First-tier Tribunal Upholds Improvement Notice but Allows Revocation
📌 In brief
The First-tier Tribunal confirmed an Improvement Notice but allowed it to be revoked because the work to address the noise hazard had been completed. The case involved a Category 2 Hazard identified under the Housing a person and Safety Rating System (HHSRS).
⚖️ Legal holding
A local housing authority has the power to serve an Improvement Notice where the application of the HHSRS identifies a category 2 hazard.
📖 What the law says
A local housing authority can take certain actions, including serving an improvement notice, if they believe a category 2 hazard exists on residential property.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal confirmed the Improvement Notice but allowed its revocation as the work had been completed.
📜 Headnote Official document
The Tribunal confirmed the Improvement Notice served by the local housing authority but allowed its revocation as the work had been completed. The case involved a Category 2 Hazard identified under the Housing Health and Safety Rating System (HHSRS).
📚 Full judgment Official document
OUTCOME: Allowed in Part
1
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case reference : BIR/31UC/HIN/2021/0006 Property : 61b [ADDRESS] [POSTCODE] Applicant: [redacted] : [NAME] Property Respondent : [redacted] Representative :
Mr [COUNSEL] [NAME] [NAME] of application : Application under paragraph 10(1) of Schedule 1 of the Housing Act 2004 to appeal against an Improvement Notice Tribunal members :
Mr [NAME] Mr [NAME] – [NAME]. JP
Venue : The property was inspected on 28th January 2022. There was no hearing and the matter was dealt with by a paper determination Date of decision : 11th February 2022
DECISION
2
BACKGROUND
1. This is an Application by [APPELLANT] and [NAME] [APPELLANT] (‘‘the Applicants’’) under the Housing Act 2004 (‘‘the Act’’) against an Improvement Notice (‘‘the Notice’’) served by Charnwood Borough Council (‘‘the Respondent’’) in respect of 61b [ADDRESS], [POSTCODE] (‘‘the Property’’).
2. On 26th October 2020 the Respondent wrote to the Applicants following an inspection of the property on 6th October 2020. The letter alerted the Applicants to the presence of Category 2 hazards at the property. On 24th November 2020 the Respondent contacted the Applicants for an update regarding the remedial works and was informed on 27th November 2020 that they were ‘in the process of being booked in’. Various correspondence continued between the parties until 3rd September 2021.
3. On 3rd September 2021 the Respondent served on the Applicants an Improvement Notice in accordance with section 12 of the Act. On the same date the Respondent served on the Applicants a demand for payment in the sum of £210.30 in accordance with section 49 of the Act for the cost of taking [NAME] action.
4. On 21st September 2021, the Applicants submitted an application to the First-tier Tribunal (Property Chamber) (‘‘the Tribunal’’) appealing against the Notice dated 3rd September 2021 and the demand for payment. The application was received by the Tribunal on 22nd September 2021.
5. Directions were issued by the Tribunal on 30th September 2021 following which submissions were made by both parties.
THE PROPERTY INSPECTION
6. The Tribunal inspected the property on 28th January 2022 in the presence of Mr [NAME] (Charnwood Borough Council), Mr [NAME] ([NAME]), Mr [NAME] ([NAME]), Mr [NAME] ([NAME]) and Mrs [NAME] ([NAME]).
7. [NAME] are the agents for the Applicants, Charnwood Borough Council are the Respondent’s and [NAME] are the Leaseholders of the flats.
8. The property was found to comprise a small self-contained ground floor bed-sit flat approached via a shared pedestrian entryway from [ADDRESS]. It is located to the rear of retail shop premises.
9. The accommodation comprises a bed-sitting room with Kitchen area, sitting area and bedroom area. There is a separate bathroom being fitted with a three-piece sanitary suite including a shower mixer over the bath.
10. The property has UPVC double glazing and gas fired central heating provided by the boiler located in a cupboard off the bathroom.
