VadeLab
AllowedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Reduces Service Charge for Lift Works

Case No.

📌 In brief

The First-tier Tribunal reduced a service charge for lift works, determining that the costs were reasonable under the Landlord and Tenant Act 1985. The decision was made by Judge Tildesley and two other members of the Tribunal.

⚖️ Legal holding

A landlord must provide reasonable costs for necessary works under the Landlord and Tenant Act 1985.

Topics

service chargesmajor workslift refurbishment

Provisions

Section 27A Landlord and Tenant Act 1985Section 20C Landlord and Tenant Act 1985

📖 Technical summary

The Tribunal determined that a service charge of £680,430 is payable for lift works, reducing the original demand.

📜 Headnote Official document

The Tribunal determined that a service charge of £680,430 is payable for major works to refurbish two lifts, reducing the original demand of £826,725. The decision was based on the reasonableness of the costs under Section 27A of the Landlord and Tenant Act 1985.

📚 Full judgment Official document

OUTCOME: Allowed

© CROWN COPYRIGHT

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

Case Reference

:

CHI/29UN/LSC/2020/0115

Property

:

[ADDRESS] [POSTCODE]

Applicant: [redacted]

[NAME] (Flat 10H) 64 [NAME] named in the Schedule at 825-827 of the hearing bundle

Representative

:

[COUNSEL] (Flat 11B)

Respondent: [redacted]

:

[COMPANY] of [NAME]

:

Reasonableness of service charges – Section 27A Landlord and Tenant Act 1985

Tribunal Member(s)

:

Judge [NAME] [NAME] and venue of Hearing

:

20 July 2021 Hearing conducted by means of Cloud Video Platform

Date of Decision

: 25 August 2021

DECISION

2 Summary of the Decision

1. The Tribunal determines that a service charge on account in the sum of £680,430 is payable in relation to major works for the refurbishment of the two lifts. The sum is made up of £535,000 for the lift works, £24,000 for surveyor’s fees, £8,025 for [NAME] agents’ fees and £113,405 for VAT.

2. The Tribunal is not persuaded by Counsel’s analysis of the lease that the Respondent has authority to recover the costs of these proceedings through the service charge. In the alternative the Tribunal makes an Order under section 20C of the Landlord and Tenant Act 1985 preventing the landlord from recovering the costs of these proceedings against the Applicants through the service charge.

Background

3. The Applicants seek a determination under Section 27A of the Landlord and Tenant Act 1985 as to whether a service charge on account in the sum of £826,725 is payable in relation to major works for the replacement of two lifts.

4. The demand for the service charge comprised £648,720 ([NAME] price for the replacement of two lifts), £24,000 (surveyor’s fees), £16,218, ([NAME] agent’s fee) and VAT of £137,787.60. The demand was originally issued on the 15 October 2020 and was subsequently replaced by a fresh demand requiring payment on 25 March 2021.

5. The Applicants also seek an order for the limitation of the landlord’s costs in the proceedings under Section 20C of the Landlord and Tenant Act 1985 and Para 5A of the Commonhold and Leasehold reform Act 2002.

6. Arlington House is 1960’s residential tower block with 18 floors consisting of 142 apartments located on the sea front in Margate Kent. The construction is of steel reinforced on-site-cast concrete.

7. The Respondent owns 36 flats in the building which are let on short assured tenancies. The remaining 106 flats belong to [NAME]

8. The issue in this case concerned the proposed costs for the replacement of the two lifts in the building. The parties were agreed that the lifts required substantial works. The Applicants accepted that the works were urgent and necessary. The Applicants, however, blamed the Respondent for taking too long to carry out the works which had led to an unwarranted escalation in the costs. The Applicants argued that the Respondent had no reason to tender

3 the works following the Tribunal’s decision on 12 May 2020 to grant the Respondent dispensation from the consultation requirements in connection with major works. The Applicants considered the Respondent’s preferred option of the complete replacement of the two lifts with a standard passenger lift and a [NAME] too costly and not required. Instead the Applicants contended for refurbishment of the lifts for which two quotations had been received at significantly lower costs than the preferred tender for replacement of the lifts.

9. Respondent’s [COUNSEL] pointed out that there was no dispute that the works to the lifts should be carried out. According to [COUNSEL], the dispute concerned what works should be carried out and what they should cost. [COUNSEL] summarised the parties’ positions as: the Applicants preferred less comprehensive and less expensive works whilst the Respondent preferred the option that conformed to current standards which included a [NAME]. In [COUNSEL] opinion the dispute between the parties turned on the question of reasonableness.

10. [COUNSEL] submitted that costs were not the only factor to be considered when examining the issue of reasonableness. In [COUNSEL] view the Respondent’s preference for the solution that conformed to current standards and maximised fire safety at a cost that was not so great met the standard of reasonableness. [COUNSEL] asserted that the Tribunal should accord the Respondent a margin of appreciation in [NAME] the final decision on which option should be taken forward in carrying out the necessary works.

