VadeLab
AllowedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Rules on Fire Safety Works Costs

Case No.

📌 In brief

The First-tier Tribunal decided on the reasonableness and cost of a person in a residential property. They found some a person unreasonable and limited the costs of others.

⚖️ Legal holding

Tenants are entitled to challenge the reasonableness and cost of a person under their lease terms.

Topics

fire safety worksservice chargeslease terms

Provisions

section 27A Landlord and Tenant Act 1985section 20C Landlord and Tenant Act 1985Schedule 11(5)(a) Commonhold and Leasehold Reform Act 2002

📖 Technical summary

The tribunal ruled on the reasonableness of a person and costs in a residential property.

📜 Headnote Official document

The First-tier Tribunal (Property Chamber) ruled on the reasonableness and cost of fire safety works carried out in a residential property. The tribunal found certain works unreasonable and limited the costs of others.

📚 Full judgment Official document

OUTCOME: Allowed

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

Case Reference : LON/00BG/LSC/2019/0158 Property : Flats 7 & 14 [NAME], [ADDRESS] [POSTCODE] Applicant: [redacted]

(1) [NAME] (Flat 7) (2) Ms [COUNSEL] (Flat 14)

Representative : In person Respondent: [redacted] London Borough of Tower Hamlets

Representative : Mr. [COUNSEL], counsel Types of [NAME] : Liability to pay service charges Tribunal Members : Judge [NAME] [NAME] and venue of Hearing

: 19 [ADDRESS] [POSTCODE]

Date of Decision

: 18 October 2019

DECISION

2 Decisions of the tribunal

I. The [NAME] are [NAME] of repair or maintenance for which, the applicants are liable to contribute in accordance with the terms of their lease.

II. The partition [NAME] to the roof space are reasonable only to the extent of the installation of three of solid [NAME] partition walls at a cost of £3,788.24 in [NAME]. The cost of the partitioning [NAME] are excessive and are limited to 75% of the final sum claimed for the five partitioning walls.

III. The installation of permanent doors in the roof space is unreasonable and the cost of these [NAME] in the sum of £3,592.19 attributed to [NAME] has been unreasonably incurred and is excessive. Therefore, it is not payable by the applicants.

IV. The cost of the installation of fixed electrical lighting and switches in the roof space in the sum of £3,404.70 attributed to [NAME] has been unreasonably incurred and is excessive. Therefore, it is not payable by the applicants.

V. The cost of the additional [NAME] to [NAME] arising from the 3 November 2017 meeting held with [NAME] amounting to £37,240.35 made up of: 26,766.37/boxing; £3,742.19/supalux lining to sloping soffit; £741.00/[NAME] seal pipe through wall and £5,990.79/ boxing newly clad purloin, are unreasonable and are not payable by the applicants.

VI. The [NAME]’s fees are excessive and limited to 25% of the £3,402 claimed for [NAME]. The administration charges are excessive and limited to 25% of the £398.75 per flat claimed.

_________________________________________________

The [NAME]

1. This is an [NAME] seeking the tribunal’s determination as to the applicants’ liability to pay service charges under section 27A of the Landlord and Tenant Act 1985 (“the 1985 Act) in respect of major [NAME] carried out in 2018/19. The applicants also seek a limitation to any costs pursuant to section 20C of the 1995 Act and Schedule 11(5)(a) of the Commonhold and Leasehold Reform Act 2002 (“the 2002 Act”).

3

The premises

2. Flats 7 and 14 comprise two flats in [NAME] (“the Building”) situated in a four storey purpose built block of flats and which form part of a development of a total of 27 blocks known as the Avebury Estate “the Estate.” The [NAME] has a total of 16 flats split into two blocks, each with their own entrance. Ms [NAME] and Dr [NAME] are the long leaseholders of their subject flats under 125 year leases dated 6th May 1991 and 10th November 1997 respectively. The leases are in substantially the same terms and therefore reference to a lease or leases in this decision includes both flat 7 and flat 14.

Background

3. Since 2008 the respondent freeholder has employed the [NAME] ([NAME]) [COMPANY] to manage its leasehold stock and the properties held by secure tenants. On 24 June 2017 a [NAME] broke out at Dickinson House, a nearby block on the Estate and identical to the [NAME]. This [NAME] originated in a top floor flat and spread to the roof space affecting all of the top floor flats in Dickinson House and required the whole of this building to be vacated while [NAME] of repair were carried out.

