First-tier Tribunal Rules on Service Charge for Repair Works
📌 In brief
The First-tier Tribunal ruled on the reasonableness of proposed works and service charges under the Landlord and Tenant Act 1985. The Tribunal decided that works to renew roofs, brickwork, and tanks/a person are reasonably incurred and recoverable as part of the service charge.
⚖️ Legal holding
Proposed works to renew roofs, brickwork, and tanks/a person are reasonably incurred and recoverable as part of the service charge.
📖 What the law says
The term 'service charge' refers to an amount paid by a tenant as part of or in addition to rent, which can cover services, repairs, maintenance, improvements, insurance, or the landlord's management costs. The 'relevant costs' include the actual or estimated costs incurred by the landlord for these purposes.
Service charges should only cover costs that are reasonably incurred and must be of a reasonable standard. If the costs are not yet incurred but a service charge is payable, the amount should be reasonable, and adjustments will be made once the actual costs are known.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal ruled on the reasonableness of proposed works and service charges under the Landlord and Tenant Act 1985.
📜 Headnote Official document
The Tribunal determined the reasonableness of proposed works and service charges under the Landlord and Tenant Act 1985, ruling that works to renew roofs, brickwork, and tanks/fans are reasonably incurred and recoverable as part of the service charge.
📚 Full judgment Official document
OUTCOME: Allowed
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
Case Reference
:
CHI/00HN/LIS/2018/0065
Property
:
[COMPANY_1] 7 & 9 [ADDRESS] [POSTCODE]
Applicant
:
[redacted]
:
[NAME_2] of [COMPANY_4]
Respondent
:
[redacted]
:
Not represented
Type of Application
:
Section 27A Landlord and Tenant Act 1985
Tribunal Members
:
Judge N P Jutton, Mr T E Dickinson BSc FRICS and Mr M R Jenkinson
Date and Venue of Hearing
1 [ADDRESS] [POSTCODE]
Date of Decision
:
10th May 2019
DECISION
© CROWN COPYRIGHT 2019
1 Introduction
2. The Applicants seeks a determination under Section 27(3) of the Landlord and Tenant Act 1985 (the 1985 Act) that if it were to carry out certain works at the Property would the cost of such works be reasonably incurred and recoverable as part of the service charge.
3. The proposed works can be broken down into four separate areas. They are:
i) Balcony weatherproofing/concrete repairs.
ii) Roof renewal and associated works.
iii) Brickwork repairs to include installation of vertical and horizontal movement joints to external brickwork.
iv) Renewal of tanks and fans.
4. Directions were made by the Tribunal on the 11 December 2018. They provided for service by the Applicant and by the Respondents of statements of case together with supporting documents and for the preparation of a hearing bundle of documents.
5. At the hearing the Applicant was represented by [NAME_2] of the Applicant’s managing agents [COMPANY_4]. Also present at the hearing were:
[NAME_5] (Flat 32)
[NAME_7] of the managing agents [NAME_8]
[NAME_10] (Flat 4)
[NAME_11] (Flat 62)
[NAME_12] (Flat 3)
[NAME_13] (Flat 37)
[NAME_14] (Flat 63)
[NAME_15] (Flat 35)
[NAME_17] (Flat 8)
[NAME_18] (Flat 11)
[NAME_19] (Flat 51)
[NAME_8] of the managing agents [NAME_8]
[NAME_21] (Flat 45)
[NAME_22] on behalf of [NAME_23] (Flat 48)
6. Documents
7. The documents before the Tribunal comprised a bundle of documents (the main bundle) together with an addendum bundle. They included the application, the directions, statements of case, copy Lease for Flat 33, reports from experts including surveyors and structural engineers, notices served pursuant to Section 20 of the 1985 Act and observations thereon, specifications of works, tenders received from contractors and other
documents. References to page numbers in this decision are references to page numbers in the main bundle. References to documents in the addendum bundle are annotated ‘AB’. The Tribunal also received a skeleton argument on behalf of [NAME_23] of flat 48.
