VadeLab
AllowedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Grants Emergency Repair Exemption

Case No.

📌 In brief

The First-tier Tribunal granted an exemption from statutory consultation requirements for a landlord who needed to perform urgent repairs to prevent water damage to electrical equipment. The decision was made by Judge Sarah McKeown on November 27, 2023.

⚖️ Legal holding

A landlord may be exempted from statutory consultation requirements if it is reasonable to do so.

Topics

statutory consultation requirementsrepair worksemergency repairs

Provisions

Landlord and Tenant Act 1985 s.20ZA

📖 What the law says

Landlord and Tenant Act 1985 s.20ZA

Under this section, a landlord can apply to the appropriate tribunal for permission to bypass consultation requirements related to certain works or long-term agreements if it is reasonable to do so.

Plain-English explanation — does not replace advice from a solicitor.

📖 Technical summary

The Tribunal granted the application for retrospective dispensation from statutory consultation requirements under the Landlord and Tenant Act 1985.

📜 Headnote Official document

The Tribunal granted an application for retrospective dispensation from statutory consultation requirements under the Landlord and Tenant Act 1985, allowing the landlord to bypass consultation for urgent repairs to prevent water ingress into an electrical intake cupboard. Judge Sarah McKeown presided over the case on 27 November 2023.

📚 Full judgment Official document

OUTCOME: Allowed

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case reference : LON/00AY/LDC/2023/0201 HMCTS code : P: PAPERREMOTE Property : 1-22 [ADDRESS], [POSTCODE] Applicant : [redacted] Borough of Lambeth Representative : [COUNSEL]: HOS/LIT/PBYFIELD/608409 Respondents : [redacted] : Not represented Type of application : To dispense with the statutory consultation requirements under section 20ZA Landlord and Tenant Act 1985 Tribunal member :

Judge Sarah McKeown

Date of decision : 27 November 2023

DECISION

This has been a remote hearing on the papers which has been consented to by the Applicant and has not been objected to by any Respondent. The form of remote hearing was P:PAPERREMOTE. A face-to-face hearing was not held because no-one requested a hearing and all issues could be determined on paper. The documents to which the Tribunal was referred are in an electronic bundle of 78 pages, the contents of which the Tribunal has noted. The decision made is as set out below.

DECISION The Tribunal grants the application for retrospective dispensation from statutory consultation in respect of the subject works, namely to repair a leak to the mains pipework, to prevent water ingress into the electrical intake cupboard. The Applicant should place a copy of this decision together with an explanation of the leaseholder’s appeal rights on its website (if any) within seven days of receipt and maintain it there for at least three months, with a sufficiently prominent link to both on its home page. It should also display copies in a prominent place in the common parts of the Property. This decision does not affect the Tribunal’s jurisdiction upon any future application to make a determination under section 27A of the Act in respect of the reasonableness and/or cost of the work. The Application References are to page numbers in the bundle provided for the hearing.

1. The Applicant seeks (p.1) a determination pursuant to section 20ZA of the Landlord and tenant Act 1985 (“the Act”) for retrospective dispensation from consultation in respect of the works set out above. The Service Charges (Consultation Requirements) Regulations 2003 provide that consultation requirements are triggered if the landlord plans to carry out qualifying works which would result in the contribution of any tenant being more than £250. The cost of the works which are the subject of the application exceed this threshold.

2. The application was made without notice to the Respondents as the application was said to be urgent because of the immediate risk of electrical outage to the block or electrical fire. It was also said that there was the possibility of a total loss of mains water supply to the block.

3. By directions (p.62) dated 31 August 2023 (‘the directions”) the Tribunal directed that the applicant had to send to each of the [NAME]

(and any residential sublessees and any [NAME]), by 22 September 2023, by email, hand delivery or first-class post:

(a) Copies of the application form unless already sent by the applicant to the leaseholder/sublessee; (b) If not already detailed in the application form, a brief statement to explain the reasons for the application; and (c) The directions.

4. The Applicant also had to display a copy of the directions in a prominent place in the common parts of the property. The Applicant had to confirm compliance by 2 October 2023. They in fact confirmed compliance on 11 September 2023 (p.77).

5. The directions provided that [NAME] and sublessees who oppose the application had to, by 20 October 2023, complete the reply form and sent to the Applicant and the Tribunal and sent to the Applicant a statement in response with copies of any documents they wished to rely upon. There was also provision for a response from the Applicant. The Applicant also had to prepare a bundle which was to contain, among other things, a statement from the Applicant/landlord to explain the reasons for the applicant.

6. The Tribunal has received no completed form from any leaseholder or sublessee.

7. The directions provided that the tribunal would decide the matter on the basis of written submissions unless any party requested a hearing. No such request has been made.

The Applicant’s case

8. The applicant is the freeholder (p.43) of the property, which is a purpose-built mixed terrace block of twenty-two 1-3 bedrooms flats, of which 14 are leasehold.

9. The specimen lease, which is for Flat 1, states that the freeholder covenants (cl. 3.2.2-3.2.3 – p.51) to repair, redecorate, renew, amend, clean, repoint and paint, among other things, the “sewers drains channels watercourses gas and water pipes electric cable and wires and supply lines in under and upon the Building” and “the boilers and heating and hot water apparatus (if any) in the Building or elsewhere…”.

