VadeLab
DismissedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Rejects Leaseholder's Challenge on Service Charges

Case No.

📌 In brief

The First-tier Tribunal dismissed a a person's challenges regarding service charges for roof works and a person Knotweed treatment, ruling that the charges were reasonable and valid under the Landlord and Tenant Act 1985.

⚖️ Legal holding

The tribunal found that the costs of roof works were reasonable under the Landlord and Tenant Act 1985, considering the scope of the works and the involvement of a surveyor.

Topics

service chargesroof repairsJapanese Knotweed

Provisions

Landlord and Tenant Act 1985 s.19Landlord and Tenant Act 1985 s.20CCommonhold and Leasehold Reform Act 2002 Schedule 10 para 5A

📖 What the law says

Landlord and Tenant Act 1985 s.19

This section states that when determining the amount of a service charge, only relevant costs that are reasonably incurred should be considered. Additionally, if these costs involve providing services or carrying out works, they must be of a reasonable standard. If a service charge is paid before the costs are incurred, the amount must be reasonable, and any necessary adjustments will be made once the costs are known.

Plain-English explanation — does not replace advice from a solicitor.

📖 Technical summary

The tribunal dismissed the applicant's challenge to the roof works costs, finding the works necessary and the costs reasonable despite delays.

📜 Headnote Official document

The First-tier Tribunal dismissed a leaseholder's challenges regarding service charges for roof works and Japanese Knotweed treatment, finding the charges reasonable and valid under the relevant legislation.

📚 Full judgment Official document

OUTCOME: Dismissed

1

Case Reference : HAV/00HB/LSC/2025/0707

Property : [RESPONDENT], Bristol, [POSTCODE]

Applicant: [redacted] : In person

Respondent: [redacted]

(Management) [RESPONDENT] : Mr [COUNSEL] (Director)

Type of Application : s.27A LTA 1985

Tribunal Members : Judge Dovar

Mr [NAME] and venue of : 9th December 2025, Bristol Hearing

Date of Decision : 23rd January 2026

_______________________________________________

DECISION ____________________________________

© CROWN COPYRIGHT

FIRST - TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

2

1. This is an application by a [NAME] for the determination of liability to pay various service charges stretching back to 2019. On the morning of the hearing the scope of the dispute narrowed significantly given that some of the challenges had already been the subject of a Tribunal determination in September 2023 (CHI/00HB/LSC/2023/0013) and in respect of other challenges, the Applicant dropped his objections.

2. As a result of that, the only matters in dispute were in relation to roof works and [NAME]. All other sums were accepted as being payable, save where the previous Tribunal had specifically determined otherwise.

3. The Property is a three storey town house converted into three self contained flats. Each flat is let on a long lease, the Applicant is the [NAME] of the first floor flat. Each long [NAME] is also a member of the Respondent company which owns the freehold. The Respondent is therefore the [NAME] under each lease and manages the Property under the terms of the same. [NAME] contributes 1/3rd of the total cost of works to the service charge. Roof Works (yr end 2025: £73,369.56 Inclusive of VAT plus surveyor £7,336.96)

4. Mr [APPELLANT] application to this Tribunal said this about the cost of the roof works

3

“Roof Contribution £15,000 – above the maximum agreed of £13,333 for a new roof rather than repairs. Significantly above the figure had this been completed back in 2018 when I requested.” And “Examining why original roof repair quotes were for a full replacement of tiles, yet the decision was taken to opt to use the existing and further second hand tiles. Losing any guarantee for the tiles as a result. Clarifying why roof repairs were carried out when I had made clear that I was willing to contribute a maximum of £40,000 toward a new roof or [NAME]’s offer to complete the necessary work … Why both a surveyor and a [COMPANY] was required where one or the other would have been sufficient for a new roof. Meaning the cost escalated because of the management company decision against my view.” 5. As a result, he clarifies that his challenges are that: a. the cost was ‘overpriced for roof repairs using the existing tiles and no guarantee being provided.’; and b. concerns had been raised about the roof in 2018 and had they been undertaken then, the cost would have been lower; i.e. ‘An example quote in 2021 for full Welsh slate roof replacement was provided at £28,000 plus VAT’

4

6. A copy of that quote to Mr [APPELLANT] from [NAME] was provided, in addition he provided a quote from [COMPANY], for £31,182, dated 25th January 2020, and from [COMPANY] for £46,552, dated 18th June 2024.

7. The Respondent accepted the roof works had taken time and should have been completed earlier. They had been the subject of comment in the previous proceedings before the Tribunal and had caused problems with insurance.