8. The Inspection
9. The Tribunal inspected the property on the morning of 1st May 2019.
10. [COMPANY_1] comprises two separate blocks of residential flats (which were described during the hearing as the South Block and the North Block) understood to have been built in the early 1970s. They are each seven storeys high. They are understood to have reinforced concrete structural frames with concrete floor slabs at each storey with external cavity walls formed with masonry and facing brick on the external skin. They have flat felted roofs. During its inspection the Tribunal viewed the balconies / interiors of Flats 35, 37 and 62. There was significant internal cracking to the internal walls of Flat 37. Looking from a window of Flat 37 (and from the roof) could be seen evidence of bulging to the brickwork of the external walls. The Tribunal also inspected the flat roof to the South Block and were shown areas from which core samples had been taken. It also inspected two galvanised water tanks and housing for roof fans.
11. The Law
12. The relevant statutory provisions are to be found in Sections 18, 19 and 27a of the 1985 Act. They provide as follows:
The 1985 Act
18 (1) In the following provisions of this Act “service charge” means an amount payable by a tenant of a dwelling as part of or in addition to the rent –
(a) which is payable, directly or indirectly, for services, repairs, maintenance, improvements or insurance or the landlord’s costs of management, and
(b) the whole or part of which varies or may vary according to the relevant costs.
(2) The relevant costs are the costs or estimated costs incurred or to be incurred by or on behalf of the landlord, or a superior landlord, in connection with the matters for which the service charge is payable.
(3) For this purpose –
(a) “costs” includes overheads, and
(b) costs are relevant costs in relation to a service charge whether they are incurred, or to be incurred, in the period for which the service charge is payable or in an earlier or later period.
19 (1) Relevant costs shall be taken into account in determining the amount of a service charge payable for a period –
(a) only to the extent that they are reasonably incurred, and
(b) where they are incurred on the provision of services or the carrying out of works, only if the services or works are of a reasonable standard;
and the amount payable shall be limited accordingly.
(2) Where a service charge is payable before the relevant costs are incurred, no greater amount than is reasonable is so payable, and after the relevant costs have been incurred any necessary adjustment shall be made by repayment, reduction or subsequent charges or otherwise
27A (1) …
(2) …
(3) An application may also be made to the appropriate tribunal for a determination whether, if costs were incurred for services, repairs, maintenance, improvements, insurance or management of any specified description, a service charge would be payable for the costs and, if it would, as to –
(a) the person by whom it would be payable,
(b) the person to whom it would be payable,
(c) the amount which would be payable,
(d) the date at or by which it would be payable, and
(e) the manner in which it would be payable.
(4) No application under subsection (1) or (3) may be made in respect of a matter which –
(a) has been agreed or admitted by the tenant,
(b) has been, or is to be, referred to arbitration pursuant to a post dispute arbitration agreement to which the tenant is a party,
(c) has been the subject of determination by a court, or
(d) has been the subject of determination by an arbitral tribunal pursuant to a post-dispute arbitration agreement.
(5) But the tenant is not to be taken to have agreed or admitted any matter by reason only of having made any payment.
13. The Lease
14. A copy of the Lease of Flat 33 at the Property appears at pages 6 – 22 and
it is assumed that all Leases at the Property are in the same form
15. The Applicant’s repairing obligations are set out in the Sixth Schedule.
Clause 2 of the Sixth Schedule provides as follows:
“(2) To maintain and keep in good and substantial repair and
condition and (where necessary) renew:
(a) the main structure of the Building and the Estate including
the principle internal girders and exterior walls and balconies
and the foundations and the roofs thereof with their main water
tanks main drains gutters and rainwater pipes (other than
those included in this demise or in the demise of any other flat in
the Building)
(b) all such gas and water mains and pipes drains waste water
and sewerage ducts and electric cables and wires as made by
virtue of the terms of this Lease be enjoyed or used by the Tenant
in common with the owners or [NAME_3] of other flats in the
Building.
…..
16. By Clause 4 of the Lease the Lessee covenants to pay to the Applicant by
way of a service charge a share of the costs incurred or to be incurred by
the Applicant in fulfilling its service obligations as set out in Schedule Six
of the Lease.
17. At the hearing it was agreed with the parties that there were four areas
of proposed works at the property which fell to be addressed by the
Tribunal (as identified above). It was agreed to address each area of
work in turn. They can be conveniently referred to under headings of:
1. Works to balconies
2. Works to the walls/brickwork
3. Works to the roof
4. Works to the tanks and fans.
18. Balconies
19. [NAME_2] explained that the original application to the Tribunal
in respect of waterproofing to the balconies was no longer proceeding.
