AllowedCivil Resolution Tribunal (British Columbia) — Small Claims·

Contractor Must Deliver Services Within Reasonable Timeframe - Claimant Entitled to Refund

Case No.

📌 In brief

The Tribunal decided that a contractor must deliver contracted services within a reasonable timeframe. In this case, the contractor failed to deliver the promised website development services, leading to a refund for the claimant.

⚖️ Legal holding

A contractor is obligated to deliver contracted services within a reasonable timeframe.

Topics

contract breachrefund entitlement

Provisions

Civil Resolution Tribunal Act, s. 118Civil Resolution Tribunal Act, s. 42

📖 Technical summary

The claimant sought a refund for website development services that were not delivered as per the contract.

📚 Full judgment

The summary, holding and questions above are VadeLab’s own material. The official decision itself is published by the court, and we do not reproduce it on this page.

⚖️ View on the official court website ↗

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The contractor failed to deliver the website and marketing services within a reasonable timeframe, breaching an implied term of the contract.
  • The contractor's failure to deliver the contracted services constituted a fundamental breach of the agreement.
  • The applicant was entitled to a refund of the amount paid due to the fundamental breach of contract.
  • The applicant was entitled to pre-judgment interest on the refund amount from the date the refund was requested.
  • The applicant was entitled to reimbursement for the tribunal fees paid.

❌ Tends to be rejected

  • The contractor's explanation for not completing the website, claiming outstanding assets and approvals, was not credible.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The claimant is entitled to a refund of $2,475.60 for undelivered website development services.

What was the dispute about?

The dispute was about the claimant's request for a refund after the contractor failed to deliver the contracted website development services.

How did the court decide, and why?

The court decided in favour of the claimant because the contractor did not deliver the website development services within a reasonable timeframe as per the contract.

Which laws or rules were applied?

The Civil Resolution Tribunal Act sections 118 and 42 were applied.

What was the argument that mattered most?

The argument that mattered most was that the contractor failed to deliver the contracted services within a reasonable timeframe.

Was the decision for or against the person who brought the case?

The decision was for the claimant.

What does this mean for someone in a similar situation?

Someone in a similar situation may be entitled to a refund if the contractor fails to deliver the contracted services within a reasonable timeframe.

What evidence or documents mattered?

The evidence that mattered included the signed contract, text messages between the parties, and the lack of delivery of the contracted services.

Official source: Civil Resolution Tribunal (British Columbia) — Small Claims this page does not reproduce the decision; it links to the court's own publication. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the Civil Resolution Tribunal (British Columbia) — Small Claims (© Province of British Columbia). VadeLab reproduces no part of the decision text; the summary above is VadeLab's own material. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.