VadeLab
AllowedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Reduces Service Charges for Major Roof Works

Case No.

📌 In brief

The First-tier Tribunal reduced the service charges for major roof works because the landlord failed to follow its own policies and managed the costs poorly. The decision reflects the importance of landlords adhering to their responsibilities and controlling costs effectively.

⚖️ Legal holding

A landlord must adhere to its own policies regarding regular inspections and timely execution of major works to avoid excessive costs.

Topics

tenancy disputesservice charges

Provisions

Landlord and Tenant Act 1985 s.20Landlord and Tenant Act 1985 s.20C

📖 Technical summary

The Tribunal reduced the service charges for major roof works due to the landlord's breach of contract and failure to control costs.

📜 Headnote Official document

The Tribunal reduced the service charges for major roof works due to the landlord's breach of contract and failure to control costs. The landlord was found to have breached its own policies and failed to manage costs effectively, leading to higher charges than necessary.

📚 Full judgment Official document

OUTCOME: Allowed

1

Case Reference : CHI/29UG/LSC/2022/0120

Property : [ADDRESS], [POSTCODE]

Applicants : [redacted]

[NAME] ([NAME] 16)

[RESPONDENT] ([NAME] 71)

[RESPONDENT] ([NAME] 52)

Respondent : [redacted]

Representative : Ms [COUNSEL] (Counsel, instructed

by Medway Council & Gravesham

Council Legal Services)

Type of Application : Section 27A, LTA’85

Tribunal Members : Judge Dovar

Mr [NAME] and venue of : 14th April 2023 Hearing

Havant Justice Centre

Date of Decision : 24th May 2023

_______________________________________________

DECISION ____________________________________

© CROWN COPYRIGHT

FIRST - TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

2 1. This an application for the determination of the payability of service charge in respect of major works to a number of the roofs to the Property.

2. The Property is in an [NAME] of 9 building plots comprising 7 blocks of flats and two terraces of houses. The [NAME] was built around 1960 and the blocks of flats are divided as to: Block 1-12, 13-21, 22-33, 43-57, 34- 42, 58-69 and 70-81. The houses are: 82-88 and 89-95.

3. The works were carried out in 2020 and the cost for each long [NAME] is between £10,000 and £12,500. Mr [NAME], as a [NAME] of a [NAME] within block 43-57 has received an invoice for £10,965.87 as his contribution towards the re-roofing programme to renew the main roof of his block. Miss [NAME], the lessee of a [NAME] in Block 70-81 received an invoice for £11,588.02. Mrs [NAME] a [NAME] in block 13-21 has an invoice for £10,552.36 and Mr [NAME] a [NAME] in block 43-57 has received an invoice for £10,965.87. It is those invoices for those three blocks which are challenged in this application.

4. The Applicants have raised the following challenges to those costs: a. Breach of Contract, in that the Respondent has failed to adhere to its own policies which direct it to carry out regular inspections and only to carry out re roofing works when a roof it at the end of its lifespan;

3 b. Failure to control the costs of the works, in that the Respondent did not have proper reports carried out and failed to carry out any necessary work earlier, with the result that the costs have risen from around £6,000 per [NAME] to around £11,000; c. There was disparity in treatment and cost between the [NAME] owners and the house owners, with the latter paying much less for more roof work. Lease Terms 5. The Tribunal was provided with a lease of [NAME] 46, which is taken as representative of the leases on the [NAME]. Clause 7 (1) of the lease contains the Respondent’s obligation to ‘maintain repair redecorate renew and clean … (a) the structure of the building and in particular … the roofs …’. There is a linked obligation on the [NAME] to pay a share of the cost of those works.

6. It is therefore clear and not in dispute, that the obligation to maintain and keep in repair the roofs falls on the Respondent and the Applicants each have a liability to contribute to the cost of the same. The Gravesham Borough Council DSO Building Management Repairs & Maintenance Policy (‘the Policy’)

7. In addition to the terms of their leases, the applicants relied on the above policy. The Policy is dated September 2020, but was created in April 2017 and has been updated in September 2020.

4 8. It sets out the objectives of the Respondent with regard to the management or repairs to its housing stock. It states that ‘This policy is based on our legal obligations as a landlord…’ that is said to be drawn from both from legislation and the terms of the leases and the Respondent says it has considered governmental guidance in the area. It also confirms that it has responsibility for keeping the roof of properties in good repair.