The Proceedings

11. On 12 May 2020 the Tribunal granted the Respondent dispensation with conditions from the consultation requirements in respect of the proposed works to the lift.

12. This Tribunal notes that on 12 May 2020 that the Applicant had obtained a specification and quotation for the works which had gone out to tender and a tender report was produced. At [14] the Tribunal recorded:

“The tender report recommended [COMPANY] at a price of £442,685 plus VAT. The tender refers to administration and supervision being charged by [COMPANY] at 20%. This tender report of September 2019 recommended that the works should be "instructed without delay to avoid the certain probability that both lifts will suffer a critical failure, with any attempt at repair being uneconomical, due to the obsolescence of all the equipment”.

13. At [27] the Tribunal imposed the following condition to the order for dispensation:

4

“The Applicant will, at its own cost, procure a report from an independent lift [NAME] who has not previously reported on the lifts at the property. They will be specifically asked to comment whether in their opinion the lifts are obsolete and whether in their professional opinion replacement is a reasonable approach if the lifts are obsolete rather than repair or refurbishment. Such report shall be provided to all the [NAME] as soon as reasonably practicable after receipt and the Applicant shall have regard to the same.

The Applicant shall serve Notification of Estimates including a schedule of any responses to the initial notice (in respect of which the window for observations has now closed). The time estimate for [NAME] to make any observations shall be reduced to 14 days from the date of service of this notice.

14. In accordance with the conditions on which dispensation was granted, the Respondent obtained an independent report from [RESPONDENT] in June 2020 that was supplemented by an email on 12 June 2020. The Report concluded that the lifts were fully obsolete and required replacement in their entirety. The Respondent decided to commission a new specification from [NAME] and obtained tenders from four companies with a further four companies declining to tender. The tender from [NAME] at £648,720 plus VAT came in at the lowest and formed the basis of the supplemental demand for service charges which triggered this [NAME].

15. On 6 April 2021 the matter came before the Tribunal which after hearing from the parties decided that independent expert evidence was required in this case. The Tribunal gave the parties permission to rely on the jointly instructed written evidence of an expert [NAME] lift [NAME] and that the expert’s report should be [COMPANY] to the following issues:

(i) whether replacement or repair of the two lifts in the building is appropriate, including the need for a [NAME];

(ii) to prepare a specification of the required works;

(iii) to prepare an estimate of the cost of the works.

16. Mr [NAME] of [NAME] was appointed as the jointly instructed expert and he produced a report on 14 June 2021.

17. The hearing was reconvened on 20 July 2021 before a differently constituted Tribunal. The Applicants were represented by Mr [COUNSEL]. [NAME] of Counsel appeared for the Respondent. Mr [COUNSEL] the jointly instructed expert was also in attendance.

5 18. At the commencement of the proceedings Judge Tildesley directed that the proceedings to be held in private because Havant Justice Centre had been closed following a COVID outbreak. Judge Tildesley also informed the parties that [NAME], the valuer member had been an equity partner for Parsons Son & Basley the [NAME] agents but this appointment had ceased in 2000, and that [NAME] had had no contact with the firm. Judge Tildesley informed the parties that [NAME]’ involvement did not in his view constitute a conflict of interest because of the passage of time. The parties made no representations to the contrary.

19. The Respondent supplied a bundle of documents comprising 1123 pages. References to documents are in [ ]. The Applicants adduced witness statements from Ms [NAME] (Flat 10H), Mr [NAME] (Flat 11B), Ms [NAME] on behalf of Mr [NAME] (Flat 13F), Ms [NAME] (Flat 12C), Mr [NAME] (Flat 10H), Mr [NAME] (Flat 9F), Ms [NAME] (Flat 5E) and Mr and Mrs [NAME] (Flat 7E). The witness statements were admitted as read with no cross examination by Counsel. The Tribunal heard from Mr [COUNSEL], the jointly instructed expert, who was asked questions by the parties’ representatives.

The Facts

20. The critical matter in this case was whether the lifts at the property should be refurbished or replaced. In this regard the parties directed the Tribunal’s attention to the surveys, quotations and tenders in the hearing bundle. The Tribunal also received expert evidence from Mr [NAME].

21. The Applicants relied on the estimate supplied by Specialist List Services (SLS). SLS reported that the lift equipment was 58 years old and had been subjected to [COMPANY] investment which had impacted on the overall reliability and condition of the lifts.

22. SLS’ first report of 20 May 2020 recommended a price of £321,388 excluding VAT [574] plus an additional cost of £17,135.00 for health and safety works which gave a total cost of £338,523 excluding VAT for works to the lifts. The second report dated 29 March 2021 recommended a price of £374,290 [914]. SLS stated that if the works were carried out it would give a 20 to 25 year lifespan with parts to the lifts.

