an attached reply form by 4 July 2025. An email with attachments was received from [NAME_10] objecting to the granting of dispensation.
The Law
10. Section 20 of the Landlord and Tenant Act 1985 limits the relevant service charge contribution of tenants unless the prescribed consultation requirements have been complied with or dispensed with under section 20ZA. The requirements are set out in The Service Charges (Consultation Requirements) (England) Regulations 2003. Section 20 applies to qualifying works if the relevant costs incurred in carrying out the works exceed an amount which results in the relevant contribution of any tenant being more than £250.
11. The consultation provisions appropriate to the present case are set out in Schedule 4 Part 2 to the Service Charges (Consultation etc) (England) Regulations 2003 (SI 2003/1987) (the 2003 Regulations). The Procedure of the Regulations are summarised in Annex 2 of this Decision and Reasons.
12. Section 20ZA allows a Landlord to seek dispensation from these requirements, as set out in Annex 2 of this Decision and Reasons and this is an Application for such dispensation.
13. The terms “tenants” “lessees” and “leaseholders” are synonymous as are “landlord” and “[NAME_13].”
Hearing
14. A virtual hearing was held on 30 July 2025 attended by [NAME_14] of [COMPANY_3], the Applicant’s [NAME_2], and [NAME_10], the Leaseholder of [NAME_5] 6.
Applicant’s Case
15. The Applicant provided a bundle to the Tribunal which included: A copy of the Lease, Application to the Tribunal, Tribunal Directions, A Report from [COMPANY_16] dated 2 October 2024, A Notice of Intention dated 22 November 2024, A Statement of Estimates dated 27 March 2025, Copies of all quotations, Letter dated 17 June 2025 from [NAME_12] to Leaseholders confirming component parts of works are:
1. Treatment of Dry Rot
4
2. Works to access area and making good 3. External works to prevent recurrence [NAME_12]’s confirmation regarding compliance with Directions. These together set out the Applicant’s case.
The Lease
16. A copy of the Lease was provided between the [NAME_17], (1), the Management Company, (2), and the Leaseholder (3), for a term of 99 years from 24 June 1983. The Leaseholders are members of the Management Company. The relevant covenants of the [NAME_17] Lease are as follows:
a) Clause 2 The Lessees covenant to pay to the Management Company (b) the service charge of the amount or amounts and in manner prescribed in Clause 2 of the Third Schedule
Clause 4 The Lessee covenants with [NAME_13] and the Management Company and with the Lessees of the other flats …in manner set forth in the Fifth and Sixth Schedules
Clause 5 [NAME_13] covenant with the Lessee in manner set forth in part I of the Seventh Schedule
Clause 6 [NAME_13] covenant with the Lessee in manner set forth in part II and III of the Seventh Schedule
b) The Third Schedule 2. The Lessee shall pay “an additional sum [to the rent] (hereinafter called the “Service Charge”) payable in equal half yearly payments in advance … on the 24th day of June and the 25th Day of December in every year…in connection with the matters mentioned in Parts II and III of the Seventh Schedule hereto (hereinafter called the “outgoings”) … Provided that if a) The actual cost to the management Company of the proportion as aforesaid of the outgoings shall for any yearly period after that ending on the 24th day of June in any year be in excess of the Service charge paid by the Lessee the Lessee will immediately on receipt of a written demand for the Management Company pay to the Management Company the amount of such excess”
5
c) The Seventh Schedule Part II (Covenants by the Management Company) (a) THAT the Management Company will upon receipt of notice in writing from the Lessee specifying any wants of repair (other than and excluding any repairs for which the Lessee shall be responsible under the terms of this Lease) to the outside main walls main timbers roof gutters downpipes and drains of the Building affecting the reasonable use and enjoyment of the demised premises so soon as reasonably can be done thereafter carry out such repairs and works thereto as are necessary and proper for maintaining and keeping them in repair the Lessee giving all reasonable and proper access to the demised premises therefor as required by the Management Company or their Surveyor
Part III “The reserved property” means FIRSTLY the approaches forecourts entrance hall lifts staircases landings and passageways of the Building including the basement thereof the exterior painted or varnished. surfaces of the front doors of all the flats in the Building the refuse hoists and closets cleaners room tank rooms motor rooms baggage stores and all other parts of the Building which are or may be used or enjoyed in common by or for the benefit of the tenants and occupiers of all the flats in the Building and the house equipment or apparatus used for providing services at all of the Said flats or which are used in connection with the provision of services for the benefit of the tenants and occupiers of all the said flats and SECONDLY all those structural walls roofs foundations and balconies (if any) not specifically demised of the Building (including the external painted or varnished surfaces of window's) and all sewers drains pipes wires vents ducts and conduits (excluding those parts which are included in any demise of an individual [NAME_5]) That the Management Company will:- 1. Carry out such works of maintenance repair and replacement as are in the opinion of the Management Company necessary and proper for maintaining and keeping all the Reserved Property in tenantable repair and condition the Lessee giving all reasonable and proper access to 'the' demised premises therefor as required by the Management Company The statement by the Applicant in the Application Form is set out above, as are the terms of the Directions and confirmation of their compliance.
