Improvement Notice Quashed but Claimant Must Pay Costs
📌 In brief
The First-tier Tribunal quashed an Improvement Notice because all required works were completed. However, the claimant was ordered to pay the Council's costs.
⚖️ Legal holding
A local authority must take appropriate enforcement action if a Category 2 hazard exists.
📖 What the law says
A local housing authority has the power to take certain types of enforcement actions if they believe a Category 2 hazard exists on residential properties. These actions include serving an improvement notice, making a prohibition order, serving a hazard awareness notice, making a demolition order, or declaring slum clearance.
If a local housing authority determines that a Category 2 hazard exists on residential premises and there is no active management order, they can serve an improvement notice requiring the recipient to take specific remedial actions to address the hazard.
An improvement notice can include a provision for suspending its operation until a specific time or event occurs, such as when a person begins or ceases to occupy the premises, or upon a breach of an accepted undertaking by the person to whom the notice is served.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Improvement Notice was quashed as all required works were completed. The claimant must pay the Council's costs.
📜 Headnote Official document
The First-tier Tribunal quashed an Improvement Notice as all required works were completed. However, the claimant was ordered to pay the Council's costs.
📚 Full judgment Official document
OUTCOME: Allowed
1
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case Reference : MAN/00FC/HIN/2024/0600 Property : 21 [ADDRESS], [POSTCODE] Applicant : [redacted] : [RESPONDENT] and [RESPONDENT] Respondent : [redacted] : Appeal against an Improvement Notice- Housing Act 2004 Schedule 1, Paragraph 10(1) Tribunal Members : Tribunal Judge J. E. Oliver Tribunal Member [NAME] of Determination : 17th April 2025 Date of Decision : 18th April 2025
DECISION
© CROWN COPYRIGHT 2025
2
Decision
1. The Improvement Notice dated 18th September 2024 is quashed on the basis all the work required by the Notice has been completed. 2. [NAME] is to pay the invoice from the Council in the sum of £460 within 28 days of the receipt of this decision by the parties.
Background
3. This is an appeal by [NAME] and [NAME] [NAME] (“[NAME]”) in respect of an Improvement Notice served on 18th September 2024 (“the Notice”) for [ADDRESS], Grimsby (“[NAME]”) by North East Lincolnshire Council (“the Council”). 4. The Notice specified several Category 2 hazards as follows:
Damp and Mould The mastic sealant around the bath is damaged.
Excess Cold The doors are missing from the front living room and back dining room.
Domestic Hygiene, pests and refuse Several kitchen doors and fronts are missing and some doors need adjustment.
Collision and Entrapment The bathroom door glazing is non-safety glass.
Structural collapse and falling elements The door frames and skirting boards in the living room and dining room are badly damaged.
5. The Improvement Notice required the necessary works to be started by 14th October 2024 and to be completed within 30 days.
6. The Respondent also served upon the Applicant a demand for payment of costs in the sum of £460.
7. On 3rd October 2024, [NAME] filed an appeal against the Notice and the demand for costs.
8. On 27th January 2025 directions were issued providing for both parties to file their statements and documents in support and thereafter for the matter to be listed for a hearing.
9. The application was listed for an inspection and a hearing on 17th April 2025.
[NAME]/Inspection
10. The Tribunal inspected [NAME] in the presence of the tenant, Mrs [APPELLANT] from the Council and [APPELLANT].
3 11. [NAME] is a 2 bedroomed mid-terraced brick-built house. At the inspection Mrs [NAME] agreed all the work specified in the Notice had been completed. This was agreed both by [NAME] and [NAME] and noted by the Tribunal.
The Law
12. The Housing Act 2004 provides the framework for the assessment of the condition of residential properties and the remedies that can be used to enforce standards in respect of them.
13. The Housing Health and Safety Rating System (HHSRS) provides a rating system for hazards. The score will determine which category the hazard falls; a score over 1000 will be a Category 1 hazard and those below 1000 will be a Category 2 hazard.
14. Section 7(2) of the Act provides that if a Category 2 hazard exists then a local authority must take the appropriate enforcement action which can be an improvement notice, prohibition order, a hazard awareness notice, emergency remedial action, demolition order or declaring the area in which the premises are situate, a clearance area. The Act further provides that if only one course of action is appropriate, that course must be taken, or if there are two or more courses available, then the local authority must take the one deemed to be most suitable.
15. Section 12 of the Act provides that if the local authority is satisfied that a Category 2 hazard exists and it serves an improvement notice that is a course of action open to a local authority.
16. Section 12(2) requires the person upon whom the improvement notice is served to take remedial action in respect of any of the hazards that are specified.
17. Schedule 1, paragraph 14 (1) of the Act provides that a person upon whom an improvement notice has been served may appeal to the First-tier Tribunal within 21 days beginning with the day upon which the improvement notice was served. The grounds for the appeal are set out in paragraphs 11 and 12 of the Act. Paragraph 13 provides an appeal may be made against the decision by a local authority to vary or revoke an improvement notice.
18. Schedule 1, paragraph 15 provides for the First-tier tribunal to deal with any appeal by way of re-hearing, thus allowing it to consider [NAME] at the date of the hearing and consider matters of which the local authority may not have been aware at the date the notice was served. The Tribunal has the power to confirm, quash or vary the improvement notice.