23. Mr [NAME] view on the specification used by SLS was that it was refurbishment. Mr [NAME] stated that under the specification SLS retained the car interior and doors and landing doors, and that it was essentially [COMPANY] to replacing the control systems. Mr [NAME] expressed concern that SLS did not intend to replace the lift machinery which he considered to be very worn. Also the retention of the landing equipment meant that no fire rating could be applied to the lifts. Finally, Mr [NAME] said that the reports made no reference to fire safety works.

6

24. The Tribunal noted that SLS’s tender price for the specification prepared by [NAME] (full replacement) was £699,680 plus VAT [148].

25. The Respondent had carried out a tender exercise in July 2019 against the specification supplied by [COMPANY]. The specification was entitled the “Modernisation of Two electric Passenger Lifts”. The Respondent received three tenders [COMPANY] (£495,950 plus VAT), [NAME] (£450,985 plus VAT), and [COMPANY] (£442,685 plus VAT). In January 2021 the Respondent approached the two contractors offering the lowest tenders for an updated price. Only Liftec provided a new price which was £514,885 plus VAT. The Tribunal understands that TLC’s specification was for refurbishment of the lifts not replacement.

26. The Respondent referred to the “Report on the Lift Installations at Arlington House” prepared by [COMPANY] dated 9 June 2020. The Executive Summary stated:

“The lifts were originally installed by [NAME] in approximately 1962 as indicated by the controller identification plate available on site. Recent insurance reports were not made available at the time of inspection, as a result [NAME] were unable to pass comment. The lifts have remained virtually untouched since installation with only minor works to the car finishes having been carried out. The major system components are life expired in accordance with CISBE Guide M. In accordance with the findings of this report it is recommended that the lifts are removed in their entirety and completely new lifts installed, along with a fully compliant [NAME] as the building is over highest occupied floor is over 18m from the main entrance level. For the above works to be carried out, we would estimate a budget of £250,000.00-£300,000 for the standard passenger lift and £350,000.00- £400,000.00 for the [NAME] excluding VAT, builders work and professional services which was estimated at £100,000”.

27. The “[NAME]” formed the basis of the specification dated June 2020 produced by [NAME] [82] which went out to tender. The Respondent obtained the following tenders for the works:

a) [COMPANY] quoted for £792,386.80 plus VAT. b) [COMPANY] quoted for £699,680.00 plus VAT. c) [COMPANY] quoted for £691.680.00 plus VAT. d) [COMPANY] quoted for £648,720.00 plus VAT

28. The tender report recommended that [NAME] were awarded the [NAME] on costs and the most specification

7 compliant. On 9 March 2021 [NAME] elevators revised the price upwards to £681,249 plus VAT (and a further provisional sum of £60,165 plus VAT for a backup generator) [NAME] a total cost £741,414 plus VAT. Their reason for the increase was because the cost of steel had nearly doubled in the UK since the works were first tendered which had led to larger than 15 per cent cost increases on the lift cars, architraves, guide rails, brackets, shaft facias, shaft division screens and all other architectural, structural and fabricated steel work. The raw material cost increases in the UK had also led to cost increases of the electrical works. [NAME] indicated that it would maintain the revised tender until 30 June 2021.

29. Mr [NAME] opined that the lift equipment at Arlington House was substantially beyond end of life but he recommended major refurbishment rather than replacement on the grounds of reduced disruption to residents, assured robustness of solution and lower cost. Mr [NAME] stated that repair alone was not sufficient. Mr [NAME] also identified an imminent risk of failure with the lifts.

30. Mr [NAME] explained under his recommendation of refurbishment of the lifts the cars would be replaced but the counterweight, guiderails, and their brackets would be retained. Mr [NAME] would also let the eventual contractor decide whether to replace the sling in which the lift car was mounted. Mr [NAME] stated that the retained items would have no adverse effect on the performance and the safety of the refurbished lifts. Mr [NAME] pointed out that the counterweight was a lump of cast iron, and that the guiderails had not worn down appreciably and were within points of a millimetre of their thickness when they were installed some 50 years ago. Mr [NAME] indicated that if guiderails were replaced it might involve additional steelwork in the open side of the lift shaft to affix the new guiderails which now came in standard lengths. Mr [NAME] emphasised that in his proposal all other lift equipment would be wholly new.

31. Mr [NAME] estimate of the costs of the proposed works was £490,000 excluding VAT or £588,000 including VAT. Mr [NAME] also included an estimate of costs of £28,500 for optional works excluding VAT or £34,200 including VAT. The optional works included essential electrical works of £9,000 which were only optional in the sense of whether the lift installer or a separate electrical works performed the works. The remaining £19,500 of costs for optional works included £16,000 for automatic rescue, £1,000 for directionally illuminated safety edges and £2,500 for the full painting of the machine room. Mr [NAME] stated that the automatic rescue enabled the lift to be moved to the next level so that occupants could get out more easily in the event of a lift failure. Mr [NAME] expressed confidence in the estimate of costs provided. Mr [NAME] said that he had analysed each line of expenditure to ensure the accuracy of the final estimate.

