First-tier Tribunal Rules on Payability of Holiday Park Service Charges
📌 In brief
The First-tier Tribunal ruled on the payability and reasonableness of service charges for a holiday a person. The charges include playground reserve charges, repairs, insurance, and contributions to reserve funds. The ruling was made under the Landlord and Tenant Act 1985 sections 27a and 20ZA.
⚖️ Legal holding
Service charges for repairs, insurance, and reserve funds are reasonable and payable.
📖 Technical summary
The Tribunal ruled on the payability and reasonableness of service charges for a holiday a person.
📜 Headnote Official document
The Tribunal ruled on the payability and reasonableness of service charges for a holiday park, including playground reserve charges, repairs, insurance, and contributions to reserve funds. The ruling was made under the Landlord and Tenant Act 1985 sections 27a and 20ZA.
📚 Full judgment Official document
OUTCOME: Allowed
© CROWN COPYRIGHT
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Tribunal Case reference : CHI/00MW/LSC/2022/0059 CHI/00MW/LSC/2022/0073
County Court claim : H4GQ4T5N Properties :
[NAME] and others Sandown Bay Holiday Centre, [ADDRESS], Sandown, Isle of Wight, [POSTCODE]
Applicant : [redacted] : [COUNSEL] of Counsel instructed by [COUNSEL] [NAME] Respondents :
[redacted] and [NAME], Chalet 12 (2) [NAME] 20 (3) [NAME] 21 and 184 (4) [NAME], Chalet 25 (5) [NAME], Chalet 26 (6) [NAME] [NAME], Chalet 28 (7) [NAME], Chalet 48 (8) [NAME[NAME], [NAME] (9) [NAME] [NAME], Chalet 60 (10) [NAME], Chalet 88 (11) [COUNSEL], Chalet 127 (12)
Representative
:
[COUNSEL] of Curtis Whiteford Crocker Solicitors Type of application :
Transferred Proceedings from County Court in relation to Service Charges Section 27a Landlord and Tenant Act 1985- determination of service charges [POSTCODE] Landlord and Tenant Act 1985 dispensation from consultation
2
Tribunal member(s)
:
Judge J [NAME] Judge : Judge J Dobson Dates of Hearing : 23rd February 2023 and 3rd March 2023 Date of Re- convene : 30th March 2023 Date of Decision : 12th June 2023
DECISION
Those parts of this decision that relate to County Court matters will take effect from the ‘Hand Down Date’ which will be the date this decision is sent to you.
Summary of the Decision of the Tribunal
1. The service charges demanded by the Applicant in the proceedings from various of the Respondents and in dispute for the service charge years 2017- 2018 to 2022 (which is not all of the service charges for any given period) are payable and reasonable in the overall sum of £589.77 per chalet, which sum is comprised of the following amounts in respect of the particular elements, per chalet, of service charge in dispute:
Playground reserve charges
£ 35.70 Repairs to paths and rebuilding retaining walls £ 394.47 Contributions to reserve funds/ general contingency £ 159.60
2. The service charges in respect of insurance demanded by the Applicant in the proceedings from the 1st Respondents is payable and reasonable in the sum of £181.92.
3. As to costs, firstly the Applicant may not recover the costs of the proceedings, whether solicitor’s costs, disbursements of managing agent’s fees, as service charges.
3 4. As to costs between the Applicant and the First Respondent, any entitlement of either of those parties to costs and the summary assessment of such costs, if not agreed, will be determined following receipt of any representations from those parties.
Summary of the Decision of the County Court
5. The Applicant succeeds against the Respondent in the sum of £421.07 in respect of the claim for service charges demanded between 20th February 2020 and 25th February 2021.
6. The Applicant succeeds in the sum of £181.92 in respect of the claim for insurance.
7. The Applicant succeeds in respect of ground rent in the sum of £206.93.
8. The Applicant is entitled to interest on the total of £809.92 of £108.oo.
9. The remainder of the Applicant’s claims are dismissed.
10. As to costs, firstly the Applicant may not recover the costs of the proceedings, whether solicitor’s costs, disbursements of managing agent’s fees, as service charges.
11. As to costs between the Applicant and the First Respondent, any entitlement of either of those parties to costs and the summary assessment of such costs, if not agreed, will be determined following receipt of any representations from those parties.
Background
12. The [COMPANY] (company number 03008262) is the freeholder of Sandown Bay Holiday Centre (“[NAME]”). The director of the Applicant is one Mr [APPELLANT]. The Applicant is at least in part a building/ construction company, although also the owner of various properties in Hampshire, including [NAME].
13. The [NAME] owner who operated [NAME] had gone into receivership in 2011. The Applicant purchased from the administrators of the [NAME] owner on 13th January 2017. The Applicant employs a managing agent to manage [NAME]. That agent was formerly [NAME] which had indeed managed [NAME] since 2011 when first appointed by the [NAME] of the [NAME] owner. More recently, January 2011, [NAME] were taken over by [RESPONDENT].
14. The 1st Respondent is [NAME] of [NAME] (“the Property”), having become so back in 2007. The other Respondents are the [NAME] of the
4 other chalets (“the Other Chalets “) listed above, save for [NAME] and [NAME[NAME] who are no longer [NAME] of [NAME], having sold that in 2022. A schedule was provided by the Applicant of the respective purchase dates, of which six post-date the Applicant’s purchase of [NAME].
15. [NAME] is a holiday [NAME], as the name indicates, and not a residential [NAME]. It is located on a hillside to the east of the island, by the coast and on the [NAME] site of military buildings, of which a barrack block and later extensions to it became a building the building referred to as the [NAME] (which term is adopted in this Decision). There are 187 single- storey holiday chalets on [NAME]. Those are brick and block constructions not mobile homes. Adjacent to [NAME] is the [NAME] site of a [NAME].
Procedural History
16. The Applicant filed a claim in the County Court Business Centre under Claim No. H4GQ4T5N by Claim Form dated 27th October 2021 [3- 4] in respect of sums said to be due from the [NAME]. The claim related to unpaid service charges, insurance (stated separately to service charges more generally), ground rent, interest and costs demanded between 20th February 2020 and 25th February 2021. The stated value of the claim on the Claim Form was £2884.19, excluding the court fee paid, which reflected that value and excluding legal costs on issue (although the £2884.19 also included £180 legal costs said to be payable in accordance with the terms of the [NAME]).
17. The 1st Respondent filed a Defence dated 30th November 2021 [6 onwards], which included an argument that no compliant demands had been made and also sought a transfer to the Tribunal.
18. The case was subsequently transferred to the administration of the Tribunal and for the determination by the Tribunal of the payability and reasonableness of the residential service charges and also determination by the Tribunal Judge sitting as a County Court Judge of the Court elements, pursuant to the Order of District Judge Grand dated 12 April 2022. The County Court elements of the case had been allocated to the Small Claims Track. The application was given the first above-listed case number.
19. An application was separately made by the 1st and the other Respondents dated 24th June 2022 for a determination by the Tribunal as to the payability and reasonableness of seven aspects of the service charges for the service charge years 2017- 2018 to 2022 inclusive. The scope of that application therefore extends beyond that of the claim against the 1st Respondent and includes the entire period of ownership of [NAME] by the Applicant. Consequently, the Tribunal decision is required to address both the period of the Applicant’s claim and the other relevant years, the [NAME] of which will be relevant to the County Court but the latter of which will not. That was given the second above-
5 listed case reference. The costs which the service charges in dispute were demanded to contribute to amounted to very broadly something in the region of £350,000. Given that such costs are divided between the [NAME], the sums were necessarily rather smaller per [NAME].
20. In addition, the Applicant has, on 23rd February 2023- the final hearing date (see below) made an application for dispensation from consultation requirements in respect of major works previously carried out. That application is made in respect of each of the Respondents. The Applicant is properly the applicant, and the Respondents are properly the respondents to that application. Necessarily, that application did not form part of the bundle but no specific pages of it require mention in this Decision. It was not given a separate reference number given its timing.
21. As previously identified in Directions, the Respondents, whilst so termed, are in practice the applicants in respect of their above applications to the Tribunal and so to any extent that any burden of proof or otherwise may apply to the Tribunal applications, it applies to the Respondents as being the applicants in those applications and/or to the Applicant as respondent in those applications.
22. There have been various Directions given, including at two case management hearings. The parties requested that the case was stayed for a time to facilitate a potential resolution of the dispute, although the case was not in consequence stayed. Rather dates were put back to build in a time for any resolution to be achieved. As will be apparent, that did not enable matters to be resolved in the event.
23. The Applicant was directed to provide a bundle for the final hearing and did so. The bundle comprises, including the index, of 673 pages.
24. The bundle helpfully included plans of [NAME] and various photographs of the [NAME], both as it formerly looked [460-478] and following the demolition of various [NAME] parts of it. In light of those and the other information contained within the bundle, the Court and Tribunal were content that it was not necessary to inspect [NAME] in order to determine the particular issues raised in this case. The parties had not requested that an inspection take place.
25. It was necessary to arrange for the Tribunal to reconvene to consider matters further, which occurred on 30th March 2023, as regrettably being the first date on which the Tribunal members were both available. Necessarily matters remained in abeyance until then.
26. There are several different elements and quite a number of determinations required, some involving findings of fact. The length of the Decision itself reflects that. The different elements are dealt with in turn and with sub- headings identifying them for ease of reference.
6 27. The Tribunal and Court nevertheless sincerely apologise for the delay in the provision of this Decision since the reconvene, which exceeded expectations.
28. Whilst the Court and Tribunal make it clear that they have read the bundles in full, many of the documents are not referred to in detail, or in many instances at all, in this Decision, it being unnecessary to so refer. Where the Court and/ or Tribunal does not refer to pages or documents in this Decision, it should not be mistakenly assumed that they have been ignored or left out of account. Insofar as reference is made to any specific pages from the bundle in this Decision, that is done by numbers in square brackets [ ], as occurs in the preceding paragraphs where appropriate, and with reference to PDF bundle page- numbering. Much of the documentation, for example pages of invoices and supporting documents [principally 247- 459], was the subject of limited if any mention.
29. This Decision seeks to focus on the key issues and, not least given there are several different elements to this case, does not cover every last factual detail. The omission to therefore refer to or make findings about every statement or document mentioned is not a tacit acknowledgement of the accuracy or truth of statements made or documents received. Many of the various matters mentioned in the bundle or at the hearing do not require any finding to be made for the purpose of deciding the relevant issues in the case. Findings have not been made about matters irrelevant to any of the determinations required. Findings of fact are made in the balance of probabilities.
The [NAME]
30. A copy of the original [NAME] of the 1st Respondent of [NAME] was provided within the bundle [91 onwards]. That [NAME] (“the [NAME]”) is dated 23rd June 2000. The parties to this dispute were not the original [NAME]. The term of the [NAME] is 125 years from 1st January 2000.
31. It was common ground that the leases held by the other Respondent are in the same or substantively the same terms at least in respect of any provisions relevant to the determination of the matters for determination in this case, although not it was said in identical terms.
32. There are certain relevant definitions in the [NAME], including, most notably, the following:
“The [NAME]”- the freehold land and property known as Sandown Bay Holiday Centre (Recital paragraph (1)).”
And “the demised premises”- the holiday chalet plus associated rights described in the First Schedule.
33. Clause 6(3) provides the Applicant has an obligation to:
7
“Maintain in good substantial repair the structure and exterior of the demised premises (as the same is further defined by Clause 1 Part 1 of the Fifth Schedule hereto) and all such sewers drains pipes wires party structures and other conveniences and parts of the [NAME] as may be enjoyed or used by one of the chalets in the [NAME] in common with others”
34. The Applicant is also (clause 6(1)) required to insure and keep insured the Property and the Other Chalets.
35. The costs and expenses to which the Respondents are required to contribute are provided for in the Fifth Schedule to the [NAME] [109 onwards]. Part I of the Schedule relates to the particular chalet demised to any given Respondent. Paragraphs 1. and 2. of the Fifth Schedule require the Respondents to pay repairing, cleaning and decorating costs and the cost of insuring the demised premises.