THE APPLICABLE LAW 11. The Act introduced a new system for the assessment of housing conditions and for the [NAME] of housing standards. The [NAME] and Safety Rating System (‘HHSRS’) replaces the system imposed by the Housing Act 1985, which was based upon
3
the concept of unfitness. The HHSRS places the emphasis on the risk to [NAME] and safety by identifying specified housing related hazards and the assessment of their seriousness by reference to (1) the likelihood over the period of 12 months of an occurrence that could result in harm to the occupier and (2) the range of harms that could result from such an occurrence. These two factors are combined in a prescribed formula to give a numerical score for each hazard. The range of numerical scores are banded into ten hazard bands, with band A denoting the most dangerous hazards and Band J the least dangerous. Hazards in Bands A to C (which cover numerical scores of 1000 or more) are classified as ‘category 1 hazards’ and those in bands D to J (which cover numerical scores of less than 1000) are classified as ‘category 2 hazards’.
12. Where the application of the HHSRS identifies a category 1 hazard the local housing authority has a duty under section 5 (1) of the Act to take appropriate [NAME] action. Section 5 (2) sets out the courses of action (which include the serving of an [NAME] notice) which may constitute appropriate [NAME] action.
13. Where the application of the HHSRS identifies a category 2 hazard the local housing authority has a power under section 7(1) of the Act to take [NAME] action. The serving of an Improvement Notice is one of the types of [NAME] action which may be taken.
14. Section 9 of the Act requires the local authority to have regard to any guidance for the time being given by the appropriate national authority about the exercise of their functions in connection with the HHSRS. In February 2006 the Secretary of State issued ‘[NAME] and Safety Rating System – Operating Guidance’ (‘Operating Guidance’) which deals with the assessment and scoring of HHSRS hazards. At the same time the Secretary of State also issued ‘[NAME] and [NAME]’ (‘[NAME]) which is intended to assist local housing authorities in deciding which is the most appropriate course of action under section 5 of the Act and how they should exercise their discretionary Powers under section 7 of the Act.
15. The person upon whom an Improvement Notice is served may appeal to a First-tier Tribunal (Property Chamber), who may by order confirm, quash or vary the Improvement Notice under Part 3 of Schedule 1 to the Act. THE IMPROVEMENT NOTICE
16. The one hazard identified in the Notice was:
Noise
The flat roof of the premises serves as a walkway to access the first-floor flats above. The walkway consists of timber decking which appears to be resting directly on the roof deck. There is noise transmission into the premises when people traverse the walkway.
Specification of works to be carried out
Either suspend the timber decking off the flat roof of the premises to prevent noise transmission into the fabric of the premises or investigate whether the roof space below the roof deck is insulated to prevent noise transmission and upgrade as necessary. The current standards for sound insulation can be found in the Building Regulations 2010 Approved Document E: Resistance to the Passage of Sound.
17. The hazard identified was judged as being a Category 2 Hazard.
4
18. The Notice stated that works were to be commenced by 11th October 2021 and be completed within 6 months of that date which the Tribunal calculates to be 10th April 2022.
THE APPLICANT’S SUBMISSIONS
19. The Applicants submissions were contained in the application to the Tribunal dated 21st September 2021 and the further submission sent under cover of a letter to the Tribunal dated 18th October 2021. In this the Applicants submitted that it was important to note that the property had been going through improvement works prior to the serving of the Improvement Notice. It was also submitted that the Applicants had been co-operating with the Local Housing Authority and Fire Service to ensure the safety of the tenants but it was unfortunate that some of the remaining issues had taken longer due to the Covid-19 pandemic and the availability of materials and tradesmen to carry them out. However, the majority of the works which had been requested through the Improvement Notice the Applicants were in the process of carrying out. The Applicants stated that they were in the process of carrying out the majority of the works which had been requested through the Improvement Notice.