8

32. Mr [NAME] stated that [NAME] was a fireman’s lift which was a regular passenger lift with a fireman’s override control switch provided at ground floor level. The override switch enabled the [NAME] to assume control of the lift in the event of fire. Mr [NAME] said that this was not the same as a [NAME] which had better structural protection than the fireman’s lift together with lift control and communication systems and a secondary back up power supply. Mr [NAME] stated that the firefighting lifts were used to bring both the firefighters and their equipment to the floors in the building where the fire was located.

33. Mr [NAME] argued that the need for the property to have a [NAME] could not be answered as a “yes or no”. Mr [NAME] stated that his recommendation for major refurbishment over replacement was not governed by a decision for or against a [NAME]. Mr [NAME] acknowledged that if this was a new building a [NAME] would be required because of the height of the building in line with BS 9991. Mr [NAME] said that BS8899 (“the Code”) was the relevant code of practice for the improvement of firefighting and evacuation provisions to existing lifts. Mr [NAME] highlighted clause 5.1 of the Code which said that “any improvement of an existing lift towards the provisions of a [NAME] was expected to have benefit to those carrying out fire and rescue operations”. Mr [NAME], however, indicated that the Code required the assessment of the benefit of a [NAME] had to be performed in the context of a wider building fire strategy. Mr [NAME] also added that there was no legal requirement for existing lifts to be upgraded to a [NAME].

34. Mr [NAME] suggested that the question of improving the fire safety of [NAME] had not been considered as part of a wider building strategy for the property despite the existence of fire risk assessments and some building improvements .

35. The Applicants pointed out that an extensive programme of fire safety works had been carried out on the property following the issue of a Fire Enforcement Notice in May 2019 which was lifted in September 2020. The works included works to means of escape routes and communal doors and improved compartmentation individual flats. The Applicants stated that in 2020 two fire risk assessments had been undertaken on the property. According to the Applicants, the assessments had not identified the need for firefighting enhancements to the passenger flats. The most recent fire risk assessment had confirmed the viability of the “Stay Put” policy in the event of a fire in the building. Mr [NAME] indicated that there were staircases at either end of the building which could be used by the [NAME] to access the floors to tackle any fire.

9 36. The Respondent relied on a letter from the [NAME] ([NAME]) dated 17 June 2021 which had been provided with copies of the “[NAME]” report and Mr [NAME] report. [NAME] said that every building should be provided with suitable access and facilities for fire-fighting purposes. According to [NAME], the time taken to move sufficient resources to the scene of operations had a direct impact on the rescue of casualties, the development of the fire and the safety of firefighters. [NAME] said that its policy was that all tall residential buildings with an occupied floor greater than 18 metres above fire and rescue access level should be provided with a [NAME].

37. Mr [NAME] accepted that the improvement of the firefighting capability of [NAME] would be of benefit for the property. Mr [NAME] was of the opinion that the refurbishment of the [NAME] should include the firefighting features integral to the lift car. Mr [NAME] acknowledged that this would not achieve full firefighting status but would be a step in the right direction. Mr [NAME] stated that careful “cost versus benefit” consideration would have to be given to the more expensive items associated with full firefighting status. Mr [NAME] referred specifically to the cost of the generator to provide the secondary power to the [NAME]. Mr [NAME] noted that [NAME] had allowed a provisional sum of £60,000 for the generator but according to Mr [NAME] there appeared to be no consideration to where the generator would be housed and the associated building costs. Mr [NAME] also went into detail about protecting the lift car and shaft from the discharge of water by firefighters used to dampen a potential fire. Mr [NAME] acknowledged Mr [NAME] point that excess water might escape via the stairwells.

38. Mr [NAME] supplied a document headed “Fire-use Feature Notes” which summarised the features of a [NAME], how they related to [NAME] and what actions might be required [1022]. Mr [NAME] explained that fire features associated with the lift car, such as the communication system, master control point, ancillary equipment and water-proofing could be incorporated in the specification at a relatively modest cost estimated at £20,000. In Mr [RESPONDENT] view, this would enable the Respondent at some future date to implement a full [NAME] without replacing the lift car and doors. Mr [NAME] advised that if a partial solution was adopted it would be important to ensure that the signage on the lift did not create confusion for the firefighters so that they knew that [NAME] was not a [NAME].

39. The Applicants asked Mr [NAME] for details of his fee if he was appointed as supervising [NAME] for the installation of the lifts. Mr [NAME] quotation had three separate elements [1105]. A fee of £13,704 excluding VAT for the role of [NAME] which included preparing the specification and going out to tender. A fee of £3,765 for [NAME] (Construction Design and Management Regulations) who ensured compliance with health

10 and safety requirements and which would be carried out by a separate person. A fee of £5,195 for the role of [NAME] Administrator and Project Management. Mr [NAME] stated that it was essential to have a [NAME] for the project so as ensure that the contractor delivered the works to the specification.