36. Part II of the Fifth Schedule identifies costs related to the wider [NAME] to which the Respondents must contribute. It merits setting those out relatively fully, given that is where the heart of the dispute lies. The costs are in respect of the following:
“1. All maintenance repair renewal cleansing and decoration effected for the purpose of keeping in good and substantial repair
(a) The boundary walls and fences of the common parts of the [NAME] b) The common access roads footpaths forecourt yard and pathways within the curtilage of the [NAME] (including the necessary lighting thereof)
2. The maintenance in good working order and repair of all sewers drains channels watercourses gutters rainwater and soil pipes sanitary apparatus water tanks wires and cables in under and upon the [NAME] and serving the same and excluding nevertheless any which exclusively serve any one chalet or other building in the [NAME] 3. ………… 4. Keeping the gardens and grounds of the [NAME] generally in neat and tidy condition and tending and renewing all lawns flower beds shrubs and trees forming part thereof and keeping the same planted free from weeds and the grass cut as [NAME] considers necessary 5. The costs of periodically inspecting examining maintaining and overhauling any part of the [NAME] for the purpose of performing the Lessors obligations hereunder and any other costs properly incurred by [NAME] for the purpose of complying with such obligations 6. ………….
7. The costs of insuring the [NAME] in respect of any risks for which [NAME] may be liable as an employer of persons working on the [NAME] in connection with the services referred to in this Schedule or as owner of the [NAME] or any part thereof (but excluding the individual chalets and other buildings thereon)
8. The cost of supplying providing overhauling and keeping in good and serviceable order and condition all appurtenances appointments fixtures and fittings bins receptacles tools appliances materials equipment and other things which [NAME] may deem desirable or necessary for the maintenance appearance upkeep or cleanliness of the [NAME] or any part thereof
8 9. All costs incurred in provision and supply of any other services or facilities relating to the [NAME] or part of it provided by [NAME] from time to time during the Term and not expressly mentioned herein 10. The establishment and maintenance of a [NAME] to provide for any items of future capital expenditure foreseen by [NAME]
11. The fees of [NAME] and [NAME]’s agents for the general management of the [NAME] and all other expenses (if any) incurred by [NAME] in and about the maintenance and convenient management and running of the [NAME] 12. ……….. 13 ………..
14. When any repairs redecorations or renewals are carried out by [NAME] under either part of this Schedule it shall be entitled to charge as the expenses or costs thereof of its normal charges (including profit in respect of such work)
37. The obligation on the Respondents to make the relevant payments is contained in clause 3(1) of the [NAME] in respect of the rent. The Respondents are also required by clause 3(3) to repair and maintain the demised premises, with related obligations in clause 4.
38. The obligation to pay the service charges is contained in clause 5 of the [NAME]. The level of contribution of the 1st Respondent to service charges is provided for in and is stated to be the full costs of insurance of the Property and 1/188th of the costs of the Applicant fulfilling its other obligations. The same applies to the other Respondents in respect of the insurance for the Other Chalets and the Applicant’s other obligations. As to why 1/188th where there are 187 chalets was not made clear.
39. The service charge mechanism provides (clause 5 (a)) for the Applicant to estimate the service charges for the given subsequent year by 31st August. The service charge year runs from 1st September to 31st August of a given year.
40. The estimated service charges are to be the estimated amount required to meet the obligations in the Fifth Schedule for the coming year, which shall be based on the previous year’s expenditure but allowing for costs reasonably to be foreseen beyond that. The Applicant may also (5(b)) include an additional sum if for any reason it is apparent that an estimate based on the above will not cover the whole cost to be incurred in the coming year, in which case the Applicant may determine the estimated additional amount.
41. The Applicant must by 31st August in any given year determine the actual expenditure in the preceding year and supply to [NAME] a copy of the accounts in respect of those, producing such supporting receipts as are available (5(c)). There is then provision for a balancing credit or charge. Any credit may be carried over to a [NAME] where related to costs reasonably foreseen or for the replacement of capital equipment.
9 42. Payment is required to be made by a [NAME] within fourteen days of the demand for estimated or balancing service charges (5(d)). All of the above is an essentially common type of arrangement.
43. There is also a requirement pursuant to clause 3(7) to pay all costs, charges and expenses incurred by the Applicant incidental to the preparation of a forfeiture notice, set out more fully below insofar as costs are addressed in this Decision.
44. The Regulations in the Second Schedule provided that the chalets may only be used as holiday chalets and during the times permitted.
45. The Fourth Schedule gives (2(a)) the Applicant the right:
“To execute works and erections and to construct buildings or to rebuild alter or use any of the adjoining or neighbouring land or buildings or to build upon or over add to or extent the [NAME] …….. in such manner as shall be approved by [NAME] …….”
and (2(c) gives the further right:
“To make such alterations as it may think in the position or extent of such of the gardens and grounds within the [NAME] as may from time to time be allocated by [NAME] for the use of the occupants of the Chalets on the [NAME]”
46. The [NAME] more generally provides for the parties to perform their obligations.
47. Whilst there has been no variation of the [NAME] or any other [NAME] the Tribunal understands, the evidence given was that in practice service charges are demanded by two instalments on 1st September and 1st March of any given year. No point was taken about that and at first blush the Tribunal perceives that the net effect was to delay the payment of half of the estimated service charges, which would appear to have been capable of being demanded all in August/ September. As no issue arises, it is unnecessary to address this aspect further.
The Construction of Leases
48. It is well- established law that the Leases are to be construed applying the basic principles of construction of such leases, and where the construction of a [NAME] is not different from the construction of another contractual document, as set out by the Supreme Court in Arnold v Britton [2015] UKSC 36 in the judgment of Lord Neuberger (paragraph 15):
“When interpreting a written contract, the court is concerned to identify the intention of the parties by reference to “what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the
10 contract to mean”, to quote [NAME] in [COMPANY] v [COMPANY] [2009] UKHL 38, [2009] 1 AC 1101, para 14. And it does so by focussing on the meaning of the relevant words, in this case clause 3(2) of each of the 25 leases, in their documentary, factual and commercial context. That meaning has to be assessed in the light of (i) the natural and ordinary meaning of the clause, (ii) any other relevant provisions of the [NAME], (iii) the overall purpose of the clause and the [NAME], (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party’s intentions.”
49. Context is therefore very important, although it is not everything. Lord [NAME] went on to emphasise (paragraph 17):
“the reliance placed in some cases on commercial common sense and surrounding circumstances (e.g. in Chartbrook [2009] AC 1101, paras 16- 26) should not be invoked to undervalue the importance of the language of the provision which is to be construed. The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader, and, save perhaps in a very unusual case, that meaning is most likely to be gleaned from the language of the provision. Unlike commercial common sense and the surrounding circumstances, the parties have control over the language that they use in a contract. And again save perhaps in a very unusual case, the parties must have been specifically focusing on the issue covered by the provision when agreeing the wording of that provision.”
The Hearing
50. The Judge sat at Havant Justice Centre. The other attendees, including [NAME], attended remotely.
51. Mr [COUNSEL], counsel, represented the [COMPANY]. The Respondents were all represented by Mr [COUNSEL], solicitor.
52. Mr [COUNSEL] provided a [NAME] late on the afternoon prior to the hearing and not seen by the case officer until the morning of the hearing. That amounted to some 24 pages and so it may be doubtful that the term [NAME] is appropriate. Nevertheless, it was of assistance in clarifying the Applicant’s position. [ADDRESS] and Tribunal were able to consider that prior to commencement of the hearing. Mr [NAME] also provided a bundle of authorities 150 pages long. [ADDRESS] and Tribunal were not also able to read those in the hour from the case officer forwarding the [NAME] and authorities until the commencement time of the hearing.
53. One matter which arose at the hearing and is touched upon above is that the Applicant had not made any prior application for dispensation from consultation in respect of the major works to the [NAME], such that if the Tribunal determined that the Applicant would otherwise be able to recover the costs of such works as service charges, the amount of such recovery was £250 per [NAME] absent compliance with
11 consultation requirements (which it was accepted had not occurred) or the grant of an application for dispensation.
54. The Applicant was permitted to make such an application, on the basis that the Respondents were alert to the issues and able to deal with them. However, the Tribunal was not prepared to deal with such an application purely on the basis of mention of it in a witness statement, [NAME] argument or similar but only on a proper application being filed and the fee paid. The Tribunal concluded that requiring any other statements of case or witness statements was unnecessary. The Tribunal would treat it as read that the Respondents objected to dispensation being granted.
55. Mr [NAME] had objected, being understandably critical of the lack of an application for dispensation despite the professionals involved with the Applicant. He also made a point that all [NAME] ought to be able to respond, although that would have required an application to be made by the Applicant in respect of dispensation against all [NAME], which the Applicant did not make. The Tribunal was mindful that all [NAME] would be expected to be respondents and that there was a risk of distinction between the particular Respondents and the other [NAME]. In the event, dispensation was of less import than it might have been, for the reasons explained below and so that potential issue need not be dwelt on.
56. A smaller matter arose as to the breakdown of the claim between the elements listed of service charges, insurance and ground rent.
57. Oral evidence was received from Mr [NAME], of [NAME] and who runs their Isle of Wight office, but giving evidence in the capacity of a lay witness and not as a surveyor expert witness, on the one hand and Mr [RESPONDENT], the 1st Respondent, on the other. The Tribunal asked various questions of witnesses seeking clarification of matters advanced. The Tribunal additionally received written evidence from Mr [NAME] [72 onwards] and from Mr [NAME] [588 onwards]. The contents of that evidence are not set out here but are referred to as appropriate below when the Court and / or Tribunal address the relevant issues. Both of those witnesses had provided written statement and much of what Mr [NAME] said in his reflected a 23 pages statement of case on behalf of the Applicant [9-33].
58. The time taken to receive evidence was such that it was not possible to receive closing submissions. The Tribunal determined, with the agreement of the advocates, that in this instance the better course was to receive submissions orally rather than in writing.
Accordingly, a further hearing was fixed for 3rd March 2023 for those oral submissions to be made and to enable the Court and Tribunal to deal with any ancillary matters. The hearing was adjourned part heard until 3rd March 2023, concluding around lunchtime on that date
12 59. Both Mr [NAME] and Mr [NAME] made oral closing submissions at that hearing. Those are not repeated here but are referred to as appropriate in the consideration of the specific issues below.
60. In respect of [NAME] and [NAME[NAME], who are no longer [NAME] of [NAME] having sold that in 2022, the Tribunal sought clarification of the basis on which the parties asserted, if they did, that the particular Respondent was entitled to any determination as to the payability and reasonableness of the service charges.
61. In closing, Mr [APPELLANT] submitted that the Landlord and Tenant (Covenants) Act 1985 applied, which the Tribunal accepts. Section 5 provides that on an assignment of whole, the tenant is released from the covenants generally. Section 17 was also referred to, which provides for the situation where a [NAME] tenant would remain liable for what is described as a fixed charge (which term includes variable service charges much as might be imagined it would not) and requires, amongst other things, a landlord to service notice on the [NAME] tenant as required for the liability to arise. He also confirmed the position in terms of the [NAME] periods of liability for service charges, accepting [NAME] liability only arose on registration. These points are returned to in the Conclusion below insofar as required.
62. The Tribunal and Court are grateful to all of the above for their assistance with this case.
The Tribunal matters
The jurisdiction of the Tribunal
Service Charges
63. The Tribunal has power to decide about all aspects of liability to pay service in relation to residential properties and can interpret the [NAME] where necessary to resolve disputes or uncertainties. Service charge is in section 18 of the Landlord and Tenant Act 1985 (“the Act”) defined as an amount:
“(1) (a) which is payable, directly or indirectly, for services, repairs, maintenance[, improvements] or insurance or the landlord’s costs of management and (2) the whole or part of which varies or may vary according to the relevant costs.”
64. The Tribunal can decide by whom, to whom, how much, when and how a service charge is payable (section 27A). Section 19 provides that a service charge is only payable insofar as it is reasonably incurred and the services or works to which it relates are of a reasonable standard. The Tribunal therefore also determines the reasonableness of the charges. The amount payable is limited to the sum reasonable.
13 65. The Tribunal may take into account the Third Edition of the RICS Service Charge Residential Management Code (“the Code”) approved by the Secretary for State under section 87 of the Leasehold Reform Housing and Urban Development Act 1993 and effective from 1 June 2016. The Approval of Code of Management Practice (Residential Management) (Service Charges) (England) Order 2009 states: “Failure to comply with any provision of an approved code does not of itself render any person liable to any proceedings, but in any proceedings, the codes of practice shall be admissible as evidence and any provision that appears to be relevant to any question arising in the proceedings is taken into account.”
66. There are innumerable case authorities in respect of several and varied aspects of service charge disputes, but most have no obvious direct relevance to the key issue in this dispute. In a number of case authorities, for example Knapper v Francis [2017] UKUT 003 (LC) (although in that case there were more specific points) it has been held that where service charges demanded were so demanded on account, the question is whether those demands were reasonable in the circumstances which existed at that date. It is for a landlord to demonstrate the reasonableness of any estimate on which the on- account demands are based, see for example the case of [COMPANY] v [NAME] Association [COMPANY] [2018] UKUT 252 (LC). [COMPANY] v [NAME] and another [2017] UKUT 382 (LC) (and also earlier authorities such as [NAME] v De [NAME] [2013] UKUT 0134 (LC)) applies such that there is a two- part approach of considering whether the decision making was reasonable and whether the sum is reasonable.