8. An initial canvassing of contractors produced cheaper quotes, but there was no surveyor involvement at that time. There was then a directors’ meeting on 11th November 2023 at which those quotes were discussed. Mr [APPELLANT] was represented by his father at that meeting. The unverified minutes indicated that the Applicant agreed the level of quotes at around £50,000, queried whether surveyors [NAME] [NAME] should be brought in to manage the works, and certainly wanted a third party to manage the work ‘which would keep the costs down overall’.

9. That was followed up in an email from Mr [NAME] of 28th November 2023, where he said “Further to the AGM and particularly [NAME] firm views representing [NAME] …that we should use [NAME] to oversee the roofing work, I have contact them.” 10. The Respondent explained that as a result of [RESPONDENT] [NAME] involvement the costs went up. Not only because they added their costs, but because

5

contractors were said to be more wary of contracting on a project monitored by a surveyor; presumably as there was an additional burden on them having their work scrutinised more closely by a professional. 11. [NAME] prepared a schedule of works for roof refurbishment and associated building works (including repairs to structural timbers, installation of a breather membrane and masonry works to chimney stacks and parapet walls) in April 2024. They then provided a tender report in May 2024, which identified the three contractors who had been asked to provide a quote. [COMPANY] were the lowest at £61,141.30 and were the preferred bid.

12. At this point, the Applicant’s father emailed ‘…I have never suggested that [APPELLANT] should be instructed to manage the roof, my position remains so, I was in favour of [NAME] being appointed by the FTT to manage the property … I agreed with Mr [NAME] suggestion, that the roof should be supervised professionally and put out to tender…’ His issue with [NAME] appears to be that they were also involved as experts in the disputes between the parties.

13. On 18th June 2024, the Applicant obtained a quote for works from [COMPANY] (as mentioned above). These were not the same works as [APPELLANT] had specified. Further, the Applicant accepted that he had not provided this quote to the Respondent, but had understood that the contractor had been in direct contact. The Respondent said the only contact they had had with [COMPANY] was prior to the [NAME]’s involvement and they were unaware of whether the contractor

6

had liaised with the surveyor over the specification; certainly [NAME[NAME] had not sent the specification out to them to tender and the quote was not in line with the [NAME]’s specification. Had [NAME[NAME] been liaising with [COMPANY] we would have expected their quote to have aligned with the specification at the very least, and also that they would have tendered for the works. The impression left with the Tribunal was that [COMPANY] had not been in contact at this time with either [NAME] or the Respondent.

14. The works were carried out and demands made from each of the leaseholders, including the Applicant. Section 19 15. The challenge to the roof works encompasses two issues: firstly should the cost be capped under s.19 of the Landlord and Tenant Act 1985; secondly, is there any claim for historic neglect which would reduce or extinguish any sum otherwise owed for the works.

16. The Applicant challenges the cost and scope of the works; less was achieved for more. In summary, rather than a replacement of the roof, it was patch repaired – and at a greater cost. This is a challenge that in light of lower quotes for more work, it was not reasonable to incur these costs (s.19(1)).

17. We do not consider that this challenge can succeed for the following reasons.

7

18. Firstly, the scope of works undertaken was different. It was not just roof works, but also included masonry and parapet works and repair to timbers. It is therefore not possible to compare like for like with the quotes that the Applicant has provided. Whilst we acknowledge that this was not a full replacement, it remained a significant repair of the roof.

19. Secondly, we were persuaded by the Respondent’s explanation as to why the cost increased from a sum initially acceptable to the Applicant, to a greater sum. Indeed the Applicant was the instigator of that increase by demanding that the works were overseen by a third party. In the Tribunal’s view this was likely to increase the overall costs. Not just the additional surveying fee, but also the fact that a quote set against a detailed tender may well drive up the cost. There is also the real possibility that the additional scrutiny of a surveyor over works, would cause the contractor to increase their fee.

20. Further, the involvement of a surveyor had the advantage of having the works monitored, and also helped to identify the proper scope of the works. To that end the Tribunal is satisfied that the works carried out were the correct works to carry out.

21. The final criticism of the Applicant is that there was no need to use both a surveyor and a firm which was roofing accredited. However, we considered that it was well within the Respondent’s discretion to engage an accredited contractor. This approach was also supported by the fact that at that time, the [NAME] had made it a stipulation of continued cover that the contractor was accredited.

8

Historic Neglect 22. To establish a claim in historic neglect, the Applicant has to show that not only was the Respondent in breach of its repairing obligations, but that as a result he has suffered a loss.

23. In this case, the Applicant has quotes for work to be carried out as far back as 2020. They are lower.

24. Whilst the Respondent accepts that it failed to carry out the works timeously and was therefore in breach of its repairing obligations, we are not satisfied that any loss has arisen. We repeat the points made above about the quotes not being like for like. The actual works carried out were to some extent more extensive. It is therefore not possible to draw from the evidence what, if any, increase has arisen because of any delay. Certainly we were provided with no evidence of significant further deterioration which became necessary to remedy because of neglect.