Application
17. The Application form identified the three elements to the qualifying works of: a) Dry Rot treatment, b) Removal & Reinstatement of Areas of [NAME_5] 2 to treat the Dry Rot, c) External brick and drainage work.
6
It was added that the Dry Rot should be remediated as soon as possible to avoid further spread.
Directions
18. The Directions have been dealt with above.
[COMPANY_16]
19. [COMPANY_16] was a survey of [NAME_5] 2 where it was noted that there was evidence of dampness and fungal attack. Dry rot spore dust was apparent, emanating either from below the floor, in the boxed in w.c. cistern or stud wall. The rain water down pipe was blocked allowing water penetration to the subfloor of [NAME_5] 2 and, in the surveyor’s opinion, was the cause of the attack.
20. It was recommended that the stud wall, and boxed in cistern should be opened up to allow for a full inspection. Sterilisation and re-instatement works should then be carried out by a suitable contractor offering an insurance backed guarantee of at least 10 years.
21. It was noted that dry rot (serpula lacrymans) may extend beyond the parameters specific in the report and works should extend to at least 1 m in all directions for the last signs of the attack.
22. It was advised that the premises should be vacated during the remediation work and the cost of dry rot treatment was likely to be £3,000.00.
23. There being 6 apartments this will result in the unit charge being more than £250.00. Therefore, the consultation procedure under section 20 of the Landlord and Tenant Act 1985 was required or dispensation granted for the full cost to be met by the service charge.
Notice of Intention
24. [NAME_12] served a Notice of Intention dated 22 November 2024 under section 20 of the Landlord and Tenant Act 1985 which stated that it was intended to carry out dry rot remediation and resultant remedial works. An invitation to comment and nominate contractors within 30 days was included, the consultation period ending on 22 December 2024. An explanation of the Consultation process was attached.
A Statement of Estimates
25. [NAME_12] served a Statement of Estimates dated 27 March 2025 under section 20 of the Landlord and Tenant Act 1985 which listed the estimates selected from all those obtained as follows: Quotations:
7
[COMPANY_18]
£9,995.00 + [NAME_19] £17, 985.00 + VAT [NAME_20] £22, 680.00 + [NAME_21]
£15,210.00 + [COMPANY_22]
£2,120.00 + [NAME_23]
£1,580.00 (+ Contingency of £1,000) + VAT
26. The Notice informed Leaseholders that there would be additional costs of: £2,000 for alternative accommodation while the works were taking place 10% contingency 10% + VAT management fees payable to [NAME_12].
27. The Notice also invited Leaseholders to inspect the estimates and to make written observations within the consultation period of 30 days ending on 27 April 2025.
Quotations
28. Copies of the selected quotations were provided to the Tribunal. The two dry rot remediation quotations included a survey report.
Correspondence to Leaseholders
29. [NAME_12] sent a letter to Leaseholders dated 17 June 2025 confirming the component parts of the works as: 1. Treatment of Dry Rot 2. Works to access area and making good 3. External works to prevent recurrence
30. At the hearing [NAME_14] said that he was confident that they had complied with the section 20 procedure. He said that the Notice of Intention had been sent to the [NAME_24] on 22 November 2024 and [NAME_10] had completed the purchase of the Lease of the [NAME_5] on 29 November 2024. However, he felt it was for the [NAME_10] owner to forward the Notice to [NAME_10] rather than the [NAME_2] to so. He acknowledged that [NAME_10] had made the Applicant and [NAME_2] aware that she had not been involved from the start of the procedure and therefore a Dispensation Application was made.
Respondent’s Case
31. [NAME_10] provided a written Statement of Case in which she said she challenged the validity and scope of the proposed dry rot works and the costs associated with them. She also said that she had concerns regarding a Director of the Applicant
8
and [NAME_12] in respect of the section 20 process. The Tribunal’s findings follow the submissions of the Respondent.
Failure to comply to the Section 20 Process
Respondent’s [NAME_10] said she had not been consulted at stage 1 of the section 20 consultation process: Notice of Intention. She said she had not received a description of the works or a rationale for them, nor was she invited to make observations or nominate contractors within the 30-day consultation period.