4. Following the [NAME] an inspection of the [NAME] was carried out by the London Planning and Emergency Authority and the respondent was served with a Schedule of [NAME] [NAME] dated 29 June 2017 requiring [NAME] to remedy the deficiencies identified to be rectified by 28 December 2017. The respondent made reference to a report prepared by [NAME] shortly before the [NAME] in the neighbouring block but the nature and extent of this report was unclear as it was not provided to the tribunal.

5. The substantive actions to be taken were identified in the Audit as:

(i) ensuring cabling within the common areas is fully fireproof and has 30 minutes of [NAME] resistance and holes within a storage cupboard and a front door to be filled and both made 30 minutes [NAME] resistant;

(ii) the provision of suitable [NAME] resisting separation by ensuring the roofing structure is sufficiently [NAME] resistant to prevent rapid spread of [NAME]; and

(iii) a review of the [NAME] risk assessment.

6. In or about September 2017, in response to this Audit the respondent prepared a Scheme Brief concerning the [NAME] and formed the view that it was expedient to carry out [NAME] to all blocks across the Estate, as its inspection had revealed a number of deficiencies despite an earlier report in or about June 2017 by [NAME] finding that [NAME] [NAME] precautions in the Building were satisfactory. [NAME] were subsequently carried out between October to December 2017 with practical completion being in March 2018. The original budget for these [NAME] had been £500,000 but was revised to £630,000.

7. Subsequently, the respondent applied for and was granted by the First- tier tribunal in its decision dated 14th November 2018, (LON/ooBG/LDC/2018/0143), retrospective dispensation under section 20ZA of the 1985 Act from the statutorily required consultation procedures imposed by that Act for the proposed major [NAME]. These [NAME] to the Estate were awarded to [NAME] and resulted in an indicative estimated amount of £2,562.60 to be paid by each of the applicants. Subsequently, during the course of these [NAME], in November 2017 further [NAME] were recommended by [NAME], the suppliers of the [NAME]-proof partitions installed in the loft area of the Building. Consequently, the costs of the [NAME] increased by approximately 45% to a total scheme estimate of £1,914,55, with revised demands being sent to each of the applicants for £4,386.21.

8. The [NAME] (‘the [NAME]”) which were carried across all of the blocks on the Estate and in the [NAME], included the installation of [NAME] break partitions within the roof spaces, the installation of permanent access doors and fixed lighting together with the replacement of porthole glazed windows with louvre vents. Following completion of these major [NAME], Dr [NAME] received a demand for payment in the sum of £4,548.86and Ms [NAME] a demand for payment in the sum of £4,386.21 said to be their contributions towards the total cost of the [NAME] at a cost of £62,617.86 [NAME] for the [NAME].

The issues

9. The tribunal identified the issues to be determined as follows:

(i) Whether the [NAME] (“the [NAME]”) are repairs or improvements and fall outside the terms of the lease?

(ii) Whether the [NAME] were unreasonable in extent?

(iii) Whether the [NAME] are reasonable in cost?

The hearing

10. At the hearing of this [NAME] the applicants appeared in person with Dr [NAME] appearing as the spokesperson for both applicants. The respondent was represented by Mr. [COUNSEL] of counsel. Each party provided an indexed bundle of documents to the tribunal containing the documents upon which they relied. Oral evidence was given by Dr [RESPONDENT] for the applicants and Mr. [APPELLANT] for the respondent.

5

The Applicant’s evidence

11. The applicants asserted that the [NAME] were [NAME] of improvement rather than repair or maintenance as there had been no [NAME] [NAME] partitions in situ in the roof space previously and therefore there had been nothing to “repair” or “maintain” in accordance with the terms of the leases. Dr [NAME] was unable to take the tribunal to any authorities to support his case, preferring the tribunal to use its expertise in determining this issue.

12. Notwithstanding, the applicants’ argument that all the [NAME] comprised [NAME] of improvement for which they had no liability to pay, the applicants had prepared a Scott Schedule detailing the [NAME] they otherwise took issue with. These items of work were as follows:

(i) Internal/External surveyors fees in the sum of £3,402.66 for the [NAME] (not agreed).

(ii) Dormer windows in the sum of £2,471.68 (agreed by respondent that this sum should be omitted).

(iii) Allowance for a plumber in every tank room at a cost of £339.97 (accepted by applicants).

(iv) Preparation clearance to working area and reinstatement of insulation at a cost of £365.63 (accepted by applicants).

(v) Screen off entrance in loft area/construct temporary wall/and secure [NAME] check door in Ply and Superlux at a cost of £310.63 (agreed by respondent to be omitted from final account).

(vi) [RESPONDENT] lining to sloping soffit (in lieu of wall and door) at a cost of £3,742.19 for [NAME] (not agreed).