67. It is also well established that a [NAME]’s challenge to the reasonableness of a service charge (or administration charge) must be based on some evidence that the charge is unreasonable. Whilst the burden is on [NAME] to prove reasonableness, [NAME] cannot simply put the lessorto proof of its case. [NAME] must produce some evidence of unreasonableness before [NAME] can be required to prove reasonableness (see for example [NAME] v [COMPANY] [2005] EW Lands LRX 26 2005, a case touched upon in Mr [NAME] [NAME] as mentioned in another case cited by him but in any event well known to the Tribunal- the other case adds nothing requiring mention). The Tribunal is entitled in determining the service charges payable whether any sum should be off- set in consequence of any breach by [NAME], where relevant.
Dispensation from consultation
68. In respect of a consultation process, section 20 of the Act applies.
69. Section 20(1) provides that the “relevant contributions of tenants” will be: “limited in accordance with subsection (6) or (7) (or both) unless the consultation requirements have been either— (a) complied with in relation to
14 the works or agreement, or (b) dispensed with in relation to the works or agreement by (or on appeal from) the appropriate tribunal.” Whereas the Act refers to tenants, as Acts tend to, that means [NAME], the term adopted in this Decision, under long leases.
70. The related Service Charges (Consultation Requirements) (England) Regulations 2003 (“the Regulations”) – specifically regulation 6- provide that the relevant sum is more than £250 per [NAME], so where [NAME] undertakes qualifying works with a cost per [NAME] above that the relevant contribution of each [NAME] (jointly where more than one under any given [NAME]) will be limited to that sum unless the required consultations have been undertaken or the requirement has been dispensed with by the Tribunal. An application may be made retrospectively.
71. The provisions of Schedule 4 Part 2 of the Regulations apply to a consultation of this nature but the specific requirements do not require exploration in detail in this instance.
72. Section 20ZA provides that on an application to dispense with any or all of the consultation requirements, the Tribunal may make a determination granting such dispensation “if satisfied that it is reasonable to dispense with the requirements”.
73. The appropriate approach to be taken by the Tribunal in the exercise of its discretion was considered by the Supreme Court in the case of [COMPANY] v [NAME] et al [2013] UKSC 14. The leading judgment of Lord [NAME] explained that a tribunal should focus on the question of whether [NAME] will be or had been prejudiced in either paying where that was not appropriate or in paying more than appropriate because the failure of [NAME] to comply with the regulations. The extent of the failure and other matters previously taken into account are not relevant considerations. The requirements were held to give practical effect to those two objectives and were “a means to an end, not an end in themselves”.
74. The factual burden of demonstrating prejudice falls on [NAME]. [NAME] must identify what would have been said if able to engage in a consultation process. If [NAME] advances a credible case for having been prejudiced, [NAME] must rebut it. The Tribunal should be sympathetic to [NAME](s).
75. Where the extent, quality and cost of the works were in no way affected by [NAME]’s failure to comply, Lord [NAME] said as follows:
“…………. I find it hard to see why the dispensation should not be granted (at least in the absence of some very good reason): in such a case the tenants would be in precisely the position that the legislation intended them to be- i.e. as if the requirements had been complied with.”
15 76. The “main, indeed normally, the sole question”, as described by Lord [NAME], for the Tribunal to determine is therefore whether, or not, [NAME] will be or has been caused relevant prejudice by a failure of the Applicant to undertake the consultation prior to the major works and so whether dispensation in respect of that should be granted.
77. The question is one of the reasonableness of dispensing with the process of consultation provided for in the Act, not one of the reasonableness of the charges of works arising or which have arisen.
78. If dispensation is granted, that may be on terms.
79. There have been subsequent decisions of the higher courts and tribunals of assistance in the application of the decision in Daejan but which are not relied on by the parties and which do not require specific mention in this Decision.
80. The Applicant does specifically rely- and Mr [APPELLANT] [NAME] cites- a case authority of Phillips v Francis [2014] EWCA Civ 1395, [2015] 1 WLR 741, of which the Tribunal is aware and understands that Mr [NAME] was similarly aware, a case relating to chalets on a holiday site were held to be dwellings within the meaning of the Act and where the site owner carried out major works without consulting in accordance with the Regulations. A particular issue was whether the work carried out was all part of one planned single set of works, so that the Consultation Regulations threshold (£250 per [NAME]) was met or a series of disparate pieces of work so that the threshold was not crossed. The first was described as the ‘aggregate approach’ and the latter as the ‘sets approach’. [ADDRESS] of Appeal approved the ‘sets approach’, holding that the question of what a single set of qualifying works comprises is one of fact and degree. It was described as a multi- factorial question, the answer to which should be determined in a common- sense way taking into account all relevant circumstances. Various relevant factors were identified, which the Tribunal returns to when considering this aspect of the dispute below.
Are the [NAME] Service Charges payable and reasonable?
81. The Applicant made a concession, set out in the [NAME], that the Applicant no longer sought some of the legal costs which had been incurred and included in the service charges from the majority of the Respondents. Such costs were the costs of pursuing [NAME] in default. The exception was the 1st Respondent, against whom the Applicant sought an award of its costs of his own asserted default. Rule 13 of The Tribunal Procedure (First Tier Tribunal) (Property Chamber) Rules 2013 was referred to, although those relate specifically to wasted costs and to such part of those costs as related to the Tribunal part of the proceedings.
16 82. The Respondents also made a concession following the evidence of Mr [NAME] in respect of the paths and retaining walls item of the service charges. It was accepted that the charges did not relate to matters connected to the new chalets to be developed- see below- and no argument was pursued further that they were not payable and reasonable.
83. The Tribunal first addresses the question of whether any of the service charges remaining in dispute have been demonstrated by the Applicant to be payable.
Validity of demands
84. The 1st Respondent specifically raised in his pleaded case the question of whether service charge demands made had been valid. Meeting requirements for service of demands is a significant matter. Where the Applicant has failed to demonstrate valid demands, the reasonableness of any service charges included in such demands and the applicable test does not arise.
85. In terms of statutory requirements, meeting those requirements is so fundamental that the Tribunal often considers that it is entitled as an expert Tribunal to consider such matters irrespective of whether the points have been raised by a [NAME], although necessarily that is where the Tribunal considers it appropriate to do so, which is not always. Indeed, quite commonly such matters are not raised by [NAME], who are unaware of those statutory requirements. It ought to be simple to demonstrate compliance where that has happened. In respect of meeting requirements of the [NAME], arguably that is even more fundamental. Certainly, a party relying on a right to demand service charges and recover unpaid service charges pursuant to the terms of a [NAME] should expect to demonstrate that the given [NAME] permits the recovery of such service charges, irrespective of what the specific sum may be. The Tribunal is entitled where appropriate and given service charges are demanded based on an entitlement in the [NAME] to so demand them, to consider whether the requirements of the [NAME] have been shown to be met.
86. Given that the 1st Respondent did take a point and is represented, it is not necessary to dwell longer on the approach which might have been taken irrespective of that. The particular and only point taken as to validity was that of whether the address provided for the Applicant landlord complied with section 47 of the Landlord and Tenant Act 1987 and so the Tribunal confines itself to that point in this instance.
87. The registered office of the Applicant is [NAME], 132a [ADDRESS], [POSTCODE]. The address on the service charge demands [e.g. 152] for the Applicant is [NAME], Wicor Path, Fareham, Hampshire, [POSTCODE], described in the witness statement of Mr [NAME] as its correspondence address and the address of Mr [APPELLANT].
17
88. The Applicant contended that the address complied as being one of several from which its business is carried out, and as such satisfies the test. The Applicant relied on Mr [APPELLANT] evidence about the nature of the Applicant and Mr [APPELLANT] role and working practices, which it asserted to be unchallenged. That written evidence was that Mr [APPELLANT] runs the day-to-day business of the Applicant from his home.
89. The Respondent had asserted that the address given was a “care of” address) or the address of an agent, and so the sort of address criticised in a case authority provided by [NAME] of [COMPANY] v Martin [2012] L. & T.R. 23. That determined the address of the landlord’s agent to be insufficient. The Upper Tribunal) Lands Chamber) explained as follows:
“The purpose of the requirement in s.47 to include in any demand the name and address of the landlord is to enable a tenant to know who his landlord is, and a name alone may not be sufficient for this purpose. To provide an address at which the landlord can be found assists in the process of identification…………..The address given was not the landlord’s address. It was not the company’s registered office or the place from which it carried on business ”
90. In closing Mr [NAME] said that the point has “largely fallen away”. He noted that a care off address was given towards the top of the demands, which was clearly correct. He accepted that a further- and the relevant- address was shown lower down. As there was no complete concession, the Tribunal determines the point.
91. The Tribunal agrees with the Applicant that the address provided on the service charge demands met the requirement of section 47 as being an address of the Applicant (and met the requirements of section 48).
92. The Tribunal accepts the evidence given by Mr [NAME] that the address given is an address from which business of the Applicant is carried out, by the sole director of the company [NAME]. The address of a director from where he conducts the business is not a care of address nor the address of an agent. It is not the sole address and it is not the registered office. Hence the address is an address of the landlord, rather than “the address”. However, “the address” singular necessarily assumes there to be only one and it was accepted by the Upper Tribunal that where the landlord has more than one address, the landlord may choose which address to use. The Applicant landlord has chosen [NAME].
93. The Tribunal observes that the relevant address is not as clearly displayed as it perhaps could be, being contained in a block of narrative. On the other hand, that does identify on the top line that notice is given of an address for the purpose of section 47 and 48 of the Landlord and Tenant Act. The year given for that Act, 1984 not 1987, is incorrect but not point was argued about that and so the Tribunal does
18 not take one, making no comment as to any preliminary assessment of any merits. The address is also expressed to not only be the address for notices by also to be the registered office address, which the evidence indicates it is not, but about which the Tribunal also makes no other comment.
Decision re validity
94. The Tribunal determines insofar as the issue was argued that the demands were valid.
The [NAME]
95. It was not identifiably in dispute that the [NAME] was in a significant state of disrepair and was contaminated with white and brown asbestos. Neither was it in dispute that in September 2019, Mr [NAME] told the [COMPANY] that he proposed to demolish parts of the [NAME] and would not re-open it.
96. The [NAME] had previously (until the receivership in 2011) operated as a bar and provided food. That had not been for the exclusive use of residents of [NAME] but rather was for general public use and the residents derived no profit or other identified benefit other than that a facility existed on [NAME]. Mr [NAME] said in evidence that it was operated by the then freeholder but not connected with the site. The [NAME] had been closed and had been fenced off for a significant time prior to the purchase of [NAME] by the Applicant.
97. It was common ground that the Applicant received an estimate from [APPELLANT] dated 4th November 2019 for demolition, site clearance and asbestos removal at the [NAME] [479]. That estimated a total cost inclusive of VAT of £130,250. The Applicant gave its own alternative estimate for those works [480] at a cost of £108,000. The works were carried out by the Applicant itself in January and February 2020, although the eventual sum charged by way of service charges was £114,990.00. The service charge for 2019-2020 was said in the Respondents’ application to include an amount of £120,000.00 plus VAT (£638.28+VAT per chalet) in respect of this element. A survey was commissioned after the event from [NAME] by the Applicant as to its opinion regarding reasonableness of the costs [483-495].
98. The dispute centred on whether the works were what the 1st Respondent described as ‘development works’ [589 and 591] to the [NAME] or whether they were works which one way or another fell within obligations of the Applicant and where the cost of complying with such obligations was one to which the Applicants were required to contribute. Mr [NAME], whilst being cross-examined, attempted to support the Applicant’s case but given the matters below was unable successfully to do so.
19 99. The Tribunal determines that the Respondents are not required to pay service charges in respect of the cost incurred by the Applicant, as explained below.
100. In relation to this issue, the Tribunal noted the terms of the [NAME] with particular care. The Tribunal considered the Fifth Schedule of the [NAME] to be particularly revealing and to provide the answer in relation to this issue.
101. The Applicant has various responsibilities in respect of the [NAME]. The [NAME] is, as noted above, defined at the start of the [NAME] as being Sandown holiday centre. However, the Schedule provides more specifically in respect of the matters to which contribution must be made by the Respondent and does not the Tribunal determines include within that all aspects of the [NAME].