There was no specification for the works as yet nor had the Applicant
begun the Section 20 consultation process. [NAME_2] said that
she had recently written to the Applicant’s insurers in relation to the
proposed works and she was waiting to receive a response from them.
20. In the circumstances it was agreed that there was insufficient
information before the Tribunal for the Tribunal to make a
determination in respect of proposed works to the balconies. In the
circumstances the Tribunal agreed to stay that part of the application for
a period of six months. That there would be liberty to apply for either
party to restore the application within six months but if it wasn’t restored
within six months the application would be dismissed.
21. Walls / Brickwork
22. The Applicants’ [NAME_2] said that when the current managing agents ([NAME_8])
had taken over the management of the property they had been instructed
to put together a five year plan which, amongst other things, would
address works required to the walls and brickwork. A structural
engineer [NAME_25] of [COMPANY_25] had been
instructed to report (85 to 96). Subsequently a surveyor [NAME_26] of [COMPANY_26] had prepared a specification for
the works (97 – 122). A notice had been served on the [NAME_3]
pursuant to Section 20 of the 1985 Act on 11 December 2018 (81 – 82).
Observations had been received from certain [NAME_3] (eg. 122a) and
tenders received from contractors. A tender report in respect of tenders
received had been produced by [NAME_26] (5–16AB) dated 22 March
2019. A second notice pursuant to the consultation process required by
Section 20 of the 1985 Act had yet to be served.
23. [NAME_2] said that it had been made clear in replies to
observations received from [NAME_3] (eg. 122a) that the works set out in
the specification included “associated works”. That would cover work to
repair brickwork and damaged masonry. The works as described in the
schedule of works (114) included work to horizontal and vertical
movement joints and the removal and reinstatement of brickwork. [NAME_2] understood that would include works to reinstate affected
brickwork to both blocks. As set out in the response to observations
(112a-j) the structural engineer retained by the Applicant had advised
that every elevation be examined and if certain works were, in the event,
not required because inter alia of earlier works carried out then they
would be removed from the contract. The specification, [NAME_2] said had been prepared under a worst case scenario so that if
works set out in the specification were found not to be required then they
wouldn’t be carried out. There was however a contingency sum in the
specification which was shown in the Tender analysis (13AB) of £15,000.
[NAME_2] said that the aim was to avoid overspend. That the
specification had been drawn to cover all eventualities as far as possible.
If in the event work was not required it wouldn’t be carried out and there
would be a saving. In answer to questions from the Tribunal [NAME_2] said that the reference to Brexit uncertainty in the Tender Report
(11AB), as she understood it, related to a small risk of an over-run on
material costs. [NAME_2] explained that scaffolding (the
anticipated cost of which is in the Tender analysis (13AB)) would not be
on the elevations which contained the balconies.
24. The Respondent’s Case
25. [NAME_13] 37.
[NAME_13] said that work had been carried out to the southern block in 2007. He described this as phase one. He was concerned that the Applicant had changed surveyors from one [NAME_27] to [NAME_26] and that as such there was a lack of continuity of surveyors. He made reference to what he described as a ‘combined specification’ which he said had been presented in June 2018 to cover all four areas of work. He accepted on being questioned by the Tribunal that the Applicant was not proceeding with that combined specification and that it was not the subject of the application before the Tribunal.
26. [NAME_13] said that he accepted the findings of [NAME_25], the structural engineer, but was surprised at what he said were certain omissions from [NAME_25]’s report.
27. [NAME_13] said that the new specification which related to work to vertical and horizontal movement joints was received in December 2018 and he had submitted his observations on it in January 2019. He was concerned that the specification did not reference previous works carried out. He was particularly concerned, understandably, that he felt the specification did not include works to the walls of his flat where there were clearly problems with movement and cracking. [NAME_13] said that he didn’t have confidence in [NAME_26].
28. [NAME_13] said that he understood that the specification had been prepared on the basis that this was a ‘clean building’. That is on the basis that the walls were not damaged. However there was known damage and that should he believed be referred to in the specification. That therefore the specification should be revised and resubmitted and a new consultation process begun. He was concerned that the surveyor’s Tender Report did not make reference to asbestos removal notwithstanding the fact that it was known that asbestos was present in the building. He had no objection, per se, to a contingency sum but submitted that that shouldn’t be within the contract with the chosen contractor because that was an invitation to the contractor to spend those monies. It should be kept back as a budget figure.