32. At the Hearing [NAME_10] said that, notwithstanding that she had not received the Notice of Intention, she was aware there was a problem with dry rot. [NAME_10] said she was not questioning the necessity of remedying the dry rot or that it needed to be done as soon as possible but she did wish to raise some questions about the work and its cost.
Tribunal’s Finding
33. The Tribunal found that the Notice of Intention had been sent to the [NAME_24] on 22 November 2024 and [NAME_10] had completed the purchase of the Lease of the [NAME_5] on 29 November 2024. Therefore, it was for the [NAME_10] owner to forward the Notice to her in good time to respond. It was now right that [NAME_10] should have the opportunity afforded by the Dispensation Application to address the concerns she would otherwise have raised following the Notice of Intention.
Respondent’s Submission
34. [NAME_10] said that she had not been given an opportunity to inspect all the quotations and make observations during the 30-day consultation period of stage 2 of the section 20 consultation process: Statement of Estimates.
Tribunal’s Finding
35. At the hearing the Tribunal stated that the [NAME_2] was only obliged to provide two estimates. In the present case that amounted to two estimates for each of the three stages of the work. A [NAME_2] was entitled to identify some estimates which were on the face of them not suitable, for example because of a lack of guarantee or the quote did not cover all the work. The Tribunal found that the Applicant had complied with section 20 procedure.
Respondent’s Submission
36. [NAME_10] said a particular concern was that the Leaseholders may be paying for an element of betterment. In particular, the Leaseholder, in this case of [NAME_5] 2,
9
might be able to replace a dated bathroom suite or kitchen with a new one through the Service Charge.
Tribunal’s Finding
37. Where a new suite or units are fitted it may be because a contractor advised that the old suite or units might be so damaged in removal that new items are necessary or that it is easier (therefore cheaper in labour costs) and so more cost effective to fit a new suite and units than to reinstall the old ones. In this circumstance it would be expected that a like for like would be fitted. However, if the Leaseholder requested a better suite or units, then it may be reasonable for that Leaseholder to pay an additional contribution to offset the cost to the Service Charge. It is open to Leaseholders to question the reasonableness of the cost with the [NAME_2] on receipt of the Service Charge account and if the matter cannot be resolved, an application under section 27A of the Landlord and Tenant Act 1985 may be made to determine the reasonableness of the cost and standard of work. However, these matters are not something a tribunal can consider when making a dispensation application determination.
38. The Tribunal found that the issue could be dealt with by way of an application under section 27A of the Landlord and Tenant Act 1985.
Historic Neglect
Respondent’s Submission
39. [NAME_10] said that the qualifying works were as a result of historical neglect. She referred to the [COMPANY_19] report which accompanied its quotation (copy provided) which stated: “During the course of the limited inspection, it was noted that Dry Rot (Serpula lacrymans) was affecting the ground floor flat bathroom and bedroom [referring to flat 2]. This defect appears to be due to defective rainwater goods/drainage defects”
40. [NAME_10] also referred to a RICS Level 3 Survey Report by [NAME_25] carried out in August 2024 (no copy was provided) which stated:
“It does appear that the property has been neglected for a number of years.” and
“The rainwater disposal system comprises of plastic guttering discharging into cast iron downpipes which feed into the ground and go presumably into the main drainage system. The guttering could be inspected closely and is clogged with leaves and other debris. Cast iron downpipes are rusting and require early replacement in PVC. A general overhaul of the rainwater goods is required.
10
It is important to keep guttering clear of leaves and other debris to limit damp penetration. The system should be regularly checked for leaks, and any noted should be immediately attended to.
There are areas of build-up of debris on the felt roof areas, which are also due to a lack of adequate surface water drainage, and this will result in the rapid deterioration of the central felt roof.”
41. [NAME_10] submitted that this was evidence that the Property (including the rainwater/drainage goods) have been neglected for a number of years prior to [NAME_10] acquiring [NAME_5] 6 resulting in extensive dry rot damage to [NAME_5]
2. This neglect has created significantly more expensive works than what would have originally been required if the [NAME_26] had identified, and the defect and carried out repairs earlier.
42. [NAME_10] said that it has been confirmed that the building insurance policy will not cover the dry rot damage probably because it is the result of long-term neglect and failure to maintain the property.
Tribunal’s Finding
43. The Tribunal found that if Leaseholders considered the cost of the qualifying works were made more expensive due to historic neglect of the building then this argument is for an application under section 27A of the Landlord and Tenant Act 1985 to determine the reasonableness of the cost and standard of work.