25. Whilst we acknowledge that over time there may have been some inflationary increase, we were given no information as to the scale of the same. We also take into account that for the period when no work was carried out, the Applicant was not asked to part with his money. Conclusion on roof works 26. Accordingly the cost of the roof work is allowed in full and the Applicant is liable to pay his 1/3rd share. Knotweed (yr end 2023: part of £4,280 (£750))

9

27. Of the sums claimed in 2023 on account, £750 was to deal with the presence of [NAME] [APPELLANT]. The Applicant says that this was not spent and that in fact he attended the issue at his own costs. He therefore considers this sum should be deducted from the service charge.

28. The Respondent accepts that it was not spent, it was a contingency sum. They point out clause 3.2 of the lease which permits them to charge for anticipated future costs.

29. That clause provides as follows “3.2. To pay to the [NAME] as further and additional rent a sum equal to one-third of the Service Charge … and so that the [NAME] shall have power at their discretion to require the cost of any non- recurring items to be spread over more than one year and so that the [NAME] shall not be entitled to object to or refuse to pay any instalment of the Service Charge on the ground that any part thereof is attributable to any past or future expenditure and not to actual expenses of the then current year” 30. Further, clause 4.1.2 provides for the Respondent to keep an account of income and outgoings and to provide a copy of the balance sheet to the Applicant for each year on demand. The lease terms do not appear to provide for any surplus or deficit charge to be made, nor does it expressly deal with any payment on account of anticipated costs, other than as set out above. The previous Tribunal decision dealt in part with the service charge mechanism at paragraphs 35 onwards..

10

31. This Tribunal considers that clause 3.2 does permit payment in advance for non-annually recurring items such as the treatment of [NAME].

Accordingly, it was a valid charge and remains payable.

32. Notwithstanding that, the Respondent offered to waive the Applicant’s 1/3rd share of the cost if he provided a receipt of payment for the work he said he had carried out. Conclusion and s.20C/Para 5A and Application Fee 33. The sums challenged are payable in full.

34. The Tribunal dismisses the applications under s.20C of the Landlord and Tenant Act 1985 and paragraph 5A of schedule 10 to the Commonhold and Leasehold Reform Act 2002. Not only has the Applicant failed in its challenges, but he abandoned most just before the hearing. Likewise no order is made for the reimbursement of the Applicant’s fees.

11

Appeals

A person wishing to appeal this decision to the Upper Tribunal ([NAME]) must seek permission to do so by making written application by email to [EMAIL] .

The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.

If the person wishing to appeal does not comply with the 28-day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28- day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.

The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The scope of roof works undertaken was different from the applicant's quotes, including masonry, parapet, and timber repairs, making direct comparison impossible.
  • The cost of roof works increased because the applicant demanded third-party oversight, which likely raised overall expenses.
  • The involvement of a surveyor helped monitor the roof works and identify their proper scope.
  • The lease allowed the respondent to charge for anticipated future costs like knotweed treatment.
  • The respondent was within its discretion to engage an accredited contractor for roof works, especially since the insurer stipulated it for continued cover.

❌ Tends to be rejected

  • The applicant's challenge that roof repair costs were overpriced for using existing tiles and providing no guarantee was rejected.
  • The applicant's claim for historic neglect due to delayed roof works was rejected because no evidence showed a loss or significant further deterioration.
  • The applicant's argument that both a surveyor and a roofing-accredited firm were unnecessary was rejected.
  • The applicant's claim that the knotweed sum should be deducted because it was not spent was rejected.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The Tribunal dismissed the leaseholder's challenges regarding service charges for roof works and Japanese Knotweed treatment.

Who was involved?

The leaseholder and the management company of the property were involved.

How did the court decide, and why?

The court decided that the service charges were reasonable and valid, considering the scope of the works and the lease terms.

Which laws or rules were applied?

The Landlord and Tenant Act 1985 sections 19 and 20C, and the Commonhold and Leasehold Reform Act 2002 Schedule 10 paragraph 5A were applied.

What was the argument that mattered most?

The argument that mattered most was that the service charges were reasonable and valid under the relevant legislation.

Was the decision for or against the person who brought the case?

The decision was against the leaseholder who brought the case.

What does this mean for someone in a similar situation?

Someone in a similar situation should carefully review the terms of their lease and the reasonableness of the service charges.

What evidence or documents mattered?

Quotes for roof works and the lease terms were important pieces of evidence.

Can a decision like this be appealed?

Yes, a person wishing to appeal this decision to the Upper Tribunal must seek permission within 28 days of receiving the written reasons for the decision.

Is it worth getting a solicitor for a case like this?

It is always recommended to seek advice from a qualified solicitor for cases involving leasehold disputes.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.