20. However, the Applicants submitted that the Improvement Notice had been served on the basis of noise which supposedly travelled from the walkway above this flat into the flat itself. It was claimed by the Respondent that the noise transmission was a Category 2 hazard yet they had provided no evidence to support this claim They were however requesting that the walkway was rebuilt and suspended off the flat roof to reduce noise transmission.
21. The Applicants further submitted that the walkway in question was a direct walkway which served three single person flats above the subject property. In the submission of the Applicants the walkway was not a public thoroughfare but was located at the rear of the property so that pedestrians (third parties) would not accidentally walk on it. The use of the walkway was very limited being used for access to the three single person flats and whatever noise might be transmitted would be infrequent throughout the day. Furthermore, the Applicants submitted that the flats are in a linear/series arrangement so the first flat is accessed first with the second and third being slightly further on and in total there was approximately 10 metres of walkway which could be walked upon.
22. It was further submitted by the Applicants that a noise hazard is defined as “Threats to physical and mental [NAME] due to exposure to noise within the property or within its curtilage”. In the submission of the Applicants the Respondent had provided no evidence to confirm the hazard which it was submitted, would need to be at a substantial level over a substantial period of time to cause such an impact. The Applicants had seen no surveys carried out by the Respondent over an acceptable level of time to ascertain the frequency of noise nor the duration of the noise when it does occur.
23. In addition, the Applicants submitted that the suggested improvement work was not practical as in attempting to suspend the walkway, not only would that be compromising the structure of the walkway but would also change the height at which the residents in the first-floor properties would be reaching their front doors. This could potentially cause a trip hazard. In addition to this, altering the height of the walkway would potentially cause an issue with the fire corridor which has been created so that tenants could use the walkway in the event of fire. It was submitted that the current walkway was 1.1 metres below the windows to comply with fire regulations and if the height was changed in order to raise the
5
walkway that would represent a far greater hazard than any minor infrequent transfer of noise.
24. It was also submitted by the Applicants that one of the other items of improvement work requested was to make the walkway less slippery and deal with small undulations in the walkway which may cause a trip hazard. The Applicants were proposing to lay a nonslip matting along the walkway which would not only make the walkway less slippery but also reduce any noise transmission as the matting would absorb a good proportion of the noise that may be transmitted from anyone using the walkway itself.
25. The Applicants therefore submitted that the Improvement Notice should be revoked together with the demand for recovery of expenses.
THE RESPONDENT’S SUBMISSIONS
26. The Respondent forwarded its written submission to the Tribunal dated 8th November 2021. The submission included a statement of the reasons for opposing the appeal and various items of correspondence between the parties.
27. The Respondent detailed the various letters and emails between the parties and submitted that it had reviewed the Applicants grounds for appealing the Improvement Notice and although it accepted that extensive remedial works had already been carried out on site these for the most part related to the remedial works required as prescribed within the letter served in October 2020 and the [NAME] served by the Leicestershire Fire Authority. However, in the opinion of the Respondent the fact that extensive remedial works had been carried out did not override a [NAME]’ power to address the continued presence of Category 2 hazards within the premises.
28. The Respondent submitted that the Applicants and the Applicant’s agent were first alerted to the hazards identified in the premises and of a Local Authority’s powers of [NAME] to address such hazards in the Respondent’s letters of 26th October 2020. The Respondent’s revisit to the premises under Notice of Entry was carried out on 16th August 2021 and the subsequent Improvement Notice served on 3rd September 2021. The Applicants made no contact with the Respondent to discuss the hazards within the property. The Respondent submitted that it repeatedly requested updates from the Applicants regarding the remedial works required and despite being given assurances that such works were either being looked at or had started on site, when it attended the premises under Notice of Entry in August 2021, hazards were still present and the Applicants were unable to provide definite timescales for addressing the outstanding remedial works.
