First-tier Tribunal Grants Dispensation for Urgent Sewage Pump Replacement
📌 In brief
The First-tier Tribunal allowed a landlord to bypass the usual consultation process for major works because the work was deemed urgent to address health and safety issues and reduce costs.
⚖️ Legal holding
A landlord may obtain dispensation from consultation requirements if it is reasonable to do so.
📖 What the law says
The First-tier Tribunal can grant permission to skip consultation requirements for certain works or long-term agreements if it finds it reasonable to do so.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal granted dispensation from consultation requirements for major works due to urgency.
📜 Headnote Official document
The First-tier Tribunal granted dispensation from consultation requirements for the replacement of a sewage pump, deeming it urgent due to health and safety concerns and financial implications.
📚 Full judgment Official document
OUTCOME: Allowed
© CROWN COPYRIGHT
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
Case Reference
:
HAV/43UJ/LDC/2025/0738
Property
:
The Acorns, Scarlett Oaks, Camberley, Surrey, [POSTCODE]
Applicant: [redacted]
:
[NAME]
Respondents
:
[redacted] 55, 56, 57 & 58)
Type of Application
: To dispense with the requirement to consult lessees about major works section 20ZA of the Landlord and Tenant Act 1985
Tribunal Member(s)
:
Tribunal Judge H Lumby
Date of Decision
:
20 January 2026
DECISION
2 Decision of the Tribunal The Tribunal grants the application for the dispensation of all or any of the consultation requirements provided for by section 20 of the Landlord and Tenant Act 1985 (Section 20ZA of the same Act) in relation to the replacement of the sewage pump at [NAME]. The background to the application 1. The Applicant seeks dispensation under Section 20ZA of the Landlord and Tenant Act 1985 from the consultation requirements imposed on the landlord by Section 20 of the 1985 Act. This application was received on 19 November 2025.
2. [NAME] is described as a purpose built block of ten flats, built in 2005.
3. The Applicant is the landlord of [NAME] and the Respondents comprise its leaseholders.
4. The application relates to the replacement of the sewage pump at [NAME]. The works are required because the existing pump has failed, causing sewage to back up into the flats. The existing sewage pit requires emptying by a tanker every few days at a cost of £1,000 per visit. The works had been instructed but not commenced at the time of the application.
5. The works were said to be urgent to prevent the sewage backing up into the flats, causing a health and safety issue. It will also avoid further emptying costs.
6. The Applicant’s agents have obtained three quotations for the works, all of whom have given a similar time estimate for completing the works. The Applicant has instructed the contractor with the lowest quotation, at £4,398.01.
7. The Applicant says that a notice of intention was issued to all leaseholders on 19 November 2025 and a notice of estimates will be provided to them. However, there is clearly insufficient time for a statutorily compliant consultation.
8. The Applicant has confirmed that no objections have been received from the Respondents.
9. By Directions of the Tribunal dated 17 December 2025 it was decided that the application be determined without a hearing, by way of a paper case. No objections have been received to this approach. I have reviewed the documentation provided and am satisfied that it remains suitable for a paper determination.
3 10. The Tribunal did not inspect [NAME] as it considered the documentation and information before it in the set of documents prepared by the Applicant enabled the Tribunal to proceed with this determination.
11. This has been a paper determination which has not been objected to by the parties. The documents that were referred to are the Applicant’s application, a specimen lease, a list of the Respondents and the Tribunal’s Directions dated 17 December 2025, the contents of which have been recorded.
The issues
12. This decision is confined to determination of the issue of dispensation from the consultation requirements in respect of the qualifying works. The Tribunal has made no determination on whether the costs are payable or reasonable. If a Lessee wishes to challenge the payability or reasonableness of those costs as service charges, including the possible application or effect of the Building Safety Act 2022, then a separate application under section 27A of the Landlord and Tenant Act 1985 would have to be made.
Law 13. Section 20 of the Landlord and Tenant Act 1985 (as amended) (“the 1985 Act”) and the Service Charges (Consultation Requirements) (England) Regulations 2003 require a landlord planning to undertake major works, where a leaseholder will be required to contribute over £250 towards those works, to consult the leaseholders in a specified form.
14. Should a landlord not comply with the correct consultation procedure, it is possible to obtain dispensation from compliance with these requirements by an application such as this one before the Tribunal. Essentially the Tribunal must be satisfied that it is reasonable to do so.
15. The Applicant seeks dispensation under section 20ZA of the 1985 Act from all the consultation requirements imposed on the landlord by section 20 of the 1985 Act.
16. Section 20ZA relates to consultation requirements and provides as follows:
“(1) Where an application is made to a leasehold valuation tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long term agreement, the tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.
(2) In section 20 and this section—
4 “qualifying works” means works on a building or any other premises, and “qualifying long term agreement” means (subject to subsection (3)) an agreement entered into, by or on behalf of the landlord or a superior landlord, for a term of more than twelve months. …. (4) In section 20 and this section “the consultation requirements” means requirements prescribed by regulations made by the Secretary of State. (5) Regulations under subsection (4) may in particular include provision requiring the landlord— (a) to provide details of proposed works or agreements to tenants or the recognised tenants’ association representing them, (b) to obtain estimates for proposed works or agreements, (c) to invite tenants or the recognised tenants’ association to propose the names of persons from whom the landlord should try to obtain other estimates, (d) to have regard to observations made by tenants or the recognised tenants’ association in relation to proposed works or agreements and estimates, and (e) to give reasons in prescribed circumstances for carrying out works or entering into agreements.