102. There are in paragraph 1 of Part II a list of various elements of the [NAME], the costs in relation to which must be contributed to. A variety of matters are required to be contributed to, none of which are particularly surprising in themselves. Those include walls, roads, pipes, various specific items of equipment and insurance. There is no specific reference to the maintenance of the [NAME] or indeed any other building on the site, which Mr [NAME] accepted, as indeed he inevitably had to.
103. The Tribunal has little doubt in the face of those detailed provisions that the cost of maintenance and repair and similar of the [NAME] would have been specifically provided for had such been intended. The size and nature of the [NAME] is such that it could scarcely have been overlooked and the Tribunal finds must have been in the minds of the [NAME]. As it is, the [NAME] did not feel it necessary to include any reference to maintenance and repair of the [NAME].
104. The Tribunal determines that to be entirely consistent with the fact that the [NAME] was used as separate commercial premises which in effect just happened to be situated on a part of [NAME] and where the business operating was open to the general public and generated profit for the operator of the business. The Tribunal agrees that the [NAME] received no direct benefit beyond that received by anyone else. It was entirely logical that any repair, maintenance and similar in relation to the building would have been borne by the [NAME] operating that business and not by the chalet owners. The fact that the [NAME] has not been operated by the Applicant or indeed for several years is not relevant to that.
105. The Tribunal considers that the only sensible construction of the provision is an intention on the part of the [NAME] not to provide for the [NAME] to contribute to the maintenance and repair of the [NAME].
20 106. The contribution by the Respondents is in any event limited to works “effected for the purpose of keeping in good and substantial repair” The Tribunal does not consider that all of the removal of asbestos and demolition of parts in poor condition falls within “keeping in good and substantial repair” in this instance- even if there might be an argument that some may in appropriate circumstances. Given the determination in the preceding paragraphs, it is unnecessary to explore that further.
107. The Tribunal rejects the other arguments of Mr [NAME] that the Respondents were obliged to contribute to the costs involved in the major works.
108. The Applicant argued that removing dangerous and dilapidated parts of the [NAME] is within the obligation to keep all parts of the [NAME] in repair and “about maintenance and convenient management and running of the [NAME]” (Part II of the Fifth Schedule paragraph 11.), by way of making the [NAME] safe and preparing the structure of the [NAME] and area around it for new uses. Mr [NAME] argued in his oral submissions that making safe fell naturally within the provisions of Part II.
109. The provision relied on by the Applicant is part of paragraph 11, the whole of which demonstrates that it relates firstly, to fees charged for management, which does not assist the Applicant in respect of this point. It does refer also to “all other expenses” for “maintenance and convenient management and running of the [NAME]” but construction of the words used and taken in the context of the other clauses cannot lead to a conclusion that the [NAME] intended it to include the costs of the major works undertaken to the [NAME] by the Applicant.
110. Mr [APPELLANT] sought to argue that paragraph 11 must include dealing with dangerous structures. It would be sizeable stretch to construe the general convenient management and running of the [NAME] to include major demolition and related works to a commercially- operated building and so the Tribunal cannot accept that argument. It would consequently be a sizeable stretch to construe the words “all other expenses” of such management and running as including the costs of the major works to the [NAME]. Rather the words relied on are clearly and simply, the Tribunal determines, intended to cover any cost in respect of more general management which could be said to go beyond the fees referred to at the start of the particular paragraph. In any event, the argument that such a general provision includes what is described as ‘rendering safe a dangerous structure and preparing it for a new use or uses’ in these circumstances would require placing a construction on the term of the [NAME] which the Tribunal determines is cannot be so placed.
111. The Applicant also seeks to argue that the provision in clause 6(3), including “such …… parts of the [NAME] as may be enjoyed or used by one of the chalets in the [NAME] in common with others” would cover the [NAME] without mentioning it specifically. However, the [NAME]
21 have not since the [NAME] was closed some years ago and before the Applicant’s ownership had any use or enjoyment of the [NAME] nor has there been any way of them doing so and they plainly will not do when the remaining part of the [NAME] is developed into three chalets sold off to purchasers of those. Even if the provision could be construed so as to include the [NAME]- which the Tribunal considers it cannot- it does not assist the Applicant.
112. The Applicant also submits that the provision in paragraph 5, including “periodically inspecting examining maintaining and overhauling any part of the [NAME]” gives an entitlement for the Applicant to charge for the major works. However, the Tribunal considers that the major works do not fall within any of those terms. The same applies to the other provisions of Part II.
113. The closest anything gets that within the clauses through suggesting a positive obligation to contribute to the [NAME] is clause 4 which makes reference to grounds. However, the remainder of the paragraph refers to trees shrubs grass and similar demonstrating the grounds in question to be land within the holiday centre and not buildings. The fact that the areas around the [NAME] were rather incidentally impacted by the demolition and the remainder of the major works does not, the Tribunal determines, make the major works fall within any sensible scope of the provision in paragraph 1 related to footpaths, forecourt and so on.
114. The Tribunal has no doubt from the provisions agreed by the [NAME] and from the words used by them that if works to the [NAME], including the major works in issue in this case, had been intended to be matters to which the Respondents must contribute, the [NAME] would have specifically said so. Insofar as there may be doubt, the resolution of that must go in favour of the Respondents.
115. The Tribunal also considered the insurance clause in Part II of the Fifth Schedule to be particularly revealing.
116. There is no reference to contributing to the insurance of any other building, indeed there is a specific exclusion that [NAME] does not so contribute, reading “but excluding the individual chalets and other buildings thereon)”. A [NAME] is required to pay the cost of the Applicant insuring the particular demised premises in Part I of the Fifth Schedule, which explains the part about “individual chalets”.
117. However, the exclusion of “other buildings” is not for that reason and so there has been a specific agreement between the [NAME] about any other buildings than the individual chalets situated on [NAME] That is very strongly indicative of any buildings falling outside of any matters for which the Respondents are obliged to contribute generally. It is sensible that the exclusion was contained within the insurance clause, which would otherwise have suggested that the [NAME] should so contribute. The clause and the drafting of the [NAME]
22 generally strongly indicates that if the [NAME] were intended to contribute anything else in respect of other buildings such as the [NAME], the [NAME] would have so stated.
118. Therefore, whilst the [NAME] is a part of the [NAME], it is far more importantly not a part of the [NAME] in respect of which the Respondents are required by the [NAME] to contribute, including with regard to the major works. The power of the Applicant to undertake various works including building works in the Fourth Schedule does not of itself produce an entitlement to charge the [NAME] for the cost of such work as service charges.
119. It is unnecessary to say more in light of that. However, the Tribunal also considers that even if the [NAME] had permitted to charge the Respondent for the costs which it incurred in respect of the [NAME], it would either not have been reasonable for any service charges to be charged or the level of service charges reasonable would have been very low.
120. Whilst it is correct to say that the Applicant removed parts of the [NAME] which were in a poor state, the evidence demonstrates that by the time the works were undertaken the Applicant did not do so in order to turn the building into one usable by the Respondents nor otherwise simply to remove any parts of the [NAME] in a poor condition. Rather the works created- and the Tribunal finds on the evidence were intended by then to create- a building which could be developed into three holiday chalets and created space to facilitate the supply of parking spaces necessary to fulfil planning requirements- see further below. It is abundantly clear that the Applicant will seek to sell those chalets for profit and will receive substantial sums for them. The effect of the Respondent funding the major works would have been to significantly reduce the cost to the Applicant of developing the three chalets and so to significantly increase the profit made by the Applicant at the [NAME] expense.
121. That is a position which was never likely to find favour and where it is likely that a Tribunal would only have allowed the cost to be recovered as service charges with the very clearest supporting [NAME] terms indicating the [NAME] or their predecessors had accepted such a scenario and with the most compelling support for reasonableness. The Applicant came nowhere remotely close to that. Mr [APPELLANT] inventive argument that the removal of dilapidated parts of the [NAME] might increase the value of the existing chalets- for which there was no evidence and mere speculation- was not persuasive.
122. It may be that if the [NAME] had firstly specifically been referred to in the [NAME] as falling within elements of the [NAME] for which costs could be charged as service charges and secondly the Applicant had removed any parts dangerous and otherwise addressed disrepair and then utilised the building for a purpose benefitting the Respondents, service charges would have been reasonable- in which regard simply
23 removing parts of the building is insufficient. However, as neither of those circumstances apply, there is nothing to be gained by speculation about this point.
123. In a similar vein, whilst Mr [NAME] suggested in cross-examination of Mr [NAME] that there had been historic neglect of the [NAME] both by the [NAME] prior to the receivership in 2011 and subsequently by the [NAME], the Tribunal does not find it necessary to make any findings in that regard, nor attempt to reach any determination as to whether that may have any relevance to the level of service charges. The same applies in respect of Mr [NAME] suggestions to Mr [NAME] that the work was reasonable and removed an eyesore. Mr [NAME] responses mostly related to having no first-hand knowledge of the work undertaken or that it had nothing to do with him.
124. The Tribunal agrees, for what its worth, that the Respondents have not provided any specific evidence that the cost of the major works was unreasonable- and so for example the burden would not have passed to the Applicant as to reasonableness generally. As to any profit element which would have been received by the Applicant in respect of the work may have been another matter. Mr [APPELLANT] suggestion that the purchase price paid by the Applicant for [NAME] would have reflected its condition may be correct but was not evidenced and, in any event, did not add anything in the event.
Dispensation in respect of major works re the [NAME]
125. In light of the above, the question of whether the Applicant would be granted dispensation from consultation in respect of the major works had the costs been chargeable as service charges is not directly relevant. However, lest it be subsequently determined that the Tribunal is incorrect in its construction of the [NAME] and the effects of that, the Tribunal does address this aspect of the dispute.
126. Mr [NAME] said in evidence that the [NAME] had received legal advice that the chalet leases were commercial in nature rather than residential and did not fall within the provisions of the Act, However, the Applicant did not pursue such an argument. Mr [APPELLANT] queried that advice in any event, given that the notice of rights had been provided with service charges demands, to which Mr [NAME] replied that the advice received had been to provide those. The fact that it was considered at the time that the [NAME] did not have the protection of the Act was given as the reason for a lack of section 20 consultation. Mr [NAME] said that there was consultation but accepted that was not in accordance with the Act.
127. The argument about the major works related to whether the project of the renovation of the [NAME] comprised one single set of works or three discrete parts- being contents removal, asbestos removal and demolition. The Applicant asserted each to be a separate process from the others and had a discrete cost for the purpose of the Act. Viewed
24 from that perspective the service charges per [NAME] would fall below £250 for any given discrete element of the overall works. Mr [NAME] argued that the demolition had to take place first, and the works sequentially more generally, and that when that work was undertaken (January 2020) there was no crystallized plan for the development of new chalets at the site, although the Tribunal notes the careful choice of words and refers to its finding above. Reference was also made to the asbestos removal work being required to be carried out by a [NAME] and that the Applicant subcontracted that work. [NAME] also said in closing that the demolition took place before planning permission was granted.
128. [NAME] said in oral evidence that the elements could be undertaken separately, although in response to cross-examination he conceded that they were undertaken as one set of works. He maintained that they did not have to be so undertaken, arguing that asbestos removal would have occurred whatever else had happened and for whatever use the [NAME] had been put, and that there were three stages, one following the other. It is doubtful whether the Applicant’s case can survive the concession in oral evidence, although nothing turns on whether it can or not in the event. The Tribunal determined the question in any event.
129. The Respondent argued that all aspects were part and parcel of one whole, hence the amount charged to each [NAME] exceeded £250 and so consultation was required. Mr [NAME] also referred to the practical need to undertake one element of work before the next could be attended to. The Tribunal agrees with the Respondent about that aspect.
130. The Tribunal has noted the examples of relevant factors identified by the Court of Appeal in Phillips v Francis. The items of work were carried out to the same building, whether the original part or subsequent extensions to it. The question of whether they were the subject of the same contract it not especially helpful in the event where the Applicant itself undertook the works, but the Tribunal accepts that a single contract would have been granted to the other company which provided an estimate, and it is very likely that the same approach would have been taken with any other external contractor. The works were done at more or less the same time. In that regard, whilst the Applicant referred to the demolition being undertaken first and in January 2020, the remainder of the work followed on swiftly. The Tribunal accepts Mr [NAME] point that the work was undertaken during a period in which [NAME] was closed and that was the best time for it to be undertaken. However, that did not weigh in favour of the Applicant. The fact that the work had to be undertaken following a sequence, not unusually, did not take the Applicant anywhere here. Neither does the need for [NAME] for any part of the work – specifically the asbestos- of itself make such work separate to the remainder and no other feature was such that it ought to be regarded as a separate set of work. The items of work had some difference of character but relatively
25 marginally. The way in which the works were planned and the Applicant's reasons for the way they were implemented, insofar as revealed, would also have supported there being a single set of works and not three individual ones.