Validity of ‘supplementary demand’
Respondent’s Submission
44. [NAME_10] said that a supplementary demand to the Service Charge had been submitted during the section 20 procedure which she submitted was not in accordance with the Lease.
Tribunal’s Finding
45. At the Hearing the Tribunal found that the Lease does not allow for supplementary demands between payments based on the estimated demand. Under the Lease only the estimated service charge is:
“payable in equal half yearly payments in advance … on the 24th day of June and the 25th Day of December in every year”. However, if: “The actual cost to the management Company of the proportion as aforesaid of the outgoings shall for any yearly period after that ending on the 24th day of June in any year be in excess of the Service charge paid by the Lessee the Lessee will
11
immediately on receipt of a written demand for the Management Company pay to the Management Company the amount of such excess”
Nevertheless, Leaseholders may agree with the [COMPANY_2] outside the Lease to make a payment towards costs such as qualifying works. The benefits of doing so include: 1) that the Management Company will be in funds and so able to instruct and pay a contractor where works are pressingly needed, particularly where there are relatively few Leaseholders; and 2) the Leaseholder can pay for the specific works when the cost arises, rather than having what might be a large Service Charge excess payable immediately on receipt of a written demand after the year ending on the 24th day of June.
Conflict of Interest
Respondent’s Submission
46. [NAME_10] said that the [NAME_26], who is also a Director of the Applicant, has expressed an intention to sell the [NAME_5] 2 as soon as possible. [NAME_10] submitted that this has resulted in a conflict of interest as his only concern was getting the dry rot issues remedied, to be able to sell his property.
47. [NAME_10] mentioned other matters in her written statement which were not relevant to the qualifying works.
Tribunal’s Finding
48. The Tribunal found that the motive of a director of the Management Company was not relevant to the Application provided the works were necessary and permitted under the Lease. Any issues as to the reasonableness of the cost or the standard of work was a matter for an application under section 27A of the Landlord and Tenant Act 1985.
Exclusion from [COMPANY_1]
Respondent’s Submission
49. [NAME_10] said that despite being a shareholder of the Applicant having purchased the Lease of 6 Kingsway on 29th November 2024, she had not been given the opportunity to join the [COMPANY_27] in place for all members of the Applicant to communicate and discuss matters regarding the maintenance of the Property. Therefore, she said she has had no input, influence or say in the dry rot section 20 process.
Tribunal’s Finding
12
50. The Tribunal appreciated that [NAME_10] felt her apparent exclusion of the Leaseholder [NAME_27] group restricted her participation in the letter stages of the section 20 procedure. However, for the purposes of the Dispensation Application the Tribunal found that [NAME_10] has been able to put forward her concerns to the Tribunal.
Concerns about [COMPANY_3]
Respondent’s Submission
51. [NAME_10] said that she felt there had been a concerted effort between the Director of the Applicant and [NAME_12] to exclude her from the [NAME_28] because she wishes to proceed with obtaining quotes for roof repairs and other urgent structural issues that require attention.
Tribunal’s Finding
52. The Tribunal would encourage Leaseholders as both shareholders and officers of the Management Company to take an interest and participate in the affairs of the company. However, for the purposes of the Dispensation Application the Tribunal found that [NAME_10] not being a director of the Management Company has not prevented her from putting forward her concerns about the qualifying works to the Tribunal.
Findings
53. The Tribunal finds from the Lease that the Applicant is obliged to carry out dry rot remedial works as they affect the “reserved property” and that the cost of this work is chargeable to the Leaseholders through the Service Charge.
54. The Tribunal found based upon [COMPANY_16] of [NAME_5] 2 the qualifying works were necessary.
55. The Tribunal also found that [NAME_12] complied with the consultation procedure under Section 20 of the Landlord and Tenant Act 1985 in that:
a) A Notice of Intention was served on 22 November 2024 which invited observations and nominations of contractors to be made within 30 days i.e. by 22 December 2024; and b) A Statement of Estimates was served on 27 March 2025 which invited observations on selected contractors to be made within 30 days i.e. by 27 April 2025. Leaseholders were informed that all estimates could be inspected upon request with contact details provided.
56. The Tribunal found that the estimates from the selected contactors were thorough in their explanation.
13
57. The Tribunal found that the only outstanding stage of the procedure was the selection of the specific contractor to carry out the qualifying works.
58. The Tribunal found that although [NAME_10] had not been involved from the start of the section 20 consultation procedure the Dispensation Application had enabled her to put forward her concerns about the qualifying works to the Tribunal.