Findings 17. In the case of [COMPANY] v Benson [2013] UKSC 14, by a majority decision (3-2), the Supreme Court considered the dispensation provisions and set out guidelines as to how they should be applied.
18. The Supreme Court came to the following conclusions:
a. The correct legal test on an application to the Tribunal for dispensation is: “Would the flat owners suffer any relevant prejudice, and if so, what relevant prejudice, as a result of the landlord’s failure to comply with the requirements?”
b. The purpose of the consultation procedure is to ensure leaseholders are protected from paying for inappropriate works or paying more than would be appropriate.
c. In considering applications for dispensation the Tribunal should focus on whether the leaseholders were prejudiced in either respect by the landlord’s failure to comply. d. The Tribunal has the power to grant dispensation on appropriate terms and can impose conditions.
5 e. The factual burden of identifying some “relevant prejudice” is on the leaseholders. Once they have shown a credible case for prejudice, the Tribunal should look to the landlord to rebut it. f. The onus is on the leaseholders to establish: i. what steps they would have taken had the breach not happened and ii in what way their rights under (b) above have been prejudiced as a consequence
19. Accordingly, the Tribunal had to consider whether there was any “relevant prejudice” that may have arisen out of the conduct of the Applicant and whether it was reasonable for the Tribunal to grant dispensation following the guidance set out above.
Consideration 20. Having read the evidence and submissions from the Applicant and having considered all of the documents and grounds for making the application provided by the Applicant, the Tribunal determines the dispensation issues as follows.
21. It is evident that a statutorily compliant consultation has not been carried out by the Applicant, with the works instructed before a stage 2 consultation had begun. Applying Daejan, the test for it was whether the Respondents have suffered any relevant prejudice, and if so, what relevant prejudice, as a result of that lack of consultation by the landlord. In doing so, it needed to focus on whether the leaseholders have been prejudiced by paying for inappropriate works or paying an inappropriate amount as a result of the lack of consultation.
22. The Applicant believes that the replacement of the sewage pump at [NAME] needed to be completed urgently for health and safety as financial reasons; it in particular refers to the backing up of sewage into flats and the costs of emptying the sewage pit every few days. On the evidence before it, the Tribunal agrees with the Applicant’s conclusions.
23. The Tribunal is of the view that, taking into account that there have been no objections to this application from the Respondents, it could not find prejudice to any of the leaseholders by the granting of dispensation relating to the replacement of the sewage pump at [NAME].
24. As a result, the Tribunal believes that it is reasonable to allow dispensation in relation to the subject matter of the application.
25. Accordingly, the Tribunal grants the Applicant’s application for the dispensation of all or any of the consultation requirements provided for
6 by section 20 of the Landlord and Tenant Act 1985 in relation to the replacement of the sewage pump at [NAME].
26. The Applicant shall place a copy of the Tribunal’s decision on dispensation together with an explanation of the leaseholders’ appeal rights on its website (if any) within 7 days of receipt and shall maintain it there for at least 3 months, with a sufficiently prominent link to both on its home page. It should also be posted in a prominent position in the communal areas. In this way, any Respondents who have not returned the reply form may view the Tribunal’s eventual decision on dispensation and their appeal rights.
Rights of appeal 1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application by email to [EMAIL]
2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.
3. If the person wishing to appeal does not comply with the 28 day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.
4. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Emergency Lift Works Dispensation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Safety Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Lift Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roofing Repairs
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Lift Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Drainage Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) Tribunal Grants Landlord Dispensation from Consultation Requirements
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Leak Repairs
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The existing sewage pump had failed, causing sewage to back up into the flats, which created a health and safety issue.
- The works were urgent to prevent further sewage backup and avoid additional emptying costs.
- The landlord obtained three quotations for the works and instructed the contractor with the lowest bid.
- No objections to the application for dispensation were received from the leaseholders.
- There was insufficient time for a statutorily compliant consultation process to be completed.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The decision allowed the landlord to bypass the usual consultation process for major works.
Who was involved?
The landlord and leaseholders were involved.
How did the court decide, and why?
The court decided that it was reasonable to grant dispensation due to the urgency of the work.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 sections 20 and 20ZA were applied.
What was the argument that mattered most?
The argument that mattered most was the urgency of the work and the potential health and safety risks.
Was the decision for or against the person who brought the case?
The decision was for the landlord.
What does this mean for someone in a similar situation?
Someone in a similar situation may also be able to bypass the consultation process if the work is deemed urgent.
What evidence or documents mattered?
The evidence included the urgency of the work, the health and safety risks, and the financial implications.
Can a decision like this be appealed?
Yes, decisions like this can be appealed to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
It is always recommended to get advice from a qualified solicitor for a case like this.