29. [NAME_15] 35
30. [NAME_15] said that from the paperwork he believed that there were two key issues that should be addressed. Firstly that account be taken very precisely as to what repairs had been undertaken historically. Only thereafter could the appropriate remedial action be addressed. Secondly there was the question as to whether new expansion movement joints should be installed before remedial works to the walls or after. That was he said a matter which should be addressed to the structural engineer [NAME_25] and [NAME_25]’s recommendations followed.
31. [NAME_22] (on behalf of [NAME_23] of Flat 48)
32. [NAME_22] said that there had been historical works carried out to one block in 2012 and another block in 2012 and 2017. He said there was a concern that that historic work had not been done properly. That full account should be taken as to whether expansion joints had been incorporated into the previous repairs and if so it shouldn’t be necessary to do that work again. That proper regard should be taken of [NAME_13]’s concerns as to whether expansion joints should be fitted to some of the walls before or after remedial repairs had been carried out. [NAME_22] made the point that the Tender Analysis at 13AB referred only to supply and fitting of vertical movement joints and there was no reference to horizontal movement joints.
33. [NAME_11] 62
34. [NAME_11] said that consideration should be given to previous work had been carried out in 2015/16. He was concerned that the surveyor [NAME_27] had been replaced by [NAME_26] who then in turn employed [NAME_25] the structural engineer who has advised of the need
to install vertical and horizontal joints to external brickwork even though [NAME_11] said that movement joints had been fitted previously when work was carried out on the north and west wall of Block C/D and the east wall of Block H/J.
35. [NAME_9] 4
[NAME_9] said that based upon the information available there was a gap in the specification and wondered if there was a contingency sum. [NAME_9] said that he was concerned about a cost overrun. He described the processes to date as “a bit of a mush” and “a money pit”. That the Section 20 consultation process had yet to be completed.
36. The Tribunal’s Decision
37. The issue for the Tribunal is that if the works proposed by the Applicant as set out in the specification (97 – 122) were carried out would the cost of those works be reasonably incurred and be recoverable from the [NAME_3] under the terms of the individual Leases. From the evidence before it and its inspection of the Property the Tribunal is of the view that there is a degree of urgency for the work to be carried out, not least to rectify the serious problem manifested by internal cracking suffered for example by [NAME_13] in Flat 37. The Tribunal notes that the structural engineer [NAME_25] recommends at the end of his report of August 2018 at paragraph 5.10 that the programme of repair works should be put in hand “as soon as possible, to avoid further damage to the building” (96).
38. The Tribunal takes into account the fact that the repairs are to be carried out pursuant to a JCT Minor Works Building Contract. Further that the Schedule of Works does make reference to both horizontal and vertical movement joints. The Tribunal is satisfied from the specification and from the submissions made to it at the hearing that the proposed works (not least because they are stated to include “associated works”) will include any related works which become apparent during the course of the works to include the removal and reinstatement of brickwork where required and that regard will be had to works historically carried out. The Tribunal notes that sensibly there is provision for contingencies in the specification and accepts [NAME_2]’s submission that the specification has been prepared on a worst case scenario so that in the event that once the building is opened up if it is found that certain works are not required they will not be carried out.
39. The proposed works remain subject to the completion of the consultation process as required by Section 20 of The 1985 Act and the parties are reminded of the need to complete that process and for the Applicant to have proper regard to observations submitted to it by [NAME_3].
40. In all of the circumstances the Tribunal is satisfied that if the proposed works as set out in the specification are carried out the cost incurred thereby (provided they are reasonable and the work is of a reasonable
standard) may be recovered by the Applicant from the [NAME_3] as part of the service charge.
41. The Roof
42. The Applicant’s Case
43. [NAME_2] explained that in 2016 core samples were taken from the roofs of both blocks which indicated that the roofs were failing. A local roofer, [NAME_28], was asked to inspect. He also took core samples and confirmed that the roofs were failing. That further samples had been taken since. That some of the top floor flats had experienced the ingress of damp. There is a specification for the proposed works at pages 134 – 139. That is a specification for the renewal of the roofs. The first notice under the Section 20 consultation process had been served and observations received. Tenders had also been received and the surveyor [NAME_26] had prepared a Tender Report (26 – 33AB).