40. The Tribunal concluded on the facts that the two lifts at the property were beyond the end of life and that they required wholesale refurbishment as described by Mr [NAME] or replacement in their entirety. The Tribunal did not consider that the SLS’ proposals of the 20 May 2020 and 29 March 2021 as favoured by the Applicants were viable. In the Tribunal’s view, the proposals did not address significant issues of disrepair particularly in relation to the lift machinery, and failed to consider the question of fire safety. The Tribunal notes that when SLS was asked to tender for the enhanced specification prepared by [NAME] their price was almost £700,000.

41. The Applicants placed weight on SLS’ indication that their proposals would provide an additional 20 to 25 years lifespan for the lifts which they contrasted with the lifespan of 15-20 years supplied by [NAME]. The Tribunal did not consider SLS’ lifespan realistic given the limitations of the specification to which SLS was operating.

42. The Tribunal observes that the tipping point between the choice of major refurbishment and replacement is whether a [NAME] should be installed in the property. Although Mr [NAME] attempted to redefine the question as major refurbishment versus replacement, the facts of the dispute inevitably focussed on the importance of fire safety for a building which has 18 floors above ground level. The Tribunal concluded that there was no legal requirement to replace an existing lift with a [NAME] but that it was a legitimate consideration which carried weight when deciding which option to pursue. Ultimately the choice of which option in the context of service charges would depend upon the assessment of the reasonableness of the costs within the meaning of section 19 of the 1985 Act.

Reasons

43. The Tribunal is deciding whether a service charge on account in the sum of £826,725 is payable in relation to major works for the replacement of two lifts. The amount of £826,725 comprised £648,720 ([NAME] price for the replacement of two lifts), £24,000 (surveyor’s fees), £16,218, ([NAME] agent’s fee) and VAT of £137,787.60. The demand was originally issued on the 15 October 2020 and was subsequently replaced by a fresh demand requiring payment on 25 March 2021.

11 44. In order to make its determination under section 27A of the 1985 Act the Tribunal has to be satisfied that (1) the service charges are recoverable under the lease (2) the charges are reasonable and (3) the charges have been properly demanded.

45. The parties accepted that the charges were recoverable under the leases. Respondent’s [COUNSEL] explained that there was some variation in the precise wording of the relevant terms of the Applicants’ leases but in every case the leases authorised the recovery of the costs associated with the major works to the lifts.1 The Applicants did not challenge Counsel’s construction of the lease. The Tribunal also agreed with Counsel’s construction and is satisfied that the costs for the major works for the lifts are recoverable under the terms of the lease.

46. The Respondent accepted that the Applicants’ leases contained different payment provisions, and that it followed that not all the Applicants were liable to pay the October demand by the due date2. The Respondent had corrected its mistake and issued new demands requiring payment by 25 March 2021. The Applicants raised no other issues about whether the service charge had been properly demanded. The Tribunal is, therefore, satisfied that the later demand requiring payment by 25 March 2021 is in accordance with the terms of the various leases held by the Applicants and the statutory requirements.

47. The contentious issue between the parties is whether the costs were reasonable. Section 19(2) of the 1985 Act provides the statutory test for on account service charges which is “where a service charge is payable before the relevant costs are incurred, no greater amount than is reasonable is so payable”.

48. [ADDRESS] of Appeal in [COMPANY] v Cowley [2019] EWCA Civ 1827 ruled that whether an amount was reasonable as an advance payment was not generally to be determined by the [NAME] of rigid rules but should be assessed in the light of the specific facts of the case. [ADDRESS] of Appeal added that considerations which should be taken into account in determining the question of reasonableness under section 19 (2) included the time at which the landlord was likely to become liable for the costs and how certain the amount of costs was. Further the wording of section 19(2) was intended to allow for flexibility, given that it did not define what was reasonable.

49. The Applicants asserted that there had been a historic failure by the Respondent to replace the lifts which had resulted in an unwarranted escalation of costs which would now have to be borne by the [NAME]. The Applicants in their statement of case

1 See the Respondent’s statement of case at [626] 2 See Respondent’s statement of case at [650].

12 referred to the Respondent’s issue of section 20 consultation notices of lift works on three occasions during 2014 and 2015. Additionally in 2014 the Respondent obtained a specification for lift works from ILECS but did not progress it. Further in 2018 the Respondent again intended to carry out substantial lift works but did nothing. The Tribunal at [11] to [13] recorded the chronology of these proceedings starting with the grant of dispensation from the consultation requirements on the 12 May 2020 on the ground of the urgency of the works.

50. Counsel argued that the history of the Respondent’s actions in relation to the repair of the lifts was not relevant to the facts of this case. Counsel relied on the decision of the Upper Tribunal in [COMPANY] v [NAME] [2014] UKUT 206 (LC) at [88] which said:

“As the Lands Tribunal (HH Judge Rich QC) explained in [NAME] v White [2006] 1 EGLR 85 an allegation of historic neglect does not touch on the question posed by s.19(1)(a), Landlord and Tenant Act 1985, namely, whether the costs of remedial work have been reasonably incurred and so are capable of forming part of the relevant costs to be included in a service charge. The question of what the cost of repair is does not depend on whether the repairs ought to have been allowed to accrue. The reasonableness of incurring the cost of remedial work cannot depend on how the need for a remedy arose.”