59. The Tribunal considered the issues raised by [NAME_10] which it found did not amount to a justification for the Tribunal to refuse dispensation from the consolation procedure required by section 20 of the Landlord and Tenant Act 1985. However, some of the issues raised might be arguments for an application under section 27A of the Landlord and Tenant Act 1985 to determine the reasonableness of the cost and standard of work if they could not otherwise be resolved.
60. The Tribunal found that the Leaseholders have not suffered any relevant prejudice by the failure to carry out the consultation procedure.
Determination
61. In making its decision the Tribunal had regard to the decision of the Supreme Court in [COMPANY_29] v [NAME_30] and others [2013] UKSC 14. In summary, the Supreme Court noted the following:
1) The main question for the Tribunal whether the landlord’s breach of the section 20 consultation requirements resulted in the leaseholders suffering real prejudice.
2) The financial consequence to the landlord of not granting a dispensation is not a relevant factor.
3) The nature of the landlord is not a relevant factor.
4) Dispensation should not be refused solely because the landlord seriously breached, or departed from, the consultation requirements.
5) The Tribunal has power to grant a dispensation as it thinks fit, provided that any terms are appropriate.
6) The Tribunal has power to impose a condition that the landlord pays the tenants’ reasonable costs (including surveyor and/ or legal fees) incurred in connection with the landlord’s application under section 20ZA.
7) The legal burden of proof in relation to dispensation applications is on the landlord. The factual burden of identifying some “relevant” prejudice that they would or might have suffered is on the tenants.
8) The Supreme Court considered that “relevant” prejudice should be given a narrow definition; it means whether non—compliance with the consultation requirements has led the landlord to incur costs in an unreasonable amount or to incur them in the provision of services, or in the carrying out of works, which fell below a reasonable standard, in other
14
words whether the non—compliance has in that sense caused prejudice to the tenant. 9) The more serious and/or deliberate the landlord’s failure, the more readily a Tribunal would be likely to accept that the tenants had suffered prejudice. 10) Once the tenants had shown a credible case for prejudice, the Tribunal should look to the landlord to rebut it.
62. The Tribunal is satisfied that it is reasonable to dispense with compliance with all the consultation requirements of Schedule 4 Part 2 to the Service Charges (Consultation etc) (England) Regulations 2003 (SI 2003/1987) that the Applicant has not carried out with all the Leaseholders.
63. The Leaseholders should note that this is not an application to determine the reasonableness of the works or their cost. If, when the service charge demands in respect of these works are sent out, any Leaseholder objects to the cost or the reasonableness of the work or the way it was undertaken, an application can be made to this Tribunal under section 27A of the Act. A landlord can also seek a determination as to the reasonableness of the cost of the work.
64. The Applicant shall serve a copy of the Tribunal’s decision on dispensation, together with the relevant appeal rights attached, to all Leaseholders.
Judge JR Morris
Annex 1 – Right of Appeal
1. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber) then a written application for permission must be made to the First-tier Tribunal at the Regional office which has been dealing with the case.
2. The application for permission to appeal must arrive at the Regional office within 28 days after the Tribunal sends written reasons for the decision to the person making the application.
3. If the application is not made within the 28 day time limit, such application must include a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed despite not being within the time limit.
4. The application for permission to appeal must identify the decision of the Tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal, and state the result the party making the application is seeking.
15
Annex 2 – The Law
1. Section 20 of the Landlord and Tenant Act 1985 limits the relevant service charge contribution of tenants unless the prescribed consultation requirements have been complied with or dispensed with under section 20ZA. The requirements are set out in The Service Charges (Consultation Requirements) (England) Regulations 2003. Section 20 applies to qualifying works if the relevant costs incurred in carrying out the works exceed an amount which results in the relevant contribution of any tenant being more than £250.
2. The consultation provisions appropriate to the present case are set out in Schedule 4 Part 2 to the Service Charges (Consultation etc) (England) Regulations 2003 (SI 2003/1987) (the 2003 Regulations). The Procedure of the Regulations and are summarised as being in 4 stages as follows:
A Notice of Intention to carry out qualifying works must be served on all the tenants. The Notice must describe the works and give an opportunity for tenants to view the schedule of works to be carried out and invite observations to be made and the nomination of contractors with a time limit for responding of no less than 30 days. (Referred to in the 2003 Regulations as the “relevant period” and defined in Regulation 2.)
Estimates must be obtained from contractors identified by the landlord (if these have not already been obtained) and any contractors nominated by the Tenants.