44. All of the core samples taken, [NAME_2] said, showed the insulation to be saturated. The proposal, as a matter of convenience and in particular to save costs, was to carry out the works to the roof at the same time as the works were carried out to the walls and brickwork so as to make use of the same scaffolding. [NAME_2] understood that the roofs had last been replaced 20 years ago and each had a concrete deck. In answer to a question from the Tribunal with reference to the Tender Analysis prepared by the surveyor [NAME_26] (33AB) [NAME_2] agreed that the specification and the Tender Analysis showed a number of preparatory items designed to cover unforeseen issues which would only be known once the roof was opened up so again the approach was to err on the side of caution.
45. In answer to a question from the Tribunal [NAME_2] said that if, instead of renewal, the roof was patched now but then had to be renewed in say three to four years’ time there would be an additional substantial scaffolding cost although not quite as much as the scaffolding currently proposed as only one area would be worked on, ie. the roof, rather than different levels and heights of the walls. One of the problems [NAME_2] suggested with just patching was knowing where to patch.
46. [NAME_13]
47. [NAME_13] said that in 2016 some local damage had been reported to the roofs and a survey had suggested that they were nearing the end of their design life. Although he had made observations in relation to the first Section 20 consultation notice he didn’t feel that the [NAME_3] as a whole had had sufficient opportunity to make observations. He said that he had asked the Applicant to include in the list of contractors a company called [NAME_29] and they had not been. That company, he said, were a member of the Intelligent Membrane Association. He felt that a contingency figure should not be included within the contract price because that was an invitation, in his view, for contractors to use it. It should just be a budget issue. He was concerned, he said, that he hadn’t received historic reports on the roof that he had asked for. He did not
consider, on the information available at the current time, that it was necessary to renew or replace the roofs in their entirety. He felt that consideration should be given to local repairs being carried out by instructing the original roofing contractor.
48. In response to [NAME_13]’s submission that he had asked for [NAME_29] to be included in the list of contractors, [NAME_2] confirmed that she had received correspondence from [NAME_13] asking that consideration be given to that company but had not realised that was a nomination for that company to be approached. [NAME_2] confirmed that a tender would be sent to [NAME_29] provided that they were roofing contractors.
49. [NAME_14]
50. [NAME_14] said that core samples had been taken on four or five occasions which all showed water ingress which together proved that the roof was failing.
51. [NAME_22]
52. [NAME_22] said that he understood that patchwork had been carried out to cure a leak that had been suffered by Flat 62 and that had been successful. He questioned therefore why couldn’t patchwork repairs be carried out now and renewal of roofs deferred to a later date. [NAME_22] in written submissions on behalf of [NAME_23] states at paragraph 34 of those submissions (495) there was little doubt that the renewal of the felt lining and associated repairs were necessary and appropriate but [NAME_23] had concerns about the estimated cost.
53. [NAME_11]
50. [NAME_11] felt that there should be more emphasis on ongoing roof repairs. He accepted that the lead flashing around the lift housing was failing and should be replaced and felt that it may be sufficient to do those repairs and to patch the roof. Historically when his flat, Flat 62, had suffered damp he had gone onto the roof and cleared rubbish from the roof and cleared out drains and that had been sufficient.
55. [NAME_5]
56. [NAME_5] said that she understood that additional core samples had been taken by [NAME_29] who had taken some seven samples from one block, four of which were wet and three were dry and five samples from the other block, two of which were wet. The two of which were wet were in positions where you would not normally expect failure. So it was difficult to predict where problems with the ingress of damp would be.
57. [NAME_15]
58. [NAME_15] said that he had taken some independent advice. He agreed that the lead flashings around the lift housing required replacing and
that repairs were certainly needed soon. He understood that beneath the roof cover was a concrete base on a metal skeleton. That skeleton he said rusts. That until the roof cover was removed it was impossible to be 100% sure what might be found. That there might be a lot more work required in relation to the metal skeleton. He was concerned about costs escalating and therefore felt that a very careful approach should be adopted. He asked why a quote had not been obtained just to carry out repairs as opposed to renewing and replacing the roof. He said that the advice which he had received was to only remove the roof covering and expose the roof if it was really necessary. In his written statement of case (405) [NAME_15] says that he believes that [NAME_26]’s recommendation to replace the roof was inappropriate. He was concerned that supporting rationale or a technical cost benefit analysis should be made available to the [NAME_3] before a decision was made to replace the roofs in their entirety as opposed to repairing.