(vii) Extra cover for boxing at the head of wall between rafters at a cost to the [NAME] of £26,766.37 (not agreed).

(viii) Extra cover for boxing – newly clad purlin at a cost for the [NAME] of £5,990.79 (not agreed).

(ix) One solid firewall at a cost for the [NAME] of £3,788.24 (not agreed).

(x) One solid wall with tank wall in-situ at a price to the [NAME] of £6,954.36 (not agreed).

(xi) Nine 1hr [NAME] doors and frames at a cost to the [NAME] of £3,592.19 (agreed by respondent only to the extent

6 that this should be reduced to 8 doors, otherwise not agreed).

(xii) To [NAME] seal pipe through wall at a cost to the [NAME] of £741.00 (cost of [NAME] agreed as reasonable but [NAME] unreasonable).

(xiii) Supply and fit 1 light and switch per partitioned area at a cost to [NAME] of £3,404.70 (not agreed).

(xiv) Safe platform working area at a cost to the [NAME] of £768.72 (accepted by applicants).

(xv) [NAME] administration fee at a cost of £398.75 per flat (not agreed).

13. Dr [NAME] submitted that in any event, the [NAME] could have been carried out at a considerably lesser cost had a horizontal barrier been constructed between the top floor flats and the roof space. Further, Dr [NAME] queried the installation of dormer windows in the roof and asserted these had not been included in the [NAME] although charged for by the respondent. Dr [RESPONDENT] also asserted that the installation of fixed electrical lighting in the partitioned spaces was unnecessary as other less permanent but equally appropriate provision for a source of light could have been found. Lastly, Dr [NAME] also challenged the amount of [NAME]’s fees and administration fees charged by the respondent as excessive.

14. Dr [RESPONDENT] also submitted to the tribunal that the applicants did not consider that the [NAME] had been necessary at all as there had been no recent change in the [NAME] [NAME] regulations and the roof space had not been built with partitions. Therefore, if the roof space was now considered to be unsafe, it was the responsibility of the respondent to remedy this at their own cost.

The respondent’s case

15. The respondent asserted that the [NAME] required by the [NAME] Authority’s Schedule of [NAME] [NAME] dated 29 June 2017 did not prescribe the exact [NAME] required, only that their nature and effect was sufficient to resolve the identified risks.

16. Mr. [RESPONDENT] submitted that the [NAME] identified by the respondent fell under the terms of lease either, as (i) [NAME] of repair or maintenance as provided for by clause 5(5)(a) or (ii) alternatively were required by the insurance covenant under clause 5(5)(c) in order to ensure that the building satisfied the insurance requirements against loss or damage by [NAME] or (iii) these [NAME] caught by the ‘sweeping up’ clause 5(5)(o) requiring the respondent to ensure the proper management and [NAME] of the building. Mr. [NAME] submitted that

7 on any of these three scenarios the [NAME] were not improvements but were necessary [NAME] of repair or maintenance or required for insurance purposes and for the proper maintenance and [NAME] of the [NAME]. As such, the applicants were liable to make their respective contributions towards the cost of these [NAME]. Mr. [NAME] also referred the tribunal to a number of cases to support his arguments including the first tier tribunal decision of [COMPANY] v [NAME]/00AH/LSC/2017/0435.

17. Mr. [NAME] submitted that the scope of the [NAME] was both necessary and reasonable as demonstrated by the inspection of the [NAME] Authority and Audit Notice. Further, Mr. [RESPONDENT] submitted that the respondent had acted reasonably by accepting and acting on the [NAME] advice of the supplier of the fireproof panels [NAME], after a meeting was held with their representative on 3 November 2017, at which further [NAME] were identified as being required, to take into account the need to safe-guard the purloins and rafter timbers not previously accounted for in the initial Scheme Brief. A further change to the original specification of [NAME] involved the provision of permanent louvred ventilation to the top floor of the Building as the other windows on the staircase were found to be openable.

18. It was accepted by the respondent that the cost of the [NAME] had increased significantly since their initial estimated cost. It was also accepted that this increase had arisen as a result of a detailed inspection of the roof space by the [NAME], [NAME] who subsequently had recommended the additional [NAME] and which were a cost that had not been originally provided for by the respondent or notified previously to the applicants. Mr. [RESPONDENT] submitted that as no alternative Schedule of [NAME] or costings had been provided by the applicants, the tribunal should accept [NAME]’s Schedule of Rates as reasonable. This Schedule of Rates had been adopted by the respondent which when compared with other contractors, provided the lowest costs. A certificate of completion dated 22 January 2019 was provided to the tribunal.