Submissions/Hearing
19. In its written submissions to the Tribunal the Council set out the history of its dealings with [NAME].
20. Mrs [NAME] made a complaint to the Council regarding the lack of repairs at [NAME] in October 2022, following which an Informal Notice was issued to [NAME] requiring remedial work to be completed by 8th December 2022. The Informal Notice included additional work to that specified in the Notice.
4 21. On 3rd July 2023 a further inspection of [NAME] was carried out where further hazards were identified. An extension was given to 31st August 2023 for the works to be completed. A further inspection completed on 11th September 2023 found the works still outstanding. An e-mail from [NAME] dated 14th September 2023 requested a further extension of time.
22. On 19th September 2023 a second Informal Notice was issued. This required the necessary works to be commenced by 2nd October 2023 and completed by 13th November 2023.
23. On 13th September 2023 Mrs [NAME] contacted the Council to say there was water ingress into the front living room. The Council contacted [NAME] who requested another extension to the time limit which was agreed. On 1st October 2023 damp work included in the Informal Notice was completed. Other works contained within the Informal Notice remained incomplete and on 18th September 2024, after a further inspection, the Notice was issued.
24. On 29th October 2024 Mrs [NAME] confirmed all the necessary works had been completed.
25. At the hearing it was agreed by the parties all the works included within the Notice had been completed. The issue was the charge made by the Council of £460. 26. [NAME] from the Council confirmed this charge was a standard charge when issuing an Improvement Notice and was based upon an average taken of the time expended by the Council when issuing such notices. It represented the time from the issue of the Improvement Notice; no charge was made for the work prior to that point. 27. [NAME] stated the charge was unreasonable. The delay in the completion of the works was beyond his control but caused by the tenant not either being available for the workmen or not allowing them into [NAME]. The tenants of his properties will generally only allow access if the issue is urgent. He confirmed he has two regular workmen who look after his portfolio of properties, totalling approximately 60 in Grimsby. There are additional contractors for electrics. Here, all the works had ben completed prior to the issue of the Notice.
Determination
28. The Tribunal noted that at the time of the inspection, all works required by the Notice had been completed. It therefore determined the Notice dated the 18th September 2024 should be quashed.
29. The Tribunal considered the costs claimed of £460 and determined those are payable by [NAME]. It noted the Council had gone to considerable trouble to get repairs completed. Two Informal Notices had been issued with several time extensions given. Although some works were completed, others remained incomplete, leaving the Council little choice other than to issue the Notice. Whilst the Tribunal acknowledged there could be difficulties with access to [NAME], there was no evidence provided to support this contention. Indeed, in the e-mail dated 14th September 2023 when [NAME] asked for a further extension, no mention was made of the tenant causing the delay by not allowing the workmen access. It was noted the works were said to have been completed prior to the issue of the Notice, but this was not accepted. The Council had inspected [NAME] on 28th August and found the works identified in the Notice still outstanding. The
5 Notice was issued shortly thereafter on 18th September 2024. [NAME] had brought no evidence so show all the works were completed by 18th September 2024. 30. The sum of £460 is payable within 28 days of the receipt of this decision by the parties.
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Reduces Financial Penalty for Landlord Due to Financial…
- First-tier Tribunal (Property Chamber) Tenant Wins Right to Buy Property Built After 1990
- First-tier Tribunal (Property Chamber) First-tier Tribunal Reduces Penalty for Unlicensed Residential Property
- First-tier Tribunal (Property Chamber) First-tier Tribunal Quashes HMO License Penalty Due to Misleading Official …
- First-tier Tribunal (Property Chamber) Claimant Wins Appeal Against Financial Penalty Due to Defective Improvement…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Extends HMO Licence Duration to Five Years
- First-tier Tribunal (Property Chamber) First-tier Tribunal Varies Improvement Notices for Tenants' Safety
- First-tier Tribunal (Property Chamber) First-tier Tribunal Varies Improvement Notice for Property Hazards
- First-tier Tribunal (Property Chamber) Financial Penalty Reduced for HMO Licence Breaches
- First-tier Tribunal (Property Chamber) First-tier Tribunal Partially Allows Appeal Against Improvement Notice
- First-tier Tribunal (Property Chamber) Tribunal Quashes HMO Licence Penalty, Upholds Management Regulation Violati…
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The local authority must consider mitigating factors when imposing penalties.
- Tenants are entitled to live in properties free from Category 1 and 2 hazards.
- A landlord must ensure that necessary repair works are completed within a reasonable timeframe.
- A financial penalty cannot be imposed based on a defective improvement notice.
- Local housing authorities must take appropriate enforcement action for Category 1 hazards.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Improvement Notice was quashed because all required works were completed.
Who was involved?
The claimant and the Council were involved.
How did the court decide, and why?
The court decided to quash the Improvement Notice because all the required works were completed.
Which laws or rules were applied?
The Housing Act 2004 was applied.
What was the argument that mattered most?
The argument that mattered most was that all the required works were completed.
Was the decision for or against the person who brought the case?
The decision was for the person who brought the case.
What does this mean for someone in a similar situation?
Someone in a similar situation should ensure all required works are completed to avoid an Improvement Notice.
What evidence or documents mattered?
Evidence showing that all required works were completed mattered.
Can a decision like this be appealed?
Yes, decisions like this can be appealed to a higher court.
Is it worth getting a solicitor for a case like this?
It is always recommended to seek advice from a qualified solicitor for cases like this.