A Notice of the Landlord’s Proposals must be served on all tenants to whom an opportunity is given to view the estimates for the works to be carried out. At least two estimates must be set out in the Proposal and an invitation must be made to the tenants to make observations with a time limit of no less than 30 days. (Also referred to as the “relevant period” and defined in Regulation 2.) This is for tenants to check that the works to be carried out are permitted under the Lease, conform to the schedule of works, are appropriately guaranteed, are likely to be best value (not necessarily the cheapest) and so on.
A Notice of Works must be given if the contractor to be employed is not a nominated contractor or is not the lowest estimate submitted. The Landlord must within 21 days of entering into the contract give notice in writing to each tenant giving the reasons for awarding the contract and, where the tenants made observations, to summarise those observations and set out the Landlord’s response to them.
3. Section 20ZA allows a Landlord to seek dispensation from these requirements, as follows: –
(1) Where an application is made to a leasehold valuation tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long term agreement, the
16
tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.
(2) In section 20 and this section— "qualifying works" means works on a building or any other premises, and "qualifying long term agreement" means (subject to subsection (3)) an agreement entered into, by or on behalf of the landlord or a superior landlord, for a term of more than twelve months.
(3) The Secretary of State may by regulations provide that an agreement is not a qualifying long term agreement— if it is an agreement of a description prescribed by the regulations, or in any circumstances so prescribed.
(4) to (7)… not relevant to this application.
1
Case Reference
: CAM/00MD/LDC/2025/0640
HMCTS
: CVP Hearing
Property
: 1-6 [ADDRESS] [POSTCODE]
Applicant (Leaseholder) : [NAME_33]
Respondent (Management Company)
: [COMPANY_1] ([NAME_2]) : [COMPANY_3]
[NAME_17] Application : To dispense with the consultation
requirements referred to in Section 20 of the
Landlord and Tenant Act 1985 pursuant to
Section 20ZA
Application
: Application for Review or Permission to Appeal
Tribunal
: Judge JR Morris
Application
: 29 May 2025 Directions
: 13 June 2025 Hearing
: 30 July 2025 Decision
: 31 July 2025 Application for Permission to Appeal : 4 September 2025 Decision
: 12 September 2025 ___________________________________
DECISION ____________________________________
© CROWN COPYRIGHT 2025
2 Decision of the Tribunal
1. The Tribunal has decided not to review its Decision and refuses permission to appeal to the Upper Tribunal because it is of the opinion that there is no realistic prospect of a successful appeal against its Decision in respect of any of the Grounds of the Application.
2. In accordance with section 11 of the Tribunals, Courts and Enforcement Act 2007 and Rule 21 of the Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, the Applicant or Respondent may make further application for permission to appeal to the Upper Tribunal (Lands Chamber). Such application must be made in writing and received by the Upper Tribunal (Lands Chamber) no later than 14 days after the date on which the First-tier Tribunal sent notice of this refusal to the party applying for permission to appeal. Where possible, you should send your application for permission to appeal by email to [EMAIL], as this will enable the Upper Tribunal (Lands Chamber) to deal with it more efficiently.
3. Alternatively, the Upper Tribunal (Lands Chamber) may be contacted at: 5th [ADDRESS] [POSTCODE] (tel: 020 7612 9710).
Reason for the Decision
4. The reason for the decision is that the Tribunal had considered all the points now raised by the Applicant, when reaching its decision.
5. The Tribunal’s decision was based on the evidence before it and the Applicant has raised no legal arguments in support of the application for permission to appeal.
6. For the benefit of the parties and of the Upper Tribunal (Lands Chamber) (assuming that further application for permission to appeal is made), the Tribunal has set out its comments on the specific points raised by the Applicants in the application for permission to appeal, in the appendix attached.
Judge J R Morris
3 APPENDIX TO THE DECISION REFUSING PERMISSION TO APPEAL
For the benefit of the parties and of the Upper Tribunal (Lands Chamber), the Tribunal records below its comments on the grounds of appeal. References in square brackets are to those paragraphs in the main body of the [NAME_17] Tribunal decision.
Application and Decision
1. On 29 May 2025 the Respondent applied for dispensation from the statutory consultation requirements in respect of qualifying works which are to treat dry rot and ancillary works at the Property.
2. [NAME_10], the Leaseholder of [NAME_5] 6, raised objections to the granting of dispensation and requested a hearing. No other objections or requests for a hearing were received.