51. The Tribunal agrees with Counsel’s submission subject to the following caveats:

i. The Applicants may have a claim for damages in respect of any increased costs to the extent they are attributable to a breach of covenant. Such a claim may be expressed as a set off in an [NAME] to determine actual service charges or in court proceedings for breach of covenant. Council accepted this in principle but pointed out that the Respondent would deny that it was in breach of its repairing covenant, and asserted that the Applicants had not articulated within this [NAME] a compelling case for breach of covenant.

ii. The fact of delay as distinct from a potential cause of action for breach of covenant may be a relevant consideration for the assessment of reasonableness.

52. [COUNSEL] argued that this was a case where the Respondent was faced with two options each of which had reasonable outcomes, and that it was not for the Tribunal to interfere with the Respondent’s chosen course of action if it produced a reasonable outcome. In support of his proposition [COUNSEL] relied on the Court of Appeal decision in [NAME] v Hounslow LBC [2017] EWCA Civ 45 at [37]:

13

“In my judgment, therefore, whether costs have been reasonably incurred is not simply a question of process: it is also a question of outcome. That said it must always be borne in mind that where the landlord is faced with a choice between different methods of dealing with a problem in the physical fabric of a building (whether the problem arises out of a design defect or not) there may be many outcomes each of which is reasonable. I agree with Mr [NAME] that the tribunal should not simply impose its own decision. If the landlord has chosen a course of action which leads to a reasonable outcome the costs of pursuing that course of action will have been reasonably incurred, even if there was another cheaper outcome which was also reasonable.”

53. [COUNSEL] contended that the Respondent’s choice of adopting the recommendations of the [RESPONDENT] report of total replacement of the lifts including the installation of a [NAME] was reasonable. [COUNSEL] advanced the Respondent’s case by the following propositions:

a) Is the outcome on cost so significant that reasonableness required prioritising reducing it? [COUNSEL] argued that the major works would run into hundreds of thousands of pounds (of which the Respondent would bear a considerable proportion). Counsel accepted that there would ultimately come a point where conforming to good practice would cost so much more than a ‘next best’ approach that it could not be justified. Counsel submitted in this case, the Respondent did not consider that point had been reached.

b) Is it unreasonable for the Respondent to follow the recommendation to install a [NAME]? Counsel pointed out that it was possible to install a [NAME] which conformed to current standards and good practice. Although it was not a legal requirement to have such a lift, the Respondent would be reluctant to economise by voluntarily departing from what had been recommended as good practice when it came to a matter as important as fire safety. Counsel said that the Respondent was supported in that position by the clear policy of [NAME]. Finally, according to Counsel, the Respondent’s would be seen as a reasonable choice by current lessees not participating in this [NAME] and by future lessees.

c) Does reasonableness require a new specification and tendering process? Counsel stated that the Respondent opposed the argument that reasonableness required it to abandon the previous specification and use

14 the not yet finalised specification accompanying Mr [NAME] report as the basis for a wholly new tendering process. That would entail substantial further delay. In circumstances where only one lift was operable and its future reliability very doubtful, avoiding further delay was a very weighty consideration.

54. Counsel in his Skeleton advanced other propositions involving “conflict of interest” and “the Applicants’ evidence on lift works in other buildings”. The Tribunal noted that Mr [NAME] did not advance these specific parts of the Applicants’ case at the hearing, and the Tribunal decided that they were not relevant to the question of reasonableness. Counsel also addressed the shortcomings in the SLS’ proposals which the Tribunal has dealt with at [40] above.

55. The Tribunal considers the Court of Appeal decision in “[NAME]” represented a turning point in how the question of reasonableness in the context of service charges should be approached. Prior to [RESPONDENT], the focus was on the rationality of the landlord’s decision- [NAME] process, the Court of Appeal shifted that focus by adding the concept of outcome which included the interests of the tenants. [NAME] LJ at [46] said

“Although I am fully aware of the desirability of predictability in the law and practice, and appreciate that landlords want to avoid the risk of non-recovery of costs incurred in good faith, the open textured nature of a test of reasonableness makes it dangerous even to attempt to be prescriptive. Factual situations are almost infinitely variable, and different considerations will come into play in different circumstances. Parliament has deliberately chosen an open ended and flexible test, and has left all factual determinations to the good sense of the F-tT.

56. The Tribunal finds the following facts:

a) The two lifts at the property were beyond the end of life and that they required wholesale refurbishment as described by Mr [NAME] or replacement as proposed by [NAME]

b) There was no legal requirement to replace an existing lift with a [NAME] but that it was a legitimate consideration which carried weight when deciding which option to pursue. Ultimately the choice of which option in the context of service charges would depend upon the assessment of the reasonableness of the costs within the meaning of section 19 of the 1985 Act.

c) There had been significant delay on the Respondent’s part in implementing a satisfactory solution for the repair of the lifts which had been ongoing since 2014.