29. The Respondent further submitted that the pre-formal and formal action taken in respect of the premises accorded with Charnwood Borough Council’s [NAME] and that the noise hazard was assessed using the Housing and Safety Rating System Operating Guidance. A hazard scoring calculation and assessment of the relevant matters was supplied to the Tribunal and, in the submission of the Respondent, evidenced the presence of the Category 2 hazard prior to service of the Improvement Notice.
30. The Respondent submitted that on 16th August 2021 Mr [RESPONDENT] (a qualified [NAME] [NAME]) had stood in the bedsit area of the premises along with the occupier and a colleague, [NAME], who was a [NAME] [NAME] [NAME]
6
Officer also employed by Charnwood Borough Council. At that time one of the officers by the [NAME] (the leaseholders) was asked to walk along the decking serving the first-floor flats. [COUNSEL] [NAME] (a representative of the Applicants) was present at the time and stood outside by the open front door. It was noted by the Respondent, that the noise generated by the [NAME] walking along the decking permeated into the premises under the roof deck. It was submitted that the noise was intrusive at the time of the property inspection (10:00am) whilst there was normal background noise from traffic etc. It was submitted that this background noise would dissipate at night, when noise nuisances become more objectionable.
31. The Respondent further submitted that the decking on the flat roof of the premises served as the only means of access to the three first floor flats within the site. As such it was extremely likely that it would be used multiple times on a daily basis by the occupiers of the flats and any visitors. The decking was over parts of the ceilings in the bathroom and bedsit area of the property and therefore noise transmission was likely to affect the occupier on a daily basis.
32. The Respondent submitted that the occupier of the property had complained to Charnwood Borough Council about the noise generated from people walking on the decking on three separate occasions and, in the opinion of the Respondent, the Applicants suggestion of laying a nonslip matting may not satisfactorily address the noise hazard as the decking rests directly on the flat roof of the property. In addition, it was submitted that had the freeholders or the Applicants been minded to carry out the works they had had plenty of opportunity to do so, yet had not even sought quotations for this at the time of the property inspection on 16th August 2021.
33. It was further submitted by the Respondent that the Applicants claims that the Improvement Notice required them to rebuild the decking was incorrect and that remedial works to rectify the noise hazard could be carried out from underneath the decking by removing the ceiling of the property below (61b), investigating the levels of noise insulation under the flat roof and upgrading as necessary. This had already been explained to the Applicant in an email on 20th September 2021 and following this option would be sensible as Improvement Notices had also been served on the Applicants on 3rd September 2021 in respect of flat [ADDRESS] (which have also been appealed) requiring in part an investigation of the fire resistance of the flat roof over 61b and any upgrade works required as necessary to provide sufficient fire resistance. Therefore, both items of work could be carried out simultaneously.
34. In conclusion the Respondent therefore submitted that the appeal should be refused.
THE TRIBUNAL’S FINDINGS
35. The Tribunal noted at its inspection that rubber matting had been fitted to the treads to the metal staircase adjacent to the rear bathroom wall of the property and to the walkway leading to the first-floor units. The walkway passed over the bathroom and sleeping area within the property. At the same time the parties informed the Tribunal that additional insulation had been fitted within the flat roof void over the subject property.
36. The Tribunal arranged to walk over the walkway and observed no undue noise in the property itself.
7
DETERMINATION
37. As described by the Respondent, the Tribunal accepts that the Hazard of Noise is a Category 2 Hazard.
38. The Tribunal accepts that the Respondent sent a letter to the Applicant dated 26th October 2020 detailing the works required to the property.
39. The Tribunal accepts that the Respondent sent various letters/emails to the Applicants between October 2020 and 3rd September 2021, requiring the Applicants to confirm the position regarding the outstanding works during which time no satisfactory response was received.
40. The Tribunal accepts that a formal Improvement Notice was served by the Respondent on the Applicants dated 3rd September 2021.