10. In its application, which is dated 11 July 2023, and which was sent to the Tribunal on 12 July 2023, the Applicant explained that on 2 July 2023, the Applicant was notified of a leak on the lead mains pipework, located in one of the property’s electrical intake cupboards. On the same day, a Work Order

was raised for the Applicant’s qualifying long-term contractor ([APPELLANT[COMPANY]) to attend and investigate the reported burst main and to install a temporary mains water supply as an emergency temporary repair. On 6 July 2023, the contractor quoted £5,076 for temporary works (which are detailed in the Applicant’s Submissions (p.11) and in the document at p.21). A Justification Report (p.24) dated 11 July 2023 was produced as the Applicant was unable to provide the full consultation period given the urgency. Due to the location of the leak causing water ingress into the electrical intake cupboard, there was an immediate risk of electrical outage to the block of electrical fire. It was also said that there was the risk of pipeline rupture, which could have resulted in a total loss of mains water supply to the block. The temporary supply was installed over-ground but the temporary solution was not safe to be left in situ on a long-term basis due to the risk of rupture and flooding of communal areas if tampered with, potentially risking further outage and inconvenience to residents. It was also said that it was not good practice for a temporary supply to be left open to the elements. For those reasons, it was said that a permanent relay of pipework needed to be installed without delay. The contractor quoted £13,444.97 for the permanent works (detailed in the Applicant’s Submissions and in the document at p.35).

11. The estimated cost for the temporary works was estimated to be £5,076.00 and the estimated cost for the permanent works was £13,444.97. The temporary works were done on 6 July 2023 and the permanent works were done on 11 July 2023.

12. The application states that the Applicant wrote to the [NAME] on 10 July 2023 (p.38) explaining why the works were required, what their estimated contribution was expected to be, and that the Applicant would be applying to the Tribunal for retrospective dispensation. The Applicant invited written observations in relation to the proposed works by 24 July 2023. It also provided a FAQ sheet.

The Respondent’s case

13. No respondent objected to the application. [NAME] (12a) did email the Applicant on 19 July 2023 asking for some further information (p.69) and this information was provided on 25 July 2023 (p.70). The [NAME] of a further property (3) emailed the Applicant on 28 July 2023 (p.74) asking why the repairs were not covered by the insurance. The Applicant responded to that email on 2 August 2023 (p.75).

Determination and Reasons

14. Section 20ZA(1) of the Act provides: “Where an application is made to a leasehold valuation tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long term agreement, the tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.”

15. The whole purpose of section 20ZA is to permit a landlord to dispense with the consultation requirements of section 20 of the Act if the tribunal is satisfied that it is reasonable for them to be dispensed with. Such an application may be made retrospectively, as it has been made here.

16. The Tribunal has taken account of the decision in [COMPANY] v [NAME] and Others [2013] UKSC 14 in reaching its decision.

17. There is no evidence before the Tribunal that the Respondents were prejudiced by the failure of the Applicant to comply with the consultation requirements. The Tribunal is therefore satisfied that it is reasonable to dispense with all or any of the consultation requirements in relation to the subject works, namely to repair a leak to the mains pipework, to prevent water ingress into the electrical intake cupboard.

18. Whether the works have been carried out to a reasonable standard and at a reasonable cost are not matters which fall within the jurisdiction of the Tribunal in relation to this present application. This decision does not affect the Tribunal’s jurisdiction upon any future application to make a determination under section 27A of the Act in respect of the reasonableness and/or costs of the works.

Judge Sarah McKeown 27 November 2023

Rights of appeal If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber), then a written application for permission must be made to the First-tier Tribunal at the regional office which has been dealing with the case. The application for permission to appeal must arrive at the regional office within 28 days after the tribunal sends written reasons for the decision to the person making the application. If the application is not made within the 28-day time limit, such application must include a request for an extension of time and the reason for not complying with the 28-day time limit; the tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed, despite not being within the time limit. The application for permission to appeal must identify the decision of the tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal and state the result the party making the application is seeking. If the tribunal refuses to grant permission to appeal, a further application for permission may be made to the Upper Tribunal (Lands Chamber).

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The landlord is granted permission to bypass consultation if it is deemed reasonable.
  • Works are considered urgent and there is no evidence of harm to tenants.
  • Retrospective applications for exemption from consultation requirements are allowed if reasonable.

❌ Tends to be rejected

  • (No factors identified that went against the claimant in the provided cases.)

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

It decided to grant the landlord's application for exemption from statutory consultation requirements for urgent repairs.

Who was involved?

The landlord and various leaseholders were involved.

How did the court decide, and why?

The court decided that it was reasonable to grant the exemption due to the urgency of the repairs and the potential risks to the building.

Which laws or rules were applied?

The Landlord and Tenant Act 1985, specifically section 20ZA, was applied.

What was the argument that mattered most?

The argument that mattered most was the immediate risk of electrical outage and fire due to water ingress into the electrical intake cupboard.

Was the decision for or against the person who brought the case?

The decision was for the person who brought the case.

What does this mean for someone in a similar situation?

Someone in a similar situation may be able to obtain an exemption from consultation requirements if they can demonstrate the urgency and necessity of the repairs.

What evidence or documents mattered?

Evidence of the immediate risk to the building and the necessity of the repairs were crucial.

Can a decision like this be appealed?

Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).

Is it worth getting a solicitor for a case like this?

Yes, it is always recommended to seek advice from a qualified solicitor for cases involving statutory consultation requirements.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.