131. The Tribunal additionally notes that there are always various elements of building work and various trades are involved. The work here was essentially one of removing parts of a building. Necessarily, items needed removing, most notably the asbestos without which the demolition could not take place and establishing a very clear link between that element and the demolition. Whilst there was a gap between demolition and planning permission being granted in February 2020 [570-584], in the Tribunal’s experience planning permissions do not materialise rapidly upon a decision to develop being made: rather the formulating of plans, any enquiries as to the prospects of a positive application and related communications, the application for planning and the planning process takes quite a period of time. The date of the grant of permission is of little relevance in itself. The Tribunal noted that the initial correspondence from the Applicant to the [NAME] dated 2nd March 2017 shortly after purchase of [NAME] [116- 118] trailed the potential demolition of parts of the [NAME] and identified one potential course as being additional chalets but the letter is too unclear as to firm intentions- its says plans are being formulated and ideas investigated- and too long before any works to assist either side. Correspondence in mid- 2018 [119-120] referred to demolition and a potential shop but essentially the same observations apply. At an uncertain later date there was sketch plan showing three chalets created from the barracks [122], apparently by April 2019 although that is not completely clear. By April 2021, there was a detailed plan (although showing four) [124] and proposal (for three) set out in a detailed document [565-569], so plainly some time before those the intended course of action had crystalised. Although there is some lack of clarity and hence the Tribunal is unable to pinpoint the exact intention at an exact given time, overall the lack of an overall plan and development only being thought of after the demolition has certainly not been adequately demonstrated and applying the balance of probabilities to the available evidence, the Applicant’s case on that fails.
132. Accordingly, the Tribunal determines that the major works comprised one set of works, albeit with different elements to them, and not three distinct sets of work. Therefore, the works would have required consultation requirements to have been complied with.
133. In respect of whether dispensation would have been granted, the Tribunal has considered the further arguments of the parties. The Tribunal accepts the Applicant’s argument that the contractor from which the Applicant obtained a quote, [APPELLANT], would have charged £42,500 for asbestos removal, whereas the Applicant itself estimated £35,000. The Applicant’s figure was again lower in respect of the other elements of the work. In addition, it was not challenged that the Applicant has chosen to absorb £11,000 of extra
26 cost [481] and that no independent contractor would have been likely to do so. As to the level of profit which the Applicant would have actually made if it had been able to charge the Respondents as it sought to, if any, is unclear and nothing turns on that.
134. The Respondents have not demonstrated that another contractor would have undertaken the work for less than the Applicant and would thereby have been instructed, such that no prejudice to the Respondents has been demonstrated. Mr [APPELLANT] oral evidence that it was for the Applicant to demonstrate that was incorrect. Whilst Mr [APPELLANT] submitted in closing that the Respondent could not obtain a quote once the work had been undertaken, he then conceded it to be possible and the Tribunal considers that an alternative quote would have been obtainable had the Respondents wished to obtain one.
135.
Accordingly, if the Tribunal had determined the works to the [NAME] to be chargeable as service charges in the first place, the Tribunal would have granted dispensation from consultation requirements in this instance. As the Tribunal did not so determine, there were no service charges which the Respondents could be required to pay and so consultation was irrelevant. The Tribunal was asked on behalf of the Respondents to impose a condition that the Applicant pay some of the Respondents’ costs if dispensation were granted, but as it has not been, because the works are not one which service charges can be charged for, that point does not arise.
Decision in respect of [NAME] charges
136. The Tribunal therefore determines that the service charges demanded in respect of the [NAME] of £114,990.00 are not payable.
Playground reserve charges
137. No playground was in the event constructed. The service charges in issue relate to investigating developing a proposed playground. As Mr [NAME] conceded, the project- as he described it- did not come to fruition. One obvious issue arising is that there was no tangible benefit to the Respondents for the expenditure incurred.
138. Nevertheless, there had been costs demanded as service charges of some £37,500.00 for each of the service charge years 2017-2018 and 2018- 2019, so £75,000.00 in total, to be placed in a reserve to meet the cost of the proposed work to the playground. Various invoices are relied on [497-500], although invoices generated by the Applicant itself and relying, the Tribunal understands, on paragraphs 11 and/ or 14 of Part II of the Fifth Schedule. Reference appears to have first been made in a letter from [NAME] of August 2017 [146 onwards].
139. In the event, the actual expenditure was £6712.80 including VAT, said by Mr [NAME] in his statement to relate to the preparations of submissions, proposals and communications with the local council. The
27 Applicant decided not to proceed further. Consequently, there was, the Applicant says, a refund of £68,287.20 to be credited across the group of [NAME] as a whole. That left a net deduction from the [NAME] per [NAME] of £35.70.
140. The Tribunal pauses to note that the Respondents say that the charges of £200.00 plus VAT per chalet for each of 2017- 2018 and 2018- 2019 would have totalled £74,400.00 plus VAT (£89,280) and the amount “refunded” was £56,906.00 and that appears to be borne out by the Budget/ Actual Report in the bundle for 01/09/2019 to 31/08/2020 [139]. There is something of a gulf between the sets of figures. However, the Tribunal is not addressing accounting matters but rather the reasonableness of service charges and more particularly the reasonableness of the actual expenditure incurred and charged (the reasonableness of the earlier estimated service charges having been rendered irrelevant by the later actual service charges). Any dispute about whether the level of refund was correct and there is money retained by the Applicant to which the Respondents are entitled would require determining in a different forum.
141. The Applicant’s case was essentially that it was entitled to charge as what came to be actual service charges for the investigatory and preparatory work and that the provisions of Part II of the Fifth Schedule at paragraphs 5 and 11 applied. The 1st [NAME] case asserts that the playground was “nothing more than an idea”- in oral evidence Mr [NAME] referred to “just a theory”, and so in effect does not cross any threshold to be costs reasonably chargeable. Mr [NAME] also relied on a lack of a planning application. He did accept that a playground would have benefitted [NAME].
142. The Tribunal has some appreciation of the Respondents’ position. However, the Tribunal finds that the costs were incurred as part of development of [NAME] which fell within matters for which the Applicant was entitled to charge the Respondents and the fact that the playground did not materialise does not render the service charges unreasonable. It is reality that not all projects, using Mr [NAME] word as being as good as any, are able to be completed.
143. The Tribunal does not consider paragraph 5 to cover the works- the playground project does not obviously involved “inspecting examining maintaining and overhauling” [NAME]. The Tribunal does determine that paragraphs 9 and 11 do cover the work on the project, which related to managing [NAME] in a broad sense and the provision of a facility more specifically, much as that did not materialise in the event. The Tribunal had some concern that it was indicated by Mr [NAME] in closing that the cost charged involved some apportionment of wider costs of different projects, including the [NAME] development- issues as to which are discussed under the header Surveys and planning permission for redevelopment. However, no point had been taken about the level of charges if any were payable.
28 144. The Tribunal notes that Mr [NAME] was rather noncommittal in his evidence in relation to this item and that Mr [NAME] said relatively little in his closing submissions. It may be, although without impact on the Tribunal’s determination, that the [NAME] identified that although expenditure by them on the costs of the proposed playground was unattractive, there was no strong argument.
145. Mr [NAME] had however cross-examined Mr [NAME] on this element of the case. Mr [NAME] said that Mr [NAME] had asked the [NAME] and there had been a strong desire on their part to have a playground. Also, that there had been no specific reason to seek to build a playground other than that it was what the [NAME] wanted. Mr [NAME] added that the areas will be landscaped and improved. None of that altered the Tribunal’s determination.
Decision in respect of Playground reserve charges
146. The Tribunal determines that £6712.80 in respect of these charges was payable, being £35.70 per chalet, including that of the 1st Respondent.
Repairs to paths and rebuilding retaining walls
147. The Respondents originally contended that this element involved major works for which no consultation had taken place. No point had been taken that such works could not be recovered under the terms of the [NAME]. The 1st [NAME] written case asserted it to be unclear where the works took place and implied that they may be related to the [NAME] works. The Applicant relied on a plan provided by Mr [APPELLANT] [521] which it said shows clearly that these are works wholly unrelated to the [NAME] demolition and also added that to the extent that the Respondents’ challenge was in effect only a request for clarification, such clarification had been provided. Estimates for works were provided [522- 530] and invoices [504– 520].
148. In light of the Respondents’ concession following Mr [NAME] oral evidence on this element of the case no determination by the Tribunal is sought. Mr [NAME] explained in closing that as the excess over the amount beyond which consultation is required is so modest, it had been decided that there was no merit in a challenge.
149. The amounts involved as referred to in the [NAME] application and the budgets were £38,160.00 inclusive of VAT for 2019- 2020 [138] and £36,000 inclusive of VAT for 2020- 2021 [141].
150. Given that the charge was accepted or admitted, there is no need to say any more about this element, save to confirm as below.
Decision in respect of repairs to paths and rebuilding retaining walls charges
151. The service charge of £394.47 per chalet is payable, including by the 1st Respondent.
29
New car parking
152. The Applicant’s case is that following the demolition of the later extensions to the [NAME], nine parking spaces, plus one spaces for bicycles (a restriction in the planning permission which prevented what the Applicant originally intended to be ten car spaces) have been provided on the available land and that those are available to the [NAME] and hence the costs of the related work is chargeable as service charges. It is said that there were previously only three spaces in that area. There is only a temporary surface, stated by Mr [APPELLANT] to be compacted hardcore, but the Applicant’s position was that it intended to create a permanent one at an anticipated cost of £30,000 plus VAT [82].
153. The Respondents’ position, as highlighted by Mr [NAME] in closing, was that the provision of parking was directly linked to the planning permission for development of the [NAME] and so the 2020- 2021 service charges in respect of this item were not payable. The Tribunal agrees.
154. The planning permission for the new chalets requires them to be provided with at least five parking spaces. Mr [NAME] accepted as much in his oral evidence, although his witness statement had asserted that all of the spaces were available for general use.
155. That written statement quotes condition 7 of the planning permission which specifies:
“the holiday accommodation hereby permitted shall not be brought into use until space has been laid out within the site for a minimum of five and a maximum of nine cars to be parked and for vehicles to be loaded and unloaded and for vehicles to turn so that they may enter and leave the site in forward gear. Thereafter this space shall only be used for the parking and manoeuvring of vehicles belonging to occupiers of the holiday accommodation hereby permitted and their visitors and not for any other purpose.”
156. Mr [NAME] says in the statement that he understands that there is no requirement for the spaces to be provided to be allocated to the new units or dedicated for use by those units. The Tribunal is unable to identify how he may have formed that understanding. The condition is quite specific that the spaces “shall only be used” by the “holiday accommodation hereby permitted” and “not for any other purpose”. That simple and clear wording cannot be construed as enabling the spaces to be used by any resident of [NAME] or visitor, explicitly saying quite the opposite.
157. Consequently, the Tribunal finds that it was necessary for the Applicant to lay out a car [NAME] and provide at least five parking spaces for the three new chalets. The Tribunal also finds that those parking spaces
30 cannot be available for the other [NAME] because the Applicant would thereby have failed to provide the necessary spaces for the new chalets. The Tribunal gives very little weight to the comment of Mr [NAME] that he understands from Mr [NAME] that the latter queried with the planning officer and was told that the intention was that the spaces be available for anyone. That comment is third- hand, is imprecise, is unsupported by anything from the planning authority and flies directly in the face of the clear words used in the condition, which could not conceivably have been adopted if the intention was the opposite.
158. Mr [NAME] added in oral evidence that the use of the spaces would not be policed and that it would not be possible to control their use in any sensible manner. However, given the terms of the planning condition, the Tribunal considers that to be inadequate. A failure to take any steps to ensure that the parking is available to the new chalets created is liable to cause difficulties, including at the time of attempted sale of the newly developed chalets, if not already sold. The Tribunal agrees with Mr [NAME] in his oral evidence, not that the point affected any determination, that there may be limited appeal to a purchaser if no parking spaces is included.
159. Nevertheless, none of that alters that fact that the Applicant must provide at least five spaces in order to comply with planning permission for the development cannot comply with the condition otherwise, and the Tribunal determines will provide them for that reason.
160. There are nine spaces and so more than the number necessary for the planning permission to be complied with. However, there has been no evidence provided of any additional cost having been incurred by the Applicant to that which the Applicant would have incurred for the provision of five spaces for the new chalets within the period in question. In addition, the four other spaces amounts to only one more than the three available previously, so benefit to the [NAME] is marginal and clear evidence of reasonable cost of providing one net additional parking space would have been required for cost to be allowed.