59. [NAME_9]
60. [NAME_9] said that he had some doubts over the surveyor’s competence. He wondered whether the maintenance work carried out since 2016 might have invalidated the insurance. He felt that a 20 year lifespan for such a roof was too short and it should be more like 50 years.
61. The Tribunal’s Decision
62. Clause 2 of the sixth schedule of the Lease provides that the Applicant will ‘maintain and keep in good and substantial repair and condition and (where necessary) renew’ the main structure of the building including the roof. In the experience of the Tribunal as an expert Tribunal the lifespan of a roof of this nature is closer to 20 years rather than the 50 years suggested by [NAME_9]. Given the results of core samples taken on several occasions in the view of the Tribunal it is reasonable to conclude that the roofs of both blocks are failing. Although it could be possible to proceed on the basis of ongoing patch repairs there could be no guarantee that that would be sufficient to stop the ingress of damp. Further, in the view of the Tribunal, it is a reasonable management decision to make use of the scaffold to be erected to do the repair works to the walls and brickwork and thus save further potentially substantial scaffolding costs in a few years’ time.
63. The Tribunal notes that the specification for the works and the tenders received go into some detail as to works which may only be known once the roofs have been exposed. To that extent the tenders err on the side of caution. For example, the Tender Analysis at 33AB includes provisions for preparation of roof decks, a provisional sum and a contingency sum.
64. Upon the basis of the advice that the Applicants have received, the surveys carried out, the core samples taken and given their age it is reasonable to conclude that it is necessary to renew the roofs. In all circumstances having considered the evidence carefully and the submissions made by the parties the Tribunal is satisfied that if the proposed works are carried out to renew the roofs of both blocks in
accordance with the specification the costs incurred thereby (provided that they are reasonable and the work is of a reasonable standard) would be reasonably incurred. Again the parties are reminded of the importance of completing the section 20 consultation process and for proper regard to be had by the Applicant to observations received from [NAME_3].
65. Renewal of Tanks and Fans
66 The Applicant’s Case
67. [NAME_2] referred the Tribunal to reports obtained from a company called [COMPANY_30] on the cold water storage tanks (169 – 174) and on the fans (175 – 180). [NAME_2] said that when her company had originally taken over the management of the property they had inspected the tanks and fans and realised that there were issues to be addressed so had instructed a consulting engineer. On the basis of the engineer’s report the specifications had been obtained. The engineer had made a presentation last July at the Applicant company’s AGM where he reported that less than 50% of the fans were working and that the water tanks were in a very poor condition.
68. A specification running to some 200 pages had been produced and a Section 20 consultation process commenced which had now reached the stage of the second notice being sent out. Observations had been received from certain [NAME_3] which had not been replied to yet.
69. [NAME_2] said she understood that some [NAME_3] were concerned that it was proposed not to replace the tanks on a like for like basis. The proposal was to replace the existing tanks with smaller tanks made of glass reinforced plastic (GRP) as opposed to galvanised steel. That the health and safety advice received was that smaller tanks reduced the risk of Legionella Disease which in her submission ‘trumped’ arguments that the tanks should be replaced on a like for like basis.
70. [NAME_2] said that the work would be carried out under the terms of a JCT Minor Works 2016 contract which would address administration, payments terms etc. The works would be supervised by the consulting supervising engineer. [NAME_2] confirmed that the Section 20 consultation process was continuing and that there would be proper regard to all observations received from [NAME_3]. The process would include due diligence in respect of proposed contractors.