3. The Applicant raised objections which included:
4. [NAME_10] having not been consulted at stage 1 of the section 20 consultation process. The Notice of Intention had been sent to the [NAME_24] on 22 November 2024 and [NAME_10] had completed the purchase of the Lease of the [NAME_5] on 29 November 2024. The Tribunal found that the [NAME_10] owner should have forwarded the Notice to her in good time to respond. When the Applicant and [NAME_2] became aware that she had not been involved from the start of the procedure a Dispensation Application was made. The Dispensation Application afforded [NAME_10] the opportunity to address the concerns she would otherwise have raised following the Notice of Intention as all that documentation was provided in the course of the Dispensation Application procedure [30] to [36].
5. [NAME_10] said that the qualifying works were because of historical neglect and referred to [NAME_10] surveys [39]. The Tribunal found that if the cost of the qualifying works were made more expensive due to historic neglect of the building, then an application under section 27A of the Landlord and Tenant Act 1985 may be made to determine the reasonableness of the cost and standard of work [43].
6. [NAME_10] said that despite being a shareholder of the Applicant, having purchased the Lease of 6 Kingsway on 29th November 2024, she had not been given the opportunity to join the [COMPANY_27] in place for all members of the Applicant to communicate and discuss matters regarding the maintenance of the Property. Therefore, she said she has had no input, influence or say in the dry rot section 20 process. For the purposes of the Dispensation Application the Tribunal found that [NAME_10] has been able to put forward her concerns to the Tribunal.
7. Overall, the Tribunal found:
The Lease obliged the Applicant to carry out dry rot remedial works and that the cost of this work is chargeable to the Leaseholders through the Service Charge [53].
4
Based upon [COMPANY_16] of [NAME_5] 2 the qualifying works were necessary [54].
[NAME_12] complied with the consultation procedure under Section 20 of the Landlord and Tenant Act 1985 in that:
a) A Notice of Intention was served on 22 November 2024 which invited observations and nominations of contractors to be made within 30 days i.e. by 22 December 2024; and b) A Statement of Estimates was served on 27 March 2025 which invited observations on selected contractors to be made within 30 days i.e. by 27 April 2025. Leaseholders were informed that all estimates could be inspected upon request with contact details provided [55].
The estimates from the selected contractors were thorough in their explanation [56].
8. The Tribunal found that although [NAME_10] had not been involved from the start of the section 20 consultation procedure due to the [NAME_10] owner not forwarding the documents to her, the Dispensation Application had enabled her to put forward her concerns about the qualifying works to the Tribunal.
9. The Tribunal considered the issues raised by [NAME_10] which it found did not amount to a justification for the Tribunal to refuse dispensation from the consultation procedure required by section 20 of the Landlord and Tenant Act 1985. However, some of the issues raised might be arguments for an application under section 27A of the Landlord and Tenant Act 1985 to determine the reasonableness of the cost and standard of work if they could not otherwise be resolved.
Grounds of Appeal and Tribunal’s Response
The judge’s decision that the applicant adhered to the section 20 consultation process for the dry rot service charges. • The judge’s decision to grant dispensation for the dry rot works.
Grounds of Appeal
10. [NAME_10] submitted the following matters as grounds of appeal:
Ground 1
11. The Tribunal made an error of fact by not considering allowing dispensation for the cost of Alternative Accommodation and Management Fees which are not permitted to be charged under The Seventh Schedule Part II (Covenants by the Management Company) (c) of the Lease which states “the management company will only be entitled to apply the service charge towards the purposes specified in parts II and III of this schedule and generally for the purpose of the better habitation of the building”
5
Tribunal’s Response
12. This issue was not raised in written representations or orally at the hearing. The need to vacate the [NAME_5] while works take place was referred to in the surveyor’s report. The Tribunal finds that if an issue as to the liability (payability) and cost of this expense cannot be resolved it is a matter for an application under section 27A of the Landlord and Tenant Act 1985.
Ground 2
13. The Management Company failed to comply with the section 20 procedure in that when requested, the applicant refused to send any quotes for inspection for the external works and the bathroom works despite multiple requests (copies of emails were provided). As a result of the section 20 procedure not being complied with [NAME_10] submitted that she had suffered prejudice because she was unable to: 1. verify whether the external works were already paid by the [NAME_10] leaseholder who sold the property ([NAME_5] 6) in November 2024, as according to both of our conveyancers, they may have already done so; 2. verify the existing bathroom condition of [NAME_5] 2 (belonging to the director of the management company) to determine if betterment would be taking place; 3. investigate and if necessary, question the full scope of the dry rot works, and was subsequently unable to identify charges for unnecessary works; 4. verify if the contractors for the bathroom works and external were reputable, inspect all quotes to view itemised charges and if necessary, make recommendations for alternative contractors.