161. The Tribunal determines that the cost of providing the new parking spaces was not work falling within paragraphs 1, 9 or 11 of Part II of the Fifth Schedule or otherwise within the provisions of the [NAME] but rather is cost incurred by the Applicant as part and parcel of the development of the three new chalets.
162. The Tribunal adds with the aim of reducing the scope for future dispute that it considers that once the construction of the new parking spaces is completed, they became part of the grounds of [NAME]. Consequently, costs incurred by the Applicant in maintaining the spaces are chargeable as service charges. However, that is separate to the cost of providing the spaces.
163. The Tribunal notes that such contribution should include contribution by the [NAME] of the new chalets once construction is complete and that
31 more generally, an increase in the number of chalets would appear to require adjustment of the contributions per chalet to avoid recovery of more than 100% of the payable service charges.
Decision in respect of charges for new car parking
164. The Tribunal determines that none of the service charges are payable.
Contribution to reserve funds and/or General contingency
165. The dispute under this sub-heading related to whether the expenditure must be for identified projects and so the appropriate construction of the sentence, “The establishment and maintenance of a [NAME] to provide for any items of future capital expenditure foreseen by [NAME]”. The Applicant’s case was that any future capital expenditure was covered, whereas the 1st Respondent contended that the sums charged as service charges had to be in respect of specific identified projects and may not be demanded otherwise. The playground had been one such identified project, although other issues arose as explained above.
166. Mr [NAME] explained in his witness statement [specifically 83] that there are two reserves, called “[NAME]” and “General Contingency”, the latter being described as a relatively small amount of money collected each year to build a buffer against unforeseen costs in the longer- term future. The [NAME] was described a sum collected either for a specific purpose or to ensure money for unexpected works in the current year.
167. Mr [APPELLANT] argued that it is for the Applicant to determine how much and for what purpose the reserves are to be collected and held, and the accounts provide sufficient detail to meet [NAME]’s obligations, referring to [COMPANY] v [COMPANY] (United Kingdom) [2021] EWHC 314 (Ch). Necessarily, that it subject to the specific terms of the [NAME] placing any greater restrictions on the purpose for which a reserve may be collected.
168. Criterion involved commercial premises, outside the jurisdiction of this Tribunal, and where the landlord was “entitled to include in the service charge for any service charge period an amount which the Landlord reasonably determines is appropriate to build up and maintain a sinking fund and a [NAME] in accordance with the principles of good [NAME] management”. That wording is somewhat different to the terms of the [NAME] and there were limits to the specific types of expenditure which the [NAME] could be used to cover.
169. Mr [NAME] concentrated on the word “foreseen”, which he argued produced a narrow entitlement to hold a [NAME] and required specific projects to be identified. It did not, he argued, permit a reserve to be kept for general future expenditure. The correct approach, he asserted was for the Applicant to identify specific items likely to require
32 expenditure and that funds obtained for one purpose could not be used for another.
170. His cross-examination of Mr [NAME] related to that. Mr [NAME] evidence on that point, whilst otherwise clear, was not easy to follow. He appeared to agree with Mr [NAME] that specific projects were required but then also said that it was possible to “foresee” that there would be matters “unforeseeable”. The point he sought to make was not clear.
171. As Mr [NAME] identified in his closing submissions, the wording of the provision is “awkward”. The Tribunal gave the construction of the provision considerable thought.
172. If the word “foreseen” onwards were removed from paragraph 10 of Part II of the Fifth Schedule, the Applicant would have a very wide discretion and one which would be unusual. There would in the normal course be some limit to the amounts, the [NAME] in the case authority limiting it by way of “reasonably determines is appropriate”. The question is how much of a limit the particular clause in the [NAME] sought to impose.
173. The Tribunal notes that the provision in the [NAME] the word “any” and does not say, ‘only such items of future capital expenditure as are identifiable at the given time’, which is the effect the Respondents wish to be given to the wording. There is no specific requirement as to the timescale in the future for the expenditure. That said “foreseen” must require the Applicant to be genuine and the Applicant to be able to demonstrate that it did foresee capital expenditure at some point ahead of incurring the expenditure and be able to explain how.
174. Equally, the Tribunal reminds itself that the full provision reads “The establishment and maintenance of a [NAME] to provide for any items of future capital expenditure foreseen by [NAME]”. So, the fund will provide for the future expenditure from the sum contained within it and the Applicant is entitled to accumulate a fund, not just to receive in advance payment for specific expenditure items. The expenditure foreseen is likely to vary from time to time as needs for capital expenditure are identified.
175. The Tribunal determines from the wording used and the terms of the other provisions, that the [NAME] intended the provision to be given the wider interpretation argued for by the Applicant and cannot be construed so as to limit the provision to the narrow one argued for by the Respondent.
176. Accordingly, the Tribunal determines the service charges demanded for the “[NAME]” are permitted. Funds collected within that for a specific purpose are unproblematic. Funds to ensure money in hand for unexpected works in the current year is really the portion to which the above discussion relates and whilst “unexpected” causes the Applicant
33 some difficulty, the Tribunal determines it to be different to “unforeseen” and that the fact that the expenditure would fall within the given current year is sufficient for the service charges to generate such sums to fall within the provision.
177. The Tribunal observes that to a large degree any difference between the parties is one of timing. To that extent Mr [NAME] reference in oral evidence that the [NAME] were not prejudiced because money stayed in the fund had some, but not complete, merit. There will be capital expenditure required and the Applicant is entitled to seek in advance the sums required for that. The need to identify specific projects might have reduced the level of services charges chargeable at given times but would in turn have increased them at others.
178. However, given that Mr [NAME] specifically describes in his witness statement the “General Contingency” as being a buffer for “unforeseen” costs, the Tribunal determines that sum does not fall within the provisions of the [NAME].
179. It is one thing to give a provision a wide interpretation determined to be intended but quite another to determine expenditure “foreseen” to include matters specifically described as “unforeseen”. The Tribunal is unable to discern any proper construction of the phrase used, including the particular word used, which could permit that.
180. No other argument as to reasonableness was advanced on behalf of the Respondents.
181. The budget sum for the Contribution to reserve funds is £5000.00 per service charge year across the 188 chalets. The relevant shares of that would be £26.60 per chalet per year.
Decision in respect of charge for contributions to reserves funds and/ or general contingency
182. The Tribunal determines that the service charges in respect of contributions in the sum of £26.60 per service charge year per chalet to the [NAME] were reasonable and payable, so £159.60 for the six years overall.
Surveys and planning permission for redevelopment
183. The Applicant’s case in relation to this aspect was not clear. It was quite difficult to discern the service charges for costs beyond those properly falling within one of the other headings above and the basis on which those are payable and reasonable.
184. The witness statement of Mr [NAME] explained that some of the preparatory and planning fees for what was described as “the project to renew common facilities” [83] were accounted for against the
34 playground reserve. The Tribunal accepts that as appropriate where the charges related to the proposed playground.
185. He also said that “generally” the Applicant has sought to charge half of the costs as service charges, giving an example of a “site investigation re contaminated land” [see 564]. However, it is asserted that Mr [APPELLANT] told Mr [APPELLANT] that the Applicant paid costs specifically related to the chalet development. There is no evidence provided of the correctness of that, either from Mr [NAME] or by way of documentary evidence, irrespective of Mr [NAME] stated confidence in such correctness.
186. There was no identified written evidence as to why contaminated land required investigation and whether that related to the [NAME] or some other part of [NAME], and if the latter then why. Mr [NAME] in oral evidence in response to enquiry by the Tribunal said that it was a requirement of planning permission, that is to say for the development of the [NAME], given the [NAME] military use of the site. The charges in respect of planning permission were said by Mr [NAME] in oral evidence to have been split 60:40, as the invoice confirmed [458]. The explanation given was that it was said that there was an attempt to come with an appropriate and fair apportionment in each instance by looking at what was intended and what it had relevance to. Mr [NAME] believed there to be ten instances of apportionment.
187. It is said by Mr [NAME] in his [NAME] that the charges relate to long-term development of [NAME] although the Applicant accepts that developing new chalets will be for its benefit in the first instance- the Tribunal understands because the Applicant will sell them for its own profit- and hence the Applicant does not seek to charge the full cost. The Applicant asserts that there will be benefit to [NAME] as a whole, although without identifying a specific provision which covers these costs.
188. The Respondents contend that they ought not to be charged any of the cost. The Tribunal application made identifies that in late 2018, the Applicant applied for planning permission to build a number of new chalets, a manager’s [NAME] and to demolish/convert the old [NAME] but that the planning application was withdrawn in early 2019. It is said that there was attendance at a meeting of the [NAME] and it was stated that [NAME] had been charged pro-rata for part of the cost of the surveys / planning application but did not go into specific detail of the amounts or what parts the [NAME] were being charged for. Given the various matters raised by the Respondents in this case, the Tribunal considers that the Respondents have gone far enough in challenging to require the Applicant to justify the service charges falling into this section of the dispute.
189. The Tribunal identifies that paragraph 11 of Part II of the Fifth Schedule may apply, as might certain other of the provisions of that Part, although none of the provisions, including paragraph 11, are
35 considered by the Tribunal to obviously be intended to relate to this situation.
190. The Tribunal determines that the charges in respect of planning permission and contaminated land relate to the development of the [NAME] and are not payable for that reason. More generally, the Applicant has offered no sufficient explanation for a 50:50 division of costs generally nor how that is reasonable. The Tribunal considered on the information provided that the percentage chosen was nothing demonstrably other than arbitrary. It is also unclear in which instances there has been any different percentage charged, save in respect of planning permission where the Tribunal determines in light of its above determinations that nothing ought to have been charged to the [NAME], and on what basis.
191. There is also inadequate evidence as to the extent to which any given element of the costs was properly chargeable to the Respondent, if any. There is no discernible analysis of the extent to which the fees relate to matters for which service charges are recoverable- which may in any event have been reduced to the extent that the Tribunal has disallowed other service charges for given works in dispute. The contaminated land investigation referred to above is one example.
192. It may well be that some survey and other fees do relate to matters properly falling within service charges and that some level of charges for such fees is reasonable. However, there is no way of the Tribunal properly identifying that on the evidence presented.
193. Rather, the Applicant has failed to demonstrate that any of the survey fees do fall within matters chargeable as service charges to the Respondents in any given sum of at all. Given that the final hearing took place and the Applicant has been represented throughout, the Tribunal has dealt with the matter on the evidence chosen to be presented.
194. The Tribunal accordingly disallows the service charges in respect of this aspect.
Decision of the Tribunal in respect of charges for surveys and planning permission for redevelopment
195. The Tribunal determines that none of the service charges are payable.
Fees for defaulting [NAME]
196. The Applicant still sought the Tribunal to determine, notwithstanding the concession in respect of legal fees, that the fees of the [NAME] incurred in respect of their work in connection with legal proceedings of some £37,084.62 were payable and reasonable. Those related to the time spent in dealing with litigation and related. In addition, the Applicant had charged for general legal fees incurred in
36 obtaining advice for the benefit of the [NAME] and all [NAME] in the sum of £445.20, which related to the removal of a car from [NAME]. The [NAME] application referred to a sum of £504 for the service charge year 2016- 2017 but that falls before the years the subject of the [NAME] application.
197. In respect of the [NAME] element, the Applicant relied on paragraphs 9 and 11 of Part II of the Fifth Schedule, whether as part of “All costs incurred in provision and supply of any other services” or “The fees of …….. [NAME]’s agents for the general management of the [NAME]”. The fees are a charge for dealing with an aspect of management of [NAME], not excluded by any of the provisions of the [NAME], the Applicant argues.
198. The Tribunal perceives that it is in respect of this aspect of the dispute that the Applicant’s Counsel included in his authorities bundle a case authority of [COMPANY] v [COMPANY] 1996] 71 P. & C.R., although the case was not referred to in the [NAME] or in oral closing and so it was not clear to the Tribunal what assistance it was considered the case would provide. In any event, the wording in the respective leases and the circumstances of the cases were different such that the Tribunal did not find the authority determinative of any issue.
199. The statement of Mr [NAME] explained that as part of the accounting process adopted the managing agent’s fees of dealing with litigation had been included under the title legal costs. Whilst Mr [APPELLANT] said that enabled the Applicant to identify the “true cost” of the litigation, he correctly conceded that it could give rise to confusion. Mr [NAME] broadly, but without enthusiasm, accepted the nature of the work undertaken by the [NAME].
200. The Respondents argued that fees of the managing for time spent assisting the lawyers fell within legal fees and that it was not realistic to distinguish between fees of the [NAME] and others. Mr [NAME] also referred to the significant charging rates.