71. [NAME_2] said the engineer’s report in relation to the fans had concluded that the fans were in very poor condition. The engineer had opened up a couple of the fans and concluded that they were all well past their serviceable life. A large part of the costs of the works, [NAME_2] said, was that of cranes. It made sense to address the replacement of the tanks and the fans at the same time. She said that there was a real concern that the tanks were not healthy and further because of the failure of fans some flats had no circulation. She believed that the existing fans fell far short of those required by current building standards. The fact
that the cold water tanks had stagnant water was dangerous from a health and safety perspective. The Applicant had considered lining the tanks but had been advised that there would be a very expensive and difficult process and not necessarily certain to work. The cost of craning tanks onto the roof, [NAME_2] said, was at least £1,200 per day. That is why it made sense to do all of the works for the tanks and the fans at the same time. It also made sense to do the works to replace the tanks and the fans before the renewal of the roof. She believed the installation of new fans would also limit the need for certain of the duct work to be repaired.
72. [NAME_15]
73. [NAME_15] said it remained possible to replace the galvanised tanks with new galvanised tanks rather than GRP. In his view galvanised tanks had a longer life. He accepted that there were pro’s and con’s in respect of both galvanised and GRP tanks. There should be, he submitted in his statement of case, a proper comparative benefit cost analysis carried out (405).
74. [NAME_13]
75. [NAME_13] said he had historically requested copies of inspection reports and it had taken over a year for those to be received. There was, he felt, no substantial report from a consultant with a final solution. He had submitted observations in respect of the proposed works as part of the Section 20 consultation process. He believed that the lowest price tender received didn’t include the full scope of the proposed works. Nor was there evidence of due diligence of the contractors. He felt that the contingency figure shown in the Tender Analysis should not be included in the contract price but should be part of the budget. He wondered whether the existing fans and motors could be refurbished rather than replaced. He awaited, [NAME_13] said, responses to his observations at the end of the Section 20 process.
76. [NAME_9]
77. [NAME_9] said that the consultation was incomplete. He wondered what due diligence had been carried out in relation to the proposed contractors. He felt that there was a lack of governance and a lack of proper due diligence of contractors.
78. [NAME_11]
79. [NAME_11] said that in 2016 an estimate had been obtained to update the cold water tanks for £12,000. He felt that if £12,000 worth of works was carried out to the tanks that would be sufficient.
80. As to the fans [NAME_11] said that in each encasement enclosing the fans there were two fans. If one fan gave out it would switch to the other fan. These particular fans he understood were still being manufactured. He questioned the suggestion that 50% of the fans didn’t work. He
accepted that on occasions hot water did overflow into the cold water tank making the water warm.
81. [NAME_19]
82. [NAME_19] said that she purchased her flat, Flat 51, last year and had had a survey carried out. The surveyor had commented on the poor state of the tanks and suggested that they needed replacing. She understood that some of the fan ducting had become horizontal and didn’t work properly. The structure of the ducting needed to be addressed.
83. [NAME_22]
84. [NAME_22] said that he felt that a proper cost benefit analysis should be carried out on both the tanks and the fans before proceeding. That if it were the case that the original fans were still serviceable, even though they might require more maintenance, then there was an argument that it wasn’t necessary under the terms of the Lease to replace them.
85. The Tribunal’s Decision
86. The issue for the Tribunal is whether or not it is necessary to replace the tanks and the fans. More particularly as regards the tanks whether they should be replaced with smaller GRP tanks or replaced on a like for like basis. As to the fans whether they should be replaced or whether they remained serviceable and could be maintained. If the works carried out as proposed by the Applicant were completed whether the cost of those works would be reasonably incurred.
87. The cold water tanks are some 47 years old. The Tribunal inspected two of the tanks. There was evidence of them rusting. The Tribunal accepts that they constitute a health risk of Legionella Disease. In the view of the Tribunal the proposed replacement of the existing galvanised tanks with smaller tanks would reduce the health risk and the risk of flooding.
88. In the view of the Tribunal to replace galvanised tanks with more modern GRP tanks was reasonable and accepted current practice. The Tribunal accepts that there are arguments for and against galvanised tanks as opposed to GRP tanks. Galvanised tanks may have a longer life but they rust.
89. The Tribunal notes that [NAME_19]’s relatively recent survey concluded that the tanks required replacing. In the view of the Tribunal lining the tanks would not be a reasonable, or indeed, sensible way of proceeding. Further that it made sense to replace the tanks and fans at the same time to make efficient use of the cost of craning.