41. The walkway was over the bathroom and sleeping area of the property. This has limited use and the rubber matting and additional insulation in the roof void will have improved the noise transmission. The Tribunal is however of the opinion that the rubber matting is likely to have a limited lifespan.
42. The Tribunal agrees with the Respondent that the service of an Improvement Notice is the appropriate course of action in this case especially as the work has been carried out.
43. The Tribunal determined that the Applicant could have made more effort to contact the Respondent to discuss the matter prior to the serving of the Improvement Notice.
44. Having considered and balanced the factors of the case the Tribunal determined that the Improvement Notice was a reasonable and proportionate response to the risks at the property. However, as the work has been completed to rectify the defect, the Improvement Notice should now be revoked.
45. As the Tribunal determined that the Improvement Notice was the appropriate action for the Respondent to take, it confirms that the fee of £210.30 is reasonable and allowable under section 49 of the Act and payable by the Applicant.
APPEAL
46. Any appeal against this Decision must be made to the Upper Tribunal ([NAME]). Prior to making such an appeal the party appealing must apply, in writing, to this Tribunal for permission to appeal within 28 days of the date of issue of this Decision, (or, if applicable, within 28 days of any decision on a review or application to set aside) identifying the decision to which the appeal relates, stating the grounds on which that party intends to rely in the appeal, and stating the result sought by the party making the application.
[NAME] First-Tier Tribunal Property Chamber (Residential Property)
📊 How courts decide similar cases
Among 11 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) Tribunal Varies Improvement Notice Due to Damp and Mould Growth
- First-tier Tribunal (Property Chamber) First-tier Tribunal Varies Improvement Notice on Residential Hazards
- First-tier Tribunal (Property Chamber) Tribunal Varies Improvement Notice Under Housing Act 2004
- First-tier Tribunal (Property Chamber) First-tier Tribunal Adjusts Improvement Notice for Tenant's Garden Safety H…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Partially Allows Appeal Against Improvement Notice
- First-tier Tribunal (Property Chamber) First-tier Tribunal Varies Improvement Notice for Residential Hazards
- First-tier Tribunal (Property Chamber) Improvement Notice Decision: Confirmed Some Issues, Reduced Others
- First-tier Tribunal (Property Chamber) Financial Penalty Reduced in Tenancy Case
- First-tier Tribunal (Property Chamber) First-tier Tribunal Varies Improvement Notice and Confirms Demand for Payme…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Confirms Improvement Notice Against Tenants
- First-tier Tribunal (Property Chamber) Improvement Notice Appeal Confirmed by First-tier Tribunal
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The local housing authority has the power to serve an Improvement Notice even for a Category 2 hazard.
- The local authority had repeatedly requested updates on remedial works but received no satisfactory response.
- The Improvement Notice was a reasonable and proportionate response to the risks at the property.
- The fee for taking enforcement action was reasonable and allowable.
❌ Tends to be rejected
- The applicants' argument that the noise hazard would need to be substantial over a long period was rejected.
- The applicants' claim that the suggested improvement work was not practical was rejected.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Tribunal confirmed the Improvement Notice but allowed its revocation because the work had been completed.
Who was involved?
The local housing authority served an Improvement Notice to the tenant.
How did the court decide, and why?
The court decided to uphold the Improvement Notice but allowed its revocation because the work had been completed.
Which laws or rules were applied?
The Housing Act 2004 sections 5 and 7 were applied.
What was the argument that mattered most?
The argument that mattered most was that the work to address the noise hazard had been completed.
Was the decision for or against the person who brought the case?
The decision was for the person who brought the case, allowing the revocation of the Improvement Notice.
What does this mean for someone in a similar situation?
Someone in a similar situation should ensure that all work required by an Improvement Notice is completed to avoid penalties.
What evidence or documents mattered?
Evidence of the completion of the work required by the Improvement Notice was crucial.
Can a decision like this be appealed?
Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
It is always recommended to seek advice from a qualified solicitor for cases involving Improvement Notices.