19. The only oral evidence for the respondent given to the tribunal was provided by Mr. [RESPONDENT], a [NAME] employed by [COMPANY] who spoke to his unsigned witness report dated 9th July 2019 (signed in the presence of the tribunal). Mr. [NAME] told the tribunal that after a survey of the building was carried out, a Scheme Brief was drawn up, which included the installation of 60 minute [NAME] break partitions within the roof space of the Building to compartmentalise the area in order to restrict the spread of any [NAME]; the installation of adequate lighting to the partitioned areas and the installation of doors to each compartmentalised area to provide access for routine maintenance to the services in the roof space which included overflow/water pipes and possibly some electrical wiring.

8 20. Mr. [NAME] told the tribunal that after an on-site meeting was held in November 2017 between the respondent’s representatives and [NAME], the suppliers of the [NAME] resistant walls, it was agreed that alterations to the Scheme Brief were required. These included increasing the diameter of the rafters in order to improve the [NAME] resistance; a lengthening of fixing screws; an extension of the boarding to the ridge tree and purlins and the addition of [NAME] sealant in identified gaps. These additional [NAME] were subsequently approved by the Respondent, thereby increasing the original cost of some elements of the [NAME] by around 45%.

21. Mr. [NAME] submitted that in the absence of any [NAME] reports or other evidence from the applicants to support their case, the tribunal should accept the evidence of the respondent as being the best available evidence.

The tribunal’s decisions and reasons

22. Despite the absence of alternative reports or costings from the applicants acting in person, the tribunal finds that the oral and documentary evidence to support the respondent’s case was significantly lacking in detail or clarity, not only in respect of the documentary evidence provided but also in the absence of significant and relevant witnesses who had been central to the decision [NAME] process behind these [NAME] and their costs. The tribunal finds that the process adopted by the respondent of ascertaining the nature and extent of the [NAME] required as well as their specifying and tendering process to be unsatisfactory and unsound, which had resulted in excessive, unnecessary and overly expensive costs. The tribunal found the lack of any independent [NAME] report to explain and justify these [NAME] to the tribunal to be a significant omission and contributed to the uncertain decision [NAME] of the respondent as to precisely what [NAME] were required in order to comply with the [NAME] [NAME].

The liability issue

23. The tribunal preferred the respondent’s submissions to those of the applicants when considering whether these were [NAME] of repair/maintenance or improvements. The tribunal accepts the respondent’s argument that these [NAME] fall within clause 5(5)(a) of the lease as [NAME] of repair or maintenance. This relevant part of which states that the respondent lessor covenants:

“To maintain and keep in good and substantial repair and condition:

(i) The main structure of the Building including the principal internal timbers and the exterior wall and the foundations and the roof thereof with its main water tanks main drains gutters and rain water pipes (other than those

9 included in the demise or in the demise of any other flat in the Building

(vi) all other parts of the Building not included in the foregoing sub-paragraphs (i) to (v) not included in this demise not included in the demise of any other flat or part of the Building and not let or intended for letting (sic)”

The extent and cost of the [NAME] issues

24. Despite the respondent having relied on the earlier [NAME] that had occurred in an identical nearby block as the justification for these [NAME], the tribunal was not provided with any evidence as to the cause of that [NAME], how it had spread or the recommendations made for the prevention and containment of any future fires. Further, the tribunal was not provided with a detailed independent [NAME] [NAME] assessment report of the subject property detailing the nature and extent of the [NAME] most suitable for the [NAME] in order to comply with the [NAME] Authority Audit. Instead, the respondent chose to rely upon non [NAME] employees and the views expressed at site meetings by the suppliers of the materials used to form the basis for these [NAME] rather than seeking the views of independent and objective experts in this area.

25. The tribunal finds that [NAME] to address the issues raised in the Schedule of [NAME] [NAME] were necessary and their costs reasonably occurred. However, the tribunal was not assisted by the absence of independent evidence from a [NAME] in ascertaining the scope of the [NAME] required. In considering the nature and extent of the partitioning [NAME] in the loft area of the Building and the diagrams produced by the respondent on page 329A of the respondent’s hearing bundle, the tribunal finds that only three of the five solid partitioning walls installed are likely to assist in preventing the spread of [NAME] from flat to flat with the remaining two walls are unlikely to be of much, if any effect. Therefore, the tribunal finds that 75% of the cost of the installation of the partitioning walls to be reasonable and payable by the applicants.