9. The Applicants relied specifically on paragraph 25, dealing with Planned Works Programmes and Maintenance which sets out the following “The council undertake programs of improvements to our properties to ensure that they meet the expectations of our residents and will look to renew certain aspects and component parts of our properties that have or are reaching the end of their useful life. Please see table below for expected life cycles: … [NAME] lifecycle 20 years … Estimates are based on a minimum lifecycle and no replacements will be considered until the component reaches its minimum expected life cycle. Near to the end of the expected life cycle, the council will contact the tenant to arrange an inspection of the component at which point the [NAME] will decide whether a replacement is needed at that point in time. If a component does not need replacing, the [NAME] will estimate a revised life expectancy and the council’s systems will be updated. No replacements will be made if there is sufficient

5 life left in the component or if the life expectancy can be extended by way of a minor repair.” Various works to the roofs over the years 10. The parties had attempted to piece together the history of roof repairs over the years. This had been mostly prompted by Mr [RESPONDENT] attempts to get the Respondent to provide evidence of what work had been done. From that the following picture emerges.

11. Having been built in around 1960, the first documentary evidence of work to the roof after that is in the early 1990s. There is a 20 year guarantee for roof works to blocks 1-12 and 70-81 dated 24th February 1994 and earlier documentation dated 24th September 1993 referring to an order for the renewal of roof covering to those blocks.

12. There is a variation instruction from Gravesham Borough Council dated 15th June 1994 referred to a quotation dated 6th June 1994 for £25,250 for roof renewal to blocks 22-33 and 58-69, a certificate of practical completion dated 3rd January 1995 and a 20 year guarantee for the works to those blocks.

13. Similar documentation has been provided for block 34-42 in around 1996 with a certificate of practical completion dated 12th August 1996 and a 20 year guarantee.

14. The certificate of service charge for the year ending 31st March 1996, dated 2nd September 1996 for [ADDRESS] (which is in block 43-

6 57) which has a line for Roof Renewal total costs £14,828.10 of which £999.90 was charged to the block and then 1/15th to the [NAME].

15. It therefore certainly seems that between 1994 and 1996, blocks 1-12, 22-33, 34-42, 43-57, 58-69, and 70-81 had roof works and most likely full replacements. There is nothing then until 2017. Reports 16. On 30th August 2017, [NAME] produced a roof survey report of 43-57, 58-69 and 70-81. Although in fact, they had only surveyed 70-81, as they said they could not access the other roofs. The report does not provide their credentials, but they appear to be the maker of a proprietary roof covering, Bauderflex Roof system.

17. From the inspection they considered: a. The decking was in good condition; b. The waterproofing system was in a reasonable condition, with some isolated defects and that ‘some remedial works are required to maintain integrity and on-going serviceability. It is worth investing in this work now before the current defects have the opportunity to deteriorate further.’ c. The drainage was adequate.

18. Under proposals they stated “The existing decking is to be re-used. The condition of the existing waterproofing is considered suitable for receiving an overlay system.” Although the body of the report did not

7 say as much, it appeared that they were recommending their system be used to overlay what was already in situ.

19. On 16th November 2020, [NAME] provided another roof survey report, this time in relation to block 13-21. As with the previous report, it was noted that the decking was in good condition ‘to be reused as part of the roof refurbishment’, the existing waterproofing system ‘appears to be in reasonable condition, but with some isolated defects’ with some ‘remedial works … required to maintain integrity and on-going serviceability. It is worth investing in this work now before the current defects have the opportunity to deteriorate further.’ Unlike the previous report it was stated that ‘The thermal performance of the existing roof build-up is poor and falls below the above standards’. This latter comment arose in this report and not the former, because of changes to building regulations.

20. As a result the following recommendations were made: a. The existing decking was to be reused; b. The existing waterproofing was to have an overlay system; and c. The insulation was to be upgraded with new drainage chutes. Consultation 21. On 29th January 2019, the Respondent gave notice of intention to enter into a qualifying long term agreement (under s.20 of the Landlord and Tenant Act 1985), being the signing up to a [NAME] for the joint procurement, with other local authorities, of major works. Following

8 that process the Respondent entered into the long term agreement for the provision of major works.

22. Between 22nd September 2020 and 12th March 2021, the Respondent wrote to the [NAME] providing them with a notice of intention under s.20 of the Landlord and Tenant act 1985 to carry out specific works in accordance with that long term agreement. The letter to Mrs [COUNSEL] of no16, which is representative of the letters that were sent out, stated “…The works to be carried out … Re-roofing programme to re- new the main roof. … We consider it necessary to carry out the works programmed and as stated in your lease agreement to maintain the structure of the building, as the main roof is beyond its life span of 20 years and there is no longer a guarantee. We have now obtained estimates in respect of the works to be carried out, which are as follows: [COMPANY] £80,316.02 of which your proportion approximately will be £8,924.00 for block 13-[ADDRESS]. As a [NAME] your contribution will be based on a proportion of the cost which will amount to approximately £11,601.20 …”

9 23. In response to queries by Mr [NAME] as to the basis upon which the works were said to be needed, [RESPONDENT] of the Respondent emailed him on 1st July 2022, stating that “Based on report finding from block 70-81, with the knowledge that the bocks were constructed at the same time, and that the [NAME] roof was previously replaced at the same time and with the same specification, it was considered reasonable that all roofs would be in a similar condition.