201. There was also a fair amount of cross-examination of Mr [NAME] by Mr [NAME] in respect of the management fees, but in the circumstances set out below the Tribunal does not consider it necessary to set that out. Similarly, there was cross-examination of the 1st Respondent by Mr [RESPONDENT] but nothing material arose.
202. The Tribunal does not agree with the Respondents’ argument. The Tribunal accepts that on the wording of the [NAME], in principle charges for the work of the [NAME] in dealing with legal proceedings may be recoverable, as management charges rather than as legal fees, in respect of management of [NAME]. Consequently, the points made by Mr [NAME] in respect of application of the Court of Appeal judgment in [NAME] v Mears [1989] 1 E.G.L.R. 65- a case not produced to the Tribunal but a longstanding and oft- quoted authority
37 of which the Tribunal had prior knowledge- are not relevant in respect of the managing agent fees. That case had related to legal costs.
203. However, the Applicant failed to provide the agreement entered into with the [NAME].
204. The Applicant thereby failed to show that the work falls within work of the [NAME] for which the Applicant is obliged to pay generally. More specifically, the Tribunal finds that it is highly likely applying its experience of agreements entered into between freeholders or equivalent on the one hand and [NAME] on the other, that there is an agreement for the Applicant to pay a given annual fee to the agents, potentially with additional charges at a specific hourly rate or at a piece rate where any work undertaken falls outside of the fixed fee.
205. The Applicant also failed to show that it is obliged to pay for the work beyond the level of any fee agreed with the agent, as being work which falls outside of such fixed fee. The Applicant did not produce any agreement enabling the terms of that to be known. The Tribunal did check with Mr [NAME] that the agreement was not provided, and he confirmed that it was not.
206. Nor was there anything to demonstrate, although not directly relevant in the event, the rate at which the managing agent could charge the Applicant for any work falling outside of the work within a fixed fee, if any. Therefore, even if the Tribunal had considered that any additional sum could be demonstrated to be payable, the Applicant would have failed to demonstrate the reasonableness of the specific sum charged. The Tribunal observes in that regard that the fees of the managing agent sought to be charged as service charges were considerable and the Tribunal would have analysed with some care the extent to which those could be regarded as reasonable.
207. The Tribunal is mindful that it did not request a copy of the agreement between the Applicant and the managing agent. However, the Tribunal considers that as both parties were represented throughout, including therefore the Applicant, the Tribunal is entitled to considers matters on the basis of the evidence which the parties saw fit to rely on and was not compelled to venture into the arena by inviting other documentary evidence.
208. In respect of the latter element, the Tribunal accepted the charges regarding removal of the car left by a [NAME] were specifically for legal advice. The Tribunal noted the information as to the work undertaken to be limited but considered that the quantity of work was relatively modest and the information to suffice in itself.
209. Mr [COUNSEL] in oral evidence raised the fact that his solicitor had asked questions which had not been replied to, but the Tribunal did not consider that took him anywhere and he accepted that advice had been sought. He also suggested that the police could have been involved,
38 although he provided no basis for it being a police matter. Mr [NAME] added in oral evidence that if the legal fees were recovered, the sum would be credited to the service charges, although he could offer no support for that occurring.
210. Mr [NAME] relied again on [NAME] and the judgement of Taylor LJ that there must be a specific provision in “clear and unambiguous terms” to allow the Applicant to receive legal fees from non- defaulting [NAME], which he contended did not exist. Mr [NAME] relied on the terms of clauses mentioned above.
211. The Tribunal determines that the work does not fall within paragraphs 9 and 11 referred to above. The removal of the car was an element of [NAME] management, using the term generally, and the legal fees were incurred related to that, but the wording of those provisions cannot be construed as including legal fees being chargeable to the [NAME]. Neither provision makes any reference to legal fees. The authority relied on by Mr [NAME] plainly applies and the provisions are a long way from providing in clear and unambiguous terms for recovery of legal fees.
Decision re fees for defaulting [NAME]
212. The service charges were not payable.
Insurance
213. The Claim Form listed insurance separately to service charges. However, the Tribunal considers that the charge for the costs of insurance is a service charge.
214. The Tribunal sought an explanation as to why insurance was listed separately, which Mr [NAME] provided, explaining that the renewal date does not coincide with service charge years because there had been no known policy in place when the [NAME] were appointed- and the Tribunal surmises the [NAME] had obtained insurance upon being made aware. The Tribunal also noted that the [NAME] refers to the insurance separately, the insurance in question relating to the individual chalet and not [NAME] as a whole, which provides a sensible explanation.
215. The insurance element of the case only involved the First Respondent. It is a matter for the Tribunal as being a service charge to be determined arising from the Court order in the proceedings between the Applicant and the First Respondent and not the Respondents’ application.
216. Mr [NAME] oral evidence as to lack of payment was that related to changes to the nature of the policy, mentioning in particular a change from residential to commercial. He did not offer evidence that suitable insurance could have been obtained for a lower sum or otherwise argue
39 that the amount was unreasonable. He failed to advance any sufficient case for there to be anything required of the Applicant in response.
217. The amount said to be payable by the Applicant was £967.26. However, the only demand identifiable during the period for which the claim is brought is one made on 1st September 2020 [190] for a period 1st September 2020 to 28th February 2021, in the sum of £181.92. Insurance for other years does not fall with the matters referred to the Tribunal by the County Court or the subsequent applications to the Tribunal.
218. Given the cost of £181.92 for six months, the Tribunal perceives a cost of £363.84 for a full year, which appears to be borne out by the charge on 1st March 2022 being the same figure [542]. In the absence of any sufficient challenge to those sums, the Tribunal determines the insurance to be payable and reasonable in full. The Tribunal makes the passing observation that if the yearly insurance for a chalet had been £967.26, the Tribunal may have called for a detailed explanation from the Applicant despite any lack of challenge, the sum appearing obviously unreasonable, a point perhaps rendered obvious by the figure apparently being for somewhat more than a year’s insurance. The Tribunal is also less than clear whether the VAT element shown was part of the premium charged by the insurance company or was added by [NAME] [NAME] but given the lack of challenge and the modest sum of £30.32 involved, an as in this instance there was another company involved (see in contrast Ground Rent below), the Tribunal leaves the matter there.
Decision in respect of insurance
219. The Tribunal determines the cost of insurance to be payable by the First Respondent and reasonable for the relevant six months of the service charge year 1st September in the sum of £181.92.
The County Court issues
Claim in relation to service charges/ insurance under the [NAME]
220. The County Court issues were considered by Judge Dobson alone, having regard to the findings and determinations of the Tribunal in respect of the [NAME] service charges. The answer in respect of this aspect of the claim is relatively simple. The Tribunal has determined on the evidence presented the service charges (including in respect of insurance) payable by each chalet owner(s), including therefore by the 1st Respondent, and reasonable, for the years 2017- 2018 to 2022- 2023.
221. However, the claim made by the Applicant is very specifically for the sums demanded between 20th February 2020 and 25th February 2021 and hence only some of amounts discussed above. [ADDRESS] cannot
40 identify any of the playground charges which were demanded between the relevant dates.
222. On the footing that half of the 2019- 2020 sum was charged in each instalment for that service charge year, so half on 1st September and half on 1st March, only the 1st March portion would fall within the period of the claim. For 2020- 2021, only the 1st September portion would so fall. Hence, the 1st Respondent is liable in respect of the County Court claim for those two halves where sums were charged during those service charge years.
223. Therefore the 1st [NAME] relevant contribution was £26.60 to the Contribution to reserve funds. In respect of the paths and retaining walls, the sum is £394.47. In addition, the contribution of the Respondent to the cost of insurance for the period was determined to be £181.92. The evidence of Mr [RESPONDENT] in his statement was that the 1st Respondent had made no payments since the date of a statement of account exhibited [541-545] and the 1st Respondent did not assert any other payments.
224. Mr [RESPONDENT] sought the sum of £4235,57 in his closing submissions, a significant increase from the amount in the Claim Form on the basis that the balance shown on the [NAME] account had increased since the issue of the claim. It had been apparent that certain invoices in the bundle post-dated the period referred to in the Claim Form. [ADDRESS] did not consider that any claim had been advanced such that the additional sum was due in the proceedings. The Claim Form prepared by solicitors is specific as to the time period and no application to amend had been made. Mr [NAME] did not seek to make further submissions. Quite what part of the larger figure may have been due if open for determination is unclear and soes not merit consideration.
225. Mr [NAME] referred in oral evidence to there being water repeatedly outside his chalet despite having supposedly been dealt with and that he had offered to sort out the problem himself but that he had been told he could not touch it. The nature of any breach of covenant by the Applicant and any impact on the payability and reasonableness of the service charges which had been identified as in dispute was not, the Court finds, sufficiently explained to provide any defence (and for the avoidance of doubt neither had the Tribunal considered there to be any basis for set- off).
226. More generally, Mr [APPELLANT] objected to paying for the Applicant’s development of the [NAME], an argument with merit in respect of much of the service charges as demonstrated by the determinations of the Tribunal. He also referred to correspondence he had sent, but not, it was highlighted in cross- examination, to [NAME]. None of that provided a defence.
227. Hence insofar as the service charges and insurance involved in the County Court claim have been found payable and reasonable by the
41 Tribunal and relate to the period for which the claim is made, the Court determines them to be owing and due.
228. The Claimant is therefore entitled to, and is granted, judgment in the sum of £1,388.35 for these elements.
.
Ground rent
229. The demands for ground rent and matters in respect of ground rent more generally were scarcely touched upon in the hearing. Mr [NAME] put to Mr [NAME] that he did not dispute the ground rent, to which Mr [NAME] agreed. His reason for not paying was that his questions had not been answered.
230. Copies of various demands were provided by the Applicant [125 onwards and 540-541], which Mr [APPELLANT] asserted in closing to be valid, the 1st Respondent had not disputed and the Court accepts at least in relation to the period with which it is concerned. [ADDRESS] finds the 1st [NAME] explanation not to provide any valid defence to the claim for ground rent and so the ground rent for the period of the claim is due.
231. [ADDRESS] notes that the demands are for rent of £206.93 on 1st of January 2020 (and the same for 2018 and 2019). However, the remittance advice in each instance is for £248.32, which appears to arise from adding 20% on top of that figure, presumably for VAT- not other explanation presents itself. The Sixth Schedule provides for a charge of £125 rent, which will be adjusted in accordance with the Retail Price Index at the relevant time.
232. [ADDRESS] proceeds on the basis that the rent so adjusted would be £206.93 as at January 2020, in the absence of any suggestion otherwise. As to why the figure was the same for the subsequent two years is less than clear. In any event, the Court can identify no provision in the [NAME] enabling the addition of VAT and cannot identify why ground rent involves a VATable service. Contrary to insurance, there is no other company which might charge VAT. The Applicant failed to demonstrate it VAT to be chargeable.
233. [ADDRESS] is very cautious about taking any point not specifically raised by the Respondent. However, each demand contains two figures, only one of which as the Court sees it can be correct. In the ordinary course, the Court would have sought supplemental submissions as to the correct figure but in this instance the Court has been particularly mindful of the small sum in question, proportionality and that seeking such submissions may leave both parties worse off whatever the outcome. For those reasons, the Court proceeds doing its best on what is before it.
234. [ADDRESS] determines that in the absence of any justification for the higher figure- and in particular for the addition of VAT if that is what
42 has occurred, the claim for ground rent year on year which has been proved on the balance of probabilities by the Applicant is £206.93. The Applicant’s claim for ground rent therefore would at first blush succeed in the sum of £620.79 on the basis of the demands in the bundle.
235. However, the claim was for sums demanded between 25th February 2020 and 25th February 2021. Only one of the demands for ground rent was made during that period, that dated 17th December 2020. Therefore the sum in that demand, net of apparent VAT and so the £206.93 figure stated is the sum which the Court will award. The Claimant is therefore entitled to, and is granted, judgment in the sum of £206.93 in respect of ground rent claimed in the proceedings.
Costs included in the claim
236. Insofar as it was said that £180 of the claim was comprised of legal costs, the Court considers that those ought not to be part of the claim but rather be part of the costs of the claim unless there is a very clear reason why they are recoverable as part of the claim itself.
237. None has been provided. The Claim Form states “The Claimant also claims Legal Expenses for £180 in accordance with the terms of the [NAME].” The Claim Form does not explain which term is considered to produce an entitlement to legal costs as part of the claim itself. There is no suggestion that the amount claimed for costs had been demanded as service charges or administration charges- in which event they would have been matters for the Tribunal. There is no explanation for the amount claimed.
238. Save for general comments about the 1st Respondent being in default, in the context of the claims for costs originally claimed as service charges but then not pursued, the basis of the claim remains unclear throughout the rest of the case. The matters uncertain from the Claim Form are never entirely clarified.