26. The tribunal finds that the additional [NAME] identified at the meeting held between [NAME] and the respondent’s representatives on 3rd November 2017 are excessive and unreasonable both in scope and cost and unjustified by any independent [NAME] evidence, despite the substantial increase in cost of the [NAME] that resulted from these additional [NAME]. Therefore, the tribunal finds the costs of these additional [NAME] are not payable by the applicants.

27. The tribunal finds that the installation of permanent doors and a fixed electricity supply and switches to the partitioned spaces to have been unnecessary and unreasonable. The tribunal finds that the limited access required to these areas could reasonably have been met by the

10 use of removable openings in the partitions and portable lamps, in order to carry out any necessary [NAME] to pipes supplying services to the [NAME], as and when they were required. Consequently, the tribunal finds the costs of these [NAME] to be excessive and unreasonable.

The [NAME]’s fees issue

28. Although Mr [NAME] submitted that the [NAME]’s fees in the sum of £3,402 per block (£91,844.82 for 27 blocks) was merited in light of the fact at least 2 surveyors as a [NAME] and a clerk of [NAME] had all been employed in delivering this major [NAME] project, he accepted that the evidence in support of the claim for the administration fees of £398.75 per flat (172,260 approx. for 27 blocks) was “less than cogent.” The tribunal finds the administration charges to be unexplained and unsupported by the evidence provided. The tribunal also finds the sums sought to be excessive and unreasonable and therefore allows only an administration fee of 25% of the sum sought per applicant’s flat.

The administration charges issue

29. The tribunal considers that these charges are unsupported by the evidence relied upon by the respondent and are excessive. As the tribunal accepts that some [NAME] have been reasonably required and carried out, it accepts that some administration charges which will have incurred. Therefore, having regard to the tribunal’s findings above the tribunal allows 25% of the administration charges sought from each applicant.

Section 20c

30. The respondent conceded that it would not seek to add the costs of this [NAME] to the service charges. Therefore, in s0 far as is necessary, the tribunal makes an order under section 20C of the 1985 determining that the costs of and associated to this [NAME] are not to be added to the service charges.

Signed: Judge Tagliavini

Dated: 18 October 2019

11

Rights of Appeal

By rule 36(2) of The Tribunal Procedure (First-tier Tribunal( ( Property Chamber) Rules 2013, the tribunal is required to notify he parties about any right of appeal they might have.

If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber), then a written [NAME] for permission must be made to the First-tier Tribunal at the regional office which has been dealing with the case.

The [NAME] for permission to appeal must arrive at the regional office within 28 days after the tribunal sends written reasons for the decision to the [NAME].

If the [NAME] is not made within the 28 day time , such [NAME] must include a request for an extension of time and the reasons for not complying with the 28 day time limit; the tribunal will then look at such reason(s) and decide whether to allow the [NAME] for permission to appeal to proceed, despite not being within these time limits.

The [NAME] for permission to appeal must identify the decision of the tribunal to which it relates (i.e. Give the date, the property and the case number), state the grounds of appeal and state the result the party [NAME] the [NAME] is seeking.

If the tribunal refuses to grant permission to appeal, a further [NAME] for permission may be made to the Upper Tribunal (Lands Chamber).

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • Tenants have the right to challenge the reasonableness of various charges and works under their lease terms.
  • Insufficient evidence supporting the necessity or reasonableness of charges often leads to challenges being successful.
  • Urgent and necessary repairs can bypass certain consultation requirements if deemed essential.
  • Landlords must adhere to the repairing covenant in the lease to maintain the property properly.
  • Administration charges imposed by landlords can be challenged for their reasonableness and payability.

❌ Tends to be rejected

  • (No significant factors listed in the provided cases that went against the claimant.)

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

It decided on the reasonableness and cost of fire safety works in a residential property.

Who was involved?

The tenant and the landlord were involved.

How did the court decide, and why?

The court decided that some fire safety works were unreasonable and limited the costs of others because they were excessive.

Which laws or rules were applied?

The Landlord and Tenant Act 1985, Section 20C, and the Commonhold and Leasehold Reform Act 2002 were applied.

What was the argument that mattered most?

The argument that mattered most was the reasonableness and cost of the fire safety works.

Was the decision for or against the person who brought the case?

The decision was for the tenant.

What does this mean for someone in a similar situation?

Someone in a similar situation can challenge the reasonableness and cost of fire safety works under their lease agreement.

What evidence or documents mattered?

Evidence and documents related to the cost and necessity of the fire safety works mattered.

Can a decision like this be appealed?

Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).

Is it worth getting a solicitor for a case like this?

Yes, it is recommended to get a solicitor for a case like this.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.