24. The Tribunal was also shown some correspondence with one of the house owners, in which her contribution to the roof works for the terrace in which her property sits, was £2,170.

25. On 2nd February 2022, the Respondent sent out the invoices for each [NAME]’s contribution to the cost of the roof works to their block. As stated above, it is those invoices which are challenged in this application.

26. At the hearing the Respondent asserted that in fact in 2017 all the blocks had been physically surveyed and that in 2020 two blocks had been surveyed again in order to take core samples. This was a surprising assertion given that there had been no mention of these surveys in the Respondent’s evidence to date, neither in their disclosure, nor in the two witness statements that had been provided. They had also failed to provide copies to the Applicants or the Tribunal. The content of the surveys appears to have been the same as with the one that was provided.

10 Costs reasonably incurred? 27. Before considering the Applicants’ challenges, the first question the Tribunal will address is whether, but for those challenges, the costs are recoverable through the service charge; particularly whether they fall within costs that are recoverable under the lease and if so, whether notwithstanding that, they should be capped in line with s.19 of the Landlord and Tenant Act 1985 on the basis that they either have not been reasonably incurred or the work is not to a reasonable standard. The latter is not in contention, no challenge has been made to the quality of the works.

28. Ostensibly they are recoverable under the terms of the lease. As set out above, the obligation to keep the roofs in repair falls on the Respondent and they are entitled to recover the costs of the same from the Applicants, as [NAME]. The Tribunal did not accept the Applicant’s contention that the obligations under the leases had been varied by the Policy. Instead, as counsel for the Respondent submitted, it was an indication as to how the Respondent would approach its obligations. It did not, in the Tribunal’s view, prevent them from re-roofing, unless there was evidence that only that approach would suffice. Further the fact that the Respondent may have failed to follow the Policy in terms of the timing of inspections and the work undertaken, was not relevant for the purposes of establishing whether sums were recoverable under the service charge. Any relevance would arise under a challenge based on a breach of contract having caused some loss to the [NAME] which could be offset against their liability for service charges.

11 29. The first query the Tribunal had was whether there was sufficient evidence of disrepair and if so, whether that warranted the works that were carried out (ignoring at this stage whether or not the disrepair was wholly or partly the fault of the Respondent). The 2017 and 2020 reports did highlight both disrepair and the latter, the need for upgraded insulation to comply with building regulations. On scrutiny of the actual works carried out, it was to a.) upgrade the insulation and b.) apply a further covering over the roof in situ. The decking remained the same and the original roof covering was left in place.

30. In the Tribunal’s view this was warranted on the evidence as: a. The sample roofs had shown signs of wear and deterioration in 2017 and that situation was only likely to have got worse since then; b. It appears that there had been no works to the roofs since around the mid 1990s and so they were all out of guarantee and past their life expectancy; c. Although the Tribunal did not have the full set of reports, it was likely that they were all in a similar condition; d. Given the works took place in 2020, the need for upgrading insulation was justified by the change in building regulations.

31. No alternative quotes had been provided and the consultation process through s.20 meant that there already had been some control over pricing.

12 32.

Accordingly, subject to the challenges brought by the Applicants, the sums claimed were ostensibly payable. Breach of Contract 33. The first challenge by the Applicants was based on breach of contract. They focused their challenge under this heading on the Policy document and the reflection of the landlord’s obligations under their leases to maintain the roof. They complained that the Respondent had not adhered to their policy of inspecting the [NAME] roofs every 20 years as set out in the Policy. They also queried, whether in respect of block 43-57 there had ever been a replacement roof. From the evidence provided to the Tribunal, set out above, it was satisfied that there had been re- roofing works for blocks 43-57 and 70-81 between 1994 and 1996. The Applicants argued that the evidence was not sufficient to draw that conclusion, however, although there was not much in the way of documentation, from what there was, it was a reasonable inference to draw that it had been re-roofed.

34. That covered three of the four applicants; however there was no evidence in respect of any works having been carried out to block 13-21. That block was the subject of the roof survey report in 2020.

35. Given those that had been replaced in around 1994-1996, and the 20 year expected life span, they should have been reinspected around 2014- 2016. The only report the Tribunal were provided with around that date was the [NAME] report in August 2017 in respect of block 70-81. As set out above, that recommended at least some patch replacement works to

13 maintain the effectiveness of the roof and prevent the situation getting worse. Those works were not carried out. As Ms [RESPONDENT] for the Respondent conceded this put the Respondent in breach of their repairing covenant in the leases.

36. The Respondent had intended to carry out works then and had sent out letters indicating the cost would have been around £6,000. There was some dispute as to whether invoices for that amount had been sent or merely letters indicating that that was the likely cost. However, it was agreed that the figure of £6,000 per [NAME] had been put forward in respect of the cost of the roof work, which had now risen to over £10,000.