15

d) In May 2020 the Respondent had been granted dispensation from consultation requirements in respect of major works on the lifts on the ground that the works were urgent. The Respondent at that time was proceeding on a specification for major refurbishment of the lift which did not include a [NAME]. The Tribunal acknowledges that as a condition of the dispensation the Respondent was required to procure a report from an [NAME] to comment whether in their opinion replacement was a reasonable option. In those circumstances the Tribunal accepts that the delay occasioned by the Respondent in considering the [RESPONDENT] report was understandable.

e) The price for the wholesale replacement of the lifts with a [NAME] was not certain, and the eventual price was likely to be significantly higher than the original tender upon which the service charge demand was based. On 9 March 2021 [NAME] revised the price upwards for wholesale replacement with a [NAME] from £648,720.00 plus VAT to £741,414.00 plus VAT (an uplift of 14.2 per cent). Also the Respondent indicated that there was no guarantee that [RESPONDENT] would hold that price. Further Mr [NAME] indicated that the price supplied by [NAME] did not include the cost of potential building works to house the generator for supplying the secondary power supply for the [NAME]. Finally Mr [NAME] was unable to assess whether the generator proposed by [NAME] met the necessary specification for a [NAME].

f) Mr [NAME] estimate for refurbishment of the lifts was derived from calculating the likely cost based on experience for each line of expenditure which promoted confidence in the accuracy of the estimate. The estimate was in line with the tenders for the lift specification prepared [COMPANY] for refurbishment carried out in July 2019.

g) Mr [NAME] supplied estimated costs for upgrading [NAME] so that the lift car and doors met the requirements of a [NAME] which would enable the Respondent at some future date to upgrade to a full [NAME] if it was considered necessary to do so.

h) Mr [NAME] estimated costs for refurbishment of the lift with essential electricity works totalled £499,000 plus VAT. The costs of the optional works were £19,500 (£16,000 for automatic rescue, £1,000 for directionally illuminated safety edges and £2,500 for the full painting

16 of the machine room) and £20,000 for upgrading the car and doors of [NAME] with the features associated with firefighting lifts.

i) The margin of difference between the tender of [NAME] and Mr [NAME] estimate included the optional works and firefighting upgrading was £203,000 (38 per cent) which in the Tribunal’s view is significant.

j) The Applicants comprised 61 per cent of the [NAME] who were independent of the Respondent. The Applicants wished the works to the lifts to be carried out without delay. They had expected the Respondent to have completed the works by now, and had experienced considerable inconvenience and potential risks to health and safety with the breakdown of the lifts. The Applicants said that individual [NAME] were facing demands varying between £4,960 and £6,283 which were significant sums of money particularly as there was no guarantee when the works would be undertaken.

k) The Applicants were not convinced with the benefits of having a [NAME] particularly in the light of the various reports on fire safety at the property which had not recommended improvements to the fire safety of the lifts.

l) The Respondent through its ownership of 36 flats at the property would be [NAME] a substantial contribution to the costs of the major works, and held a legitimate view that the works should meet best practice with regard to fire safety.

m) The Tribunal considered that the proposal for wholesale replacement of lifts with a [NAME] carried a higher risk of delay than progressing with the refurbishment option as advocated by Mr [NAME]. The Tribunal formed the view that there remained considerable uncertainty about the eventual costs of the wholesale replacement and that the current demand in dispute was not sufficient to cover the known costs for replacement. Also the Tribunal was not convinced that the dispensation from consultation covered the wholesale replacement of lifts. The Tribunal on the other hand considered that the costs of refurbishment was relatively certain and that if the Respondent proceeded on the basis of Mr [RESPONDENT] proposal with enhancement the tendering exercise would be relatively swift and probably would not require a further [NAME] for dispensation.

17

57. The Tribunal having regard to the facts found places weight on avoiding further delay in implementing the works to the lift and the need to have certainty about the eventual costs. In this regard the Tribunal is satisfied that the option of wholesale replacement does not result in reasonable outcomes. The Tribunal would add that the potential difference in cost between the options of wholesale replacement and major refurbishment is significant and has reached the point where priority should be given to reducing it. The Tribunal acknowledges the Respondent’s desire to ensure that the lifts comply with best practice regarding fire safety of lifts. The Tribunal, however, considers that this can be best achieved by carrying out Mrs [NAME] suggested improvements to the lift car and doors.

58. The Tribunal, therefore, decides that a sum of £535,000 plus VAT is no greater amount than is reasonable for the costs of the refurbishment of the lifts. The Tribunal has arrived at £535,000 by adding the estimated costs of £16,000 for automatic rescue and £20,000 for fire safety to the basic estimate of £499,000 proposed by Mr [NAME].