239. The Applicant’s statement of case argues that the words of paragraph 9 of Part II of the Fifth Schedule “All costs….” are wide enough to allow for this claim and so too “all other expenses……” in paragraph 11, a similar but not identical argument to that referred to in paragraph 198 above.
240. The Tribunal repeats the reference to [NAME] and the judgement of [NAME] LJ that there must be a specific provision in “clear and unambiguous terms”. The provisions relied on by the Applicant are not, the Court determines anything like clear and unambiguous as to legal costs. The only provision which is clear is the very narrow one touched on by the Tribunal in paragraph 44 above, clause 3(7) and more specifically referring to “all costs charges and expenses (including Solicitors costs and Surveyors fees) incurred by [NAME] incidental to the preparation and service of a notice under sections 146 and 147 of the Law of Property Act 1925”.
43
241. That is, as the Appellant’s Statement of Case noted, very restrictive, not even covering work in contemplation of a notice or similar wording. It is also explicit in its reference to solicitors’ costs, indicating that the [NAME] could identify those and provide for them where appropriate. [ADDRESS] is confident that the [NAME] would have referred to solicitors’ costs and other legal fees and related expenses if they had intended to do so.
242. The Applicant is of course able to recover its legal costs in other circumstances where a party is able to do so, simply not as contractual costs. In any event, none of the above provides an entitlement to claim legal costs as part of the claim itself.
243. [ADDRESS] determines that the Applicant has failed to demonstrate a basis for this element of the claim, [ADDRESS] therefore disallows that part of the sum claimed in the Claim Form.
Interest
244. [ADDRESS] notes that the claim made for interest related to the period from 20th February 202o. That daily rate presumably assumed the claim succeeding in full, which it has not. Rather the claim has succeeded in the sum of £809.92. £0.18 is the daily rate of interest at 8% on that.
245. However, the Court does not allow interest at 8% Commonly awards have been at 1% or 2% during the period since the claim, in which time the bank base rate was generally very low and that impacted the approach of Courts. That rate has increased more recently. Taking matters in the round, the Court allows 4%, so a daily rate of £0.09. For a period of 1200 days to date, that amounts to a total of £108.00.
246. Therefore, the Applicant is entitled to £108.00 in respect of interest.
Conclusion
247. It will be identified that the Tribunal has determined certain of the service charges to be payable and reasonable of the various types identified by the above headings, utilised as those were the areas of dispute set out on behalf of the Respondents and adopted by the parties in presenting their cases.
248. [ADDRESS] and Tribunal note Mr [NAME] stated that it would be difficult to appropriately debit and credit the Respondents’ accounts, given that the relevant time period is not the same for each in light of their dates of purchase and the Applicant’s statement of case had sought the Tribunal’s determination to be limited essentially for that reason. However, the task of the Tribunal is to determine whether service charges in dispute are payable and reasonable and not to address the accounting consequences. The task of the Court was to
44 decide whether any sum was owed by the 1st Respondent to the Applicant of the sums claimed in the County Court claim. The question of whether any other Respondent owes any sum to the Applicant or is owed any sum by the Applicant, or indeed the 1st Respondent owes or is owed any other sum, is a matter for the parties to resolve, if necessary by separate proceedings but much better by negotiation or another form of dispute resolution such as mediation if necessary. Accounting difficulties caused to the Applicant because it has sought to charge service charges which have ben determined not to be payable or not to be reasonable is its own problem arising demands which ought not to have been made. Advancing an argument that the Tribunal ought not to disallow service charges which properly ought to be disallowed because that is inconvenient to the party which demanded them is optimistic in the extreme and unhesitatingly rejected by the Court and Tribunal.
249. Consequently, whilst the Tribunal posed a question as to the effect of purchases after 2017 and the sale by Mr and Ms [NAME], the Tribunal considers that the impact is one for the parties to take account of and does not alter the payability and reasonableness of the service charges. If the effect had been that no Respondent at all would be liable for service charges for any given year and so there had been no basis for the Tribunal to make any determination for such given year, that would have been another matter.
250. [ADDRESS] and Tribunal also observe that the Applicant and those Respondents who continue to own chalets on [NAME] will be involved in an ongoing relationship in that regard year on year. Save that all parties should carefully consider the effect of this Decision and what may be charged for and with what supporting evidence, the parties must sensible seek to maintain a constructive relationship, lest substantial sums be expended in further litigation. It is to be trusted that insofar as the Applicant sought to claim other sums not covered by the claimed as stated in the Claim Form, it will not be difficult to identify which of those sums would, or would not, be awarded, in the event of proceedings and hence those will not prove necessary.
Costs and fees- Court and Tribunal
251. There are different but over-lapping jurisdictions which fall to be exercised by the Tribunal and by the Court. There are distinct provisions as to costs.
252. Costs were referred to by Mr [APPELLANT] in his [NAME]. The Applicant did not oppose the disallowance of the recovery of the legal costs of these proceedings by the Applicant through the service charge pursuant to section 20C of the Act, making no distinction in that regard between costs of the County Court and costs of the Tribunal proceedings.
253. That element of costs is therefore addressed below as not requiring anything further.
45
254. However, the Applicant did also seek to claim costs against the 1st Respondent specifically as a defaulting leaseholder who had, the Applicant argued, forced it to issue proceedings. Reference was made to the provisions of rule 13 of The Tribunal Procedure (First Tier Tribunal) (Property Chamber) Rules 2013. The Applicant indicated that it would seek the costs of the County Court proceedings also. That raises the question of how best to deal with such costs.
255. In respect of the County Court costs, the claim was allocated to the Small Claims Track and so the jurisdiction to award costs is significant limited by the provisions of the Civil Procedure Rules. There ought to be summary assessment of any County Court costs awarded, although it must first be determined to which party, if either, any costs should be awarded. Submissions will be required as to both the nature and amount of the costs order. Consideration will also need to be given by the Tribunal to any costs application made pursuant to rule 13 in respect of costs of the Tribunal proceedings.
256. With a little reluctance the Court and Tribunal have concluded that written submissions should be required as to costs as between the Applicant and the First Respondent. Directions will be given by the Tribunal in respect of both elements.
257. Whilst some questions were asked of the 1st Respondent by Mr [RESPONDENT] in respect of costs, the Tribunal does not record those or the answers given at this stage.
Section 20C applications
258. With regard to the section 20C application of the Respondents and in light of the Applicant’s stated position at least in respect of costs other than managing agent’s fees, the Court and Tribunal do, separately and in respect of the specific costs falling with the jurisdiction of each, disallow the recovery of costs through the service charges pursuant to section 20C. [ADDRESS] and Tribunal do so without a separate heading for each decision on the basis that is unnecessary in this instance.
259. However, both the Court and Tribunal do make the following observations in respect of costs and whether the costs of the proceedings could be charged as service charges pursuant to the terms of the [NAME] in any event.
260. Clause 3(7) of the [NAME] provides that the Respondent shall pay:
“all costs, charges and expenses (including Solicitors costs, and surveyors fees) incurred by [NAME] incidental to the preparation and service of a notice under Sections 146 and 147 of the Law of Property Act 1925 notwithstanding forfeiture is avoided otherwise than by relief granted by the Court or incidental to the inspection of the premises and the drawing up of Schedules of dilapidations.”
46
261. There is nothing obvious in the Applicant’s claim which states that the County Court proceedings were taken incidental to the service of a forfeiture notice and/ or that such of the original proceedings as became Tribunal proceedings were pursued for that purpose. It is at least not obvious at this stage that proceedings would be recoverable by the Applicant from the Respondent pursuant to the terms of the [NAME]. The claim and the Tribunal proceedings do not relate to an inspection and schedule. However, neither the Court or the Tribunal reach any final determination on this point, which may be relevant to any claim for costs by the Applicant and which application ought not to be pre- judged.
262. Section 20C enables the disallowance of contractual costs which would otherwise be recoverable. There are a number of applicable case authorities in respect of section 20C. [NAME] -v- [COMPANY] [2013] UKUT 592 (LC) is the one most often cited. In very brief summary, the test to be applied boils down to whether an order is just and equitable, a test with wide scope for application to the circumstances of the individual case as considered appropriate by the Tribunal (or Court) exercising its discretion. The particular authority adds that it is, “essential to consider what will be the practical and financial consequences for all of those who will be affected by the order, and to bear those consequences in mind when deciding”.
263. In other circumstances, the Court and/ or Tribunal would be likely to consider whether there is an ability for the Applicant to seek to recover the costs of the proceedings and whether disallowance of the contractual costs is appropriate if there is no ability for the Applicant to seek to recover the costs of the proceedings in any event- so whether there is a need to determine such ability. However, on balance, the Court and Tribunal have concluded that an order disallowing recoverability of the Applicant’s costs as service charges charges would be just and equitable in light of the Applicant’s concession as to all costs other than managing agent fees and the determination by the Tribunal with regard to the recoverability of those fees, and that there is considerable merit in providing finality and avoiding any potential for later argument or proceedings over recovery of costs as service charges
264. Therefore, the Court and Tribunal have determined that the appropriate approach to take is to make the orders identified.
47
ANNEX - RIGHTS OF APPEAL
Appealing against the Tribunal’s decision
1. A written application for permission must be made to the First-tier Tribunal at the Regional office which has been dealing with the case. The application for permission to appeal must arrive at the Regional office within 28 days after the date this decision is sent to the parties.
2. If the application is not made within the 28-day time limit, such application must include a request for an extension of time and the reason for not complying with the 28-day time limit; the Tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed despite not being within the time limit.
3. The application for permission to appeal must state the grounds of appeal and state the result the party making the application is seeking. All applications for permission to appeal will be considered on the papers.
4. Any application to stay the effect of the decision must be made at the same time as the application for permission to appeal.
Appealing against a reserved judgment made by the Judge in his/her capacity as a Judge of the County Court
5. A written application for permission must be made to the court at the Regional Tribunal office which has been dealing with the case. The date that the judgment is sent to the parties is the hand-down date.
6. From the date when the judgment is sent to the parties (the hand-down date), the consideration of any application for permission to appeal is hereby adjourned for 28 days.
7. The application for permission to appeal must arrive at the Regional office within 28 days after the date this decision is sent to the parties:
1. The application for permission to appeal must state the grounds of appeal and state the result the party making the application is seeking. All applications for permission to appeal will be considered on the papers
2. If an application is made for permission to appeal and that application is refused, and a party wants to pursue an appeal, then the time to do so will be extended and that party must file an Appellant’s Notice at the Regional Tribunal office within 21 days after the date the refusal of permission decision is sent to the parties.
3. Any application to stay the effect of the order must be made at the same time as the application for permission to appeal.
Appealing against the decisions of the tribunal and the decisions of the Judge in his/her capacity as a Judge of the County Court
8. In this case, both the above routes should be followed.
48
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation from Consultation Requirements for …
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Reasonable
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Works to Prevent Water D…
- First-tier Tribunal (Property Chamber) Service Charges Not Payable Due to Invalid Demands
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules on Tenant's Liability for Service Charges
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges and Administration Fees Reasonabl…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Reasonable and Payable
- First-tier Tribunal (Property Chamber) Landlord Granted Exemption for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules on Service Charge Calculation Method
- First-tier Tribunal (Property Chamber) First-tier Tribunal Upholds Freeholder's Service Charges
- First-tier Tribunal (Property Chamber) First-tier Tribunal Determines Payability and Reasonableness of Service Cha…
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- Charges for repairs to paths and rebuilding retaining walls were determined to be payable and reasonable.
- Contributions to reserve funds and general contingency were deemed payable and reasonable.
- The applicant succeeded in its claim for ground rent.
❌ Tends to be rejected
- The court rejected the argument that it should not disallow service charges just because it would be inconvenient for the applicant.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The decision determined the payability and reasonableness of service charges for a holiday park.
Who was involved?
The decision involved a property management company and tenants of a holiday park.
How did the court decide, and why?
The court decided that the service charges were reasonable and payable based on the evidence presented.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 sections 27a and 20ZA were applied.
What was the argument that mattered most?
The argument that mattered most was the reasonableness and necessity of the service charges.
Was the decision for or against the person who brought the case?
The decision was for the property management company.
What does this mean for someone in a similar situation?
Tenants in a similar situation should ensure that service charges are reasonable and necessary.
What evidence or documents mattered?
Evidence and documents related to the cost breakdown and necessity of the service charges mattered.
Can a decision like this be appealed?
Yes, decisions like this can be appealed to a higher court.
Is it worth getting a solicitor for a case like this?
Yes, it is recommended to get a solicitor for a case like this.