37. The Respondents initially contended that although they accepted they were in breach of covenant by reason of the disrepair, the [NAME] had not suffered because of that. Further that there was no time line set for when they would have to carry out those repairs. It was asserted by their counsel that the timeline was what was reasonable in the circumstances. The reason why the works were not carried out in 2017, was because the Respondent wanted to tie them up with cyclical repairs that were on the horizon for painting and windows and so the works were put off until then.

38. However, in the meantime, the costs had increased because not only had the cost of materials and labour increased, but the change in building regulations meant that the insulation needed to be upgraded. The

14 Respondent argued that this increase could not have been foreseen and so should not be counted against them.

39. The Tribunal does not agree with that approach to the rising cost. More simply put, the Respondent was in breach of covenant at least by 2017. Had it carried out the work then, it would have cost around £6,000. It did not do so. Had it complied with its obligations then, the [NAME] would have paid less.

Accordingly, by reason of the continued breach, the cost of the works has risen.

40. The Tribunal therefore sets-off against the sums claimed by the Respondent, against each Applicant the sum of £3,000 to take into account the following: a. The difference between the estimated amount in 2017 and the actual amount in 2020 (i.e. around £4,000 less); b. The fact that the estimated amount was only an estimate and might have been increased by unforeseen costs at the time (which justifies some reduction of the £4,000); c. The [NAME] have had the benefit of not paying for the works and so keeping the money (or not having to borrow the money) for 4 years (which justifies a marginal reduction of the £4,000); d. The inclusion of insulation, which although being a benefit to the [NAME], would not have been necessary from a regulatory perspective and from the comments by the [NAME] was not actually necessary in these blocks as there are no issues with insulation (the issue is therefore neutral). Lack of Control over Costs 41. The Applicants clarified at the hearing that in essence this head of challenge was the same as the previous one in that had the works been carried out in 2017, they would not have cost as much. Parity 42. The final challenge relates to the fact that the [NAME] paid less for the works than the [NAME] [NAME].

43. The Tribunal accepts the Respondent’s defence to the claim of unequal treatment with the house owners, in that the obligations vis a vis repairs and maintenance are, by the lease/contractual terms, different between the [NAME] and the house owners. Conclusion 44.

Accordingly, the Tribunal determines that each of the invoices levied by the Respondent on each Applicant is payable save that the amount payable is reduced by £3,000 to account for the breach of covenant by the Respondent. Mr [RESPONDENT] and Mr [RESPONDENT] are therefore liable to pay £7,965.87, Miss [NAME], £8,588.02 and Mrs [NAME], £7,552.36.

45. The Tribunal also makes an order under s.20C of the 1985 Act preventing the Respondent from recovering the cost of these proceedings from the Applicants through the service charge. Not only have the

16 Applicants been partially successful in their challenge and achieved a reduction in the sum payable, but the Tribunal also took into account the lack of information provided by the Respondent in respect of these works, in particular, the failure to provide all the reports and the failure to set out the fact that the 2017 works were stalled due to other cyclical works. JUDGE DOVAR

17 Appeals

A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application by email to [EMAIL] .

The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.

If the person wishing to appeal does not comply with the 28-day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28- day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.

The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The landlord was in breach of its repairing covenant by not carrying out recommended patch replacement works in 2017.
  • The inclusion of insulation, while a benefit, was not necessary from a regulatory perspective for these blocks.

❌ Tends to be rejected

  • The landlord's argument that the tenants had not suffered from the breach of covenant was rejected.
  • The landlord's argument that the increase in costs due to changes in building regulations could not have been foreseen was rejected.
  • The argument that there was unequal treatment and cost between flat owners and house owners was rejected because their lease obligations were different.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The Tribunal reduced the service charges for major roof works due to the landlord's breach of contract and failure to control costs.

Who was involved?

The tenants and the landlord were involved in the dispute over service charges.

How did the court decide, and why?

The court decided that the service charges should be reduced because the landlord failed to adhere to its own policies and managed the costs poorly.

Which laws or rules were applied?

The Landlord and Tenant Act 1985 sections 20 and 20C were applied.

What was the argument that mattered most?

The argument that mattered most was that the landlord failed to adhere to its own policies regarding regular inspections and timely execution of major works.

Was the decision for or against the person who brought the case?

The decision was for the tenants who brought the case.

What does this mean for someone in a similar situation?

Someone in a similar situation should ensure that their landlord adheres to the terms of the lease and manages costs effectively.

What evidence or documents mattered?

The evidence included the landlord's policies, previous roof works records, and cost estimates.

Can a decision like this be appealed?

Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).

Is it worth getting a solicitor for a case like this?

Yes, it is always recommended to seek advice from a qualified solicitor for such cases.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.