90. In the view of the Tribunal the fact that up to 50% of the fans were failing at any given time was clearly indicative of them reaching the end of their serviceable life. On the basis of the evidence before it both in the reports in the bundle of documents and the submissions made by the parties at the hearing the Tribunal is satisfied that if the proposed works were carried out to replace the cold water tanks and the fans such works would
be reasonably incurred. That the costs of such works would be recoverable under the terms of the Lease from the [NAME_3] as part of the service charge (provided those costs were reasonable and the work was carried out to a reasonable standard).
91. Again the Tribunal reminds the parties of the importance of completing the Section 20 consultation process and of the Applicant having proper and due regard and consideration to observations made by [NAME_3] as part of that process.
92. Summary of Tribunal’s Decision
93. If the works proposed by the Applicant to renew the roofs of the blocks and associated works, brickwork repairs to include the installation of vertical and horizontal movement joints to external brickwork and for the renewal of tanks and fans are carried out in accordance with the specifications produced by the Applicant then the costs thereby incurred by the Applicant (provided the costs are reasonable and the work of a reasonable standard) may be recovered by the Applicant from the [NAME_3] as part of the service charge.
94. The Applicant’s application in respect of proposed works to the balcony weatherproofing / concrete repairs is stayed for a period of six months from the date of this decision with liberty to either party to apply to restore that application within that six month period. If that application is not restored within the said six month period the application shall be dismissed without further order.
Dated this 10th day of May 2019
Judge N P Jutton
Appeals
1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application to the First-tier Tribunal at the Regional office which has been dealing with the case.
2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.
3. If the person wishing to appeal does not comply with the 28-day time limit, the person shall include with the application for permission to
appeal a request for an extension of time and the reason for not complying with the 28-day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.
4. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.
📊 How courts decide similar cases
Among 11 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) Service Charges Capped Due to Consultation Failure
- First-tier Tribunal (Property Chamber) First-tier Tribunal Determines Service Charge Proportions and Costs
- First-tier Tribunal (Property Chamber) Tenant Successfully Challenges Service Charges Under Landlord and Tenant Ac…
- First-tier Tribunal (Property Chamber) Tribunal Rules on Service Charge Liability for Tenant
- First-tier Tribunal (Property Chamber) First-tier Tribunal Decides on Reasonableness of Service Charges and Admin …
- First-tier Tribunal (Property Chamber) First-tier Tribunal rules on service charges for restaurant and laundry
- First-tier Tribunal (Property Chamber) Reasonableness of Service Charges and Legal Costs Ruled
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules on Service Charges and Administration Fees
- First-tier Tribunal (Property Chamber) First-tier Tribunal Determines Reasonableness of Estimated Service Charge
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Payable
- First-tier Tribunal (Property Chamber) First-tier Tribunal Decides on Service Charges and Administration Charges
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- Service charges are considered reasonable if they are well-documented and justified.
- Works such as renewing roofs, brickwork, and tanks/fans are deemed necessary and recoverable.
- Tenants are required to pay reasonable service charges as per their lease agreement.
- Courts allow service charges if they comply with the Landlord and Tenant Act 1985.
- Determinations of the reasonableness of service charges are often allowed in part.
❌ Tends to be rejected
- Challenges to service charges are dismissed if there's no valid set-off claim.
- Requests for assessments of service charges are sometimes dismissed if the charges are already deemed reasonable.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Tribunal ruled that works to renew roofs, brickwork, and tanks/fans are reasonably incurred and recoverable as part of the service charge.
Who was involved?
The case involved a landlord and tenants of a multi-story building.
How did the court decide, and why?
The court decided that the proposed works were reasonable and recoverable based on the condition of the property and the necessity of the works.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 sections 18, 19, and 27A were applied.
What was the argument that mattered most?
The argument that mattered most was the necessity and reasonableness of the proposed works based on the condition of the property.
Was the decision for or against the person who brought the case?
The decision was in favour of the landlord.
What does this mean for someone in a similar situation?
Tenants in a similar situation should ensure that the proposed works are reasonable and necessary before agreeing to the service charge.
What evidence or documents mattered?
Evidence included expert reports, specifications of works, and tenders received from contractors.
Can a decision like this be appealed?
Yes, a person wishing to appeal this decision must seek permission from the First-tier Tribunal within 28 days of receiving written reasons for the decision.
Is it worth getting a solicitor for a case like this?
It is recommended to seek advice from a qualified solicitor for cases involving service charges and repair works.