59. The Tribunal having regard to the evidence of Mr [NAME] on the necessity for a [NAME] and the associated roles of [NAME] ([NAME]) and [NAME] Administrator decides that a fixed sum of £24,000 plus VAT is no greater amount than is reasonable.

60. The Tribunal is not convinced about the reasonableness of the costs of the [NAME] agent which was calculated at 2.5 per cent of the [NAME] price. Counsel said that the costs represented the time spent by the [NAME] agent in carrying out the statutory consultation on the works, dealing with [NAME] enquiries and for preparing and sending out the service charge demands. The Tribunal notes that there has been no statutory consultation on these works, and that the preparation of the demands would be within the standard costs of a [NAME] agent. The Tribunal accepts that the [NAME] agent would incur additional costs when the works are carried out in liaising with [NAME] about the plans for the works. The Tribunal applying its general knowledge and expertise considers an amount of £8,025 (1.5 per cent of the [NAME] price) plus VAT is reasonable.

61. The Tribunal determines that a service charge on account in the sum of £680,430 is payable in relation to major works for the refurbishment of the two lifts. The sum is made up of £535,000 for the lift works, £24,000 for surveyor’s fees, £8,025 for [NAME] agents’ fees and £113,405 for VAT.

62. The Tribunal considered whether the works could be phased in order to mitigate the financial burden on the [NAME]. The

18 Tribunal accepted Mr [NAME] opinion that it was not possible to phase works without a significant increase in costs.

63. The Tribunal is not persuaded by Counsel’s analysis of the lease that the Respondent has authority to recover the costs of these proceedings through the service charge. In the alternative, the Tribunal makes an Order under section 20C of the Landlord and Tenant Act 1985 preventing the landlord from recovering the costs of these proceedings against the Applicants through the service charge. The Tribunal is satisfied that it is just and equitable to make such an Order because the Applicants have been successful in reducing the service charge, and that the necessity for the proceedings has been in part due to the Respondent’s delay in not carrying out the works to the lifts earlier. The Tribunal does not agree with the Respondent’s assertion that the Applicants have conducted the proceedings in a vexatious manner.

19

Rights of appeal

By rule 36(2) of the Tribunal Procedure (First-tier Tribunal) (Property Chamber) Rules 2013, the tribunal is required to notify the parties about any right of appeal they may have. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber), then a written [NAME] for permission must be made to the First-tier Tribunal at the regional office which has been dealing with the case. The [NAME] for permission to appeal must arrive at the regional office within 28 days after the tribunal sends written reasons for the decision to the [NAME]. The [NAME] should be send by email to [EMAIL] If the [NAME] is not made within the 28 day time limit, such [NAME] must include a request for an extension of time and the reason for not complying with the 28 day time limit; the tribunal will then look at such reason(s) and decide whether to allow the [NAME] for permission to appeal to proceed, despite not being within the time limit. The [NAME] for permission to appeal must identify the decision of the tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal and state the result the party [NAME] the [NAME] is seeking. If the tribunal refuses to grant permission to appeal, a further [NAME] for permission may be made to the Upper Tribunal (Lands Chamber).

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • Tenants are entitled to challenge service charges deemed unreasonable under the Landlord and Tenant Act 1985.
  • Legal costs incurred by the landlord are not considered reasonable service charges for tenants to pay.
  • Tenants are not required to pay for repairs made to another tenant's property without their consent.
  • Charges for major works, such as replacing lifts, are considered reasonable if they are necessary and incurred reasonably.
  • Managers can determine reasonable service charges based on the property's condition and requirements.

❌ Tends to be rejected

  • Electricity costs for lift refurbishment were not considered reasonably incurred if they did not meet the criteria for necessity and reasonableness.
  • Certain charges were struck out as not being service charges within the meaning of section 18 of the Landlord and Tenant Act 1985.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The Tribunal reduced the service charge for lift works from £826,725 to £680,430.

Who was involved?

The decision involved tenants and a landlord in a residential property in Margate, Kent.

How did the court decide, and why?

The court decided that the costs were reasonable under the Landlord and Tenant Act 1985, considering the necessity and urgency of the works.

Which laws or rules were applied?

The court applied Section 27A and Section 20C of the Landlord and Tenant Act 1985.

What was the argument that mattered most?

The argument that mattered most was the reasonableness of the costs for the necessary works.

Was the decision for or against the person who brought the case?

The decision was for the tenants who brought the case.

What does this mean for someone in a similar situation?

Someone in a similar situation might be able to challenge unreasonable service charges for necessary works.

What evidence or documents mattered?

Evidence included surveys, quotations, and tenders related to the lift works.

Can a decision like this be appealed?

Yes, a decision like this can be appealed to the Upper Tribunal within 28 days.

Is it worth getting a solicitor for a case like this?

It is always recommended to get advice from a qualified solicitor for a case like this.

Official source: First-tier Tribunal (Property Chamber) — headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.