Tribunal’s Response
14. The section 20 procedure was followed but the assignor of the lease for the [NAME_5] failed to pass the information to [NAME_10] in recognition of which the Management Company applied for dispensation.
1. The assignor of the lease should have been able to verify whether he or she had paid for the works. At the hearing the Management Company’s Representative said that the leaseholders of flats 1 to 5 had made a payment but [NAME_10] had not. The Tribunal comments upon this in the reasons [45]. 2. [NAME_10] would not have been entitled to inspect another leaseholder’s [NAME_5]. Whether or not the works amount to the betterment of the bathroom of [NAME_5] 2 might be deduced from the fittings that might be seen to be removed and the invoices for the works. If this is an issue that cannot be resolved it is a matter for an application under section 27A of the Landlord and Tenant Act 1985.
3. At the Hearing [NAME_10] said that, notwithstanding that she had not received the Notice of Intention, she was aware there was a problem with dry rot. She said she was not questioning the necessity of remedying the dry rot or that it needed to be done as soon as possible but she did wish to raise some questions about the work and its cost [32]. The Tribunal found the survey report and the quotations comprehensive and the dispensation application proceedings afforded [NAME_10] with an opportunity to raise any questions but she did not identify any unnecessary charges or works.
6 4. The dispensation application proceedings afforded [NAME_10] an opportunity to raise any questions regarding suitability of the contractors but she did not identify any problems with those selected or submit any alternative contractors who would have been more reputable.
Ground 3
15. [NAME_10] referred to the Lease which provided her with an entitlement to become a member of the Management Company. She said she had not been given an opportunity to contact or communicate with the other freeholders since acquiring the leasehold of her property in November 2024. She also felt that the Tribunal should have had regard to what she considered to be a lack of integrity and transparency of the Management Company, its Officers and its representative.
16. [NAME_10] also referred to an objection raised by the Management Company’s Representative to her applying under section 27A of the Landlord and Tenant Act 1985 following the hearing and decision. This has already been dealt with by through the Tribunal Office.
Tribunal’s Response
17. [NAME_10] acknowledged in her application that the Tribunal could not deal with the matters regarding her membership of the company as part of the dispensation application. The Tribunal also did not consider that [NAME_10]’s opinion of the Management Company, its Officers and its representative were relevant to the dispensation application [49] to [52].
Conclusion
18. Therefore, the tribunal is of the opinion that all the points raised in the above grounds of appeal were addressed in the Decision of 31 July 2025 which: applied the law correctly, followed [COMPANY_29] v [NAME_30] and others [2013] UKSC 14, a binding decision of a higher court, provided adequate reasons for its decision, only took relevant matters and did not take irrelevant matters into account when making its decision, and followed proper procedure.
Judge J R Morris
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Fire Safety Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Landlord Permission for Urgent Lift Repairs With…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Repairs Due to Leaking B…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Allows Landlord's Application for Urgent Roof Repairs W…
- First-tier Tribunal (Property Chamber) Landlord Allowed to Skip Consultation for Urgent Flat Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Permission to Skip Consultation for Urgent Tree …
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Fire Safety Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Allows Landlord to Skip Consultation for Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Property Repairs
- First-tier Tribunal (Property Chamber) Landlord Allowed to Skip Consultation for Urgent Roof Repairs
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The Tribunal was satisfied that it was reasonable to dispense with consultation requirements.
- The landlord's failure to consult did not cause the tenants any relevant prejudice.
- The tenant was given an opportunity to raise concerns through the dispensation application.
- The legal burden of proof for dispensation is on the landlord, but the factual burden of identifying prejudice is on the tenants.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Tribunal granted dispensation from consultation requirements for dry rot treatment works.
Who was involved?
The landlord and leaseholders of a multi-flat building were involved.
How did the court decide, and why?
The court decided to grant dispensation because the statutory conditions were met, allowing the landlord to proceed with the works without full consultation.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 sections 20 and 20ZA were applied, along with the Service Charges (Consultation etc) (England) Regulations 2003.
What was the argument that mattered most?
The argument that mattered most was that the statutory conditions for dispensation were met, allowing the landlord to bypass certain consultation requirements.
Was the decision for or against the person who brought the case?
The decision was for the landlord who brought the case.
What does this mean for someone in a similar situation?
Someone in a similar situation may be able to seek dispensation from consultation requirements if they meet the statutory conditions.
What evidence or documents mattered?
Evidence and documents such as a survey report, estimates, and a notice of intention were important.
Can a decision like this be appealed?
Yes, decisions like this can be appealed to a higher court.
Is it worth getting a solicitor for a case like this?
It is always recommended to get advice from a qualified solicitor for cases involving complex legal issues.
