VadeLab
DismissedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Rejects Pitch Fee Increase for Mobile Home Park

Case No.

📌 In brief

The First-tier Tribunal decided against increasing the pitch fee for a mobile home park, stating that the proposed changes did not constitute sufficient improvements to justify the increase.

⚖️ Legal holding

A pitch fee increase over and above the Retail Price Index (RPI) percentage is only justified if there are actual improvements to the park that benefit the residents.

Topics

tenancy disputespitch fee increasesMobile Homes Act 1983

Provisions

Mobile Homes Act 1983, Schedule 1, Part 1, Chapter 2, Para 16Mobile Homes Act 1983, Schedule 1, Part 1, Chapter 2, Para 18Mobile Homes Act 1983, Schedule 1, Part 1, Chapter 2, Para 20

📖 Technical summary

The Tribunal ruled that the pitch fee increase was not justified due to insufficient improvements to the mobile home park.

📜 Headnote Official document

The First-tier Tribunal determined that the proposed pitch fee increase for a mobile home park was not justified due to insufficient improvements and lack of proper consultation with residents.

📚 Full judgment Official document

OUTCOME: Dismissed

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case Reference : MAN/00DB/PHI/2019/0004 Property : OAKLAND HILL ESTATE, FRYSTON LANE FERRYBRIDGE [POSTCODE]

Applicant : [redacted] Respondents : [redacted]

Type of Application : APPLICATION FOR DETERMINATION OF NEW PITCH FEE: Mobile Homes Act 1983, Schedule 1, Part 1, Chapter 2, Para 16

Tribunal Members : [NAME], [NAME] of Determination : 3 March 2020 Date of Decision : 22 April 2020

DECISION

© CROWN COPYRIGHT 2020

The pitch fee payable by the Respondents for the year commencing 1 April 2019 is the pitch fee for the previous year increased by a percentage equivalent to RPI for the relevant period (2.5%).

REASONS

BACKGROUND 1. On 20 February 2019 the Applicant sent to each of the Respondents at [ADDRESS] (“the Park”) a Pitch Fee Review Notice advising that the pitch fee payable for the year beginning 1 April 2019 would be the pitch fee for the previous year plus a percentage increase of 2.5% (RPI) and an additional charge (“the additional pitch fee increase”) of £4.32 per month.

2. The Respondents agreed to the RPI percentage increase but did not agree to the additional pitch fee increase.

3. On 17 June 2019 the Applicant sought a determination from the Tribunal as to the pitch fee payable.

THE LAW 4. Chapter 2 of Schedule 1 to the Mobile Homes Act 1983 (as amended) (“the Implied Terms”) sets out the terms implied into every contract between the owner and occupier of a pitch on a protected site such as [ADDRESS]

5. Paragraph 16 of the Implied Terms provides that

“the pitch fee can only be changed…………….., either –

(a) with the agreement of the occupier, or (b) if [the Tribunal] ....... considers it reasonable for the pitch fee to be changed and makes an order determining the amount of the new pitch fee.”

6. Paragraph 18 provides

“(1) When determining the amount of the new pitch fee particular

regard shall be had to – (a) any sums expended by the owner since the last review date on

improvements (i) which are for the benefit of the occupiers of mobile homes on the protected site; (ii) which were the subject of consultation in accordance with paragraph 22(e) and (f) below; and (iii) to which a majority of the occupiers have not disagreed in writing or which, in the case of such disagreement, the [Tribunal], on the application of the owner, has ordered should be taken into account when determining the amount of the new pitch fee; …….;

7. Paragraph 20 of the Implied Terms provides “(1) There is a presumption that the pitch fee shall increase or decrease by a percentage which is no more than any percentage increase or decrease in the retail prices index since the last review date, unless this would be unreasonable having regard to paragraph 18 (1) above.” 8. Paragraph 22 (e) and (f) read: 22 The owner shall… (e) consult the occupier about improvements to the protected site in general and in particular about those which the owner whishes to be taken into account when determining the amount of any new pitch fee; (f) consult a [COMPANY], if there is one, about all matters which relate to the operation and management of, or improvements to, the protected site and may affect the occupiers either directly or indirectly.

9. Paragraphs 24 and 25 define “consult” as 24 (a) to give the occupier at least 28 clear days’ notice in writing of the proposed improvements which – (i) describes the proposed improvements and how they will benefit the occupier in the long and short term; (ii) details how the pitch fee may be affected when it is next reviewed; and (iii) states when and where the occupier can make representations about the proposed improvements; and

(b) to take into account any representations made by the occupier

about the proposed improvements in accordance with

paragraph (a)(iii), before undertaking them. 25 (a) to give the association at least 28 clear days’ notice in writing of

the matters referred to in paragraph 22 (f) which (i) describes the matters and how they may affect the occupiers either directly or indirectly in the long and short term; and (ii) states when and where the association can make representations about the matters, and

(b) to take into account any representations made by the association, in accordance with paragraph (a)(iii), before proceeding with the matters.

10. It was common ground between the parties that the majority of the residents at the Park were members of a [COMPANY].

INSPECTION 11. The Tribunal inspected [ADDRESS] on 3 March 2020, accompanied by [NAME] [APPELLANT] who own the [COMPANY], and Mrs [APPELLANT] representing the Respondents.

12. The Tribunal were shown the fenced area under which is sited the sewage [NAME] (“the [NAME]”) that serves the Park, and other areas of the Park. [ADDRESS] is well maintained but residents’ enjoyment of the site is affected by smells emanating from the [NAME].

HEARING 13. At a hearing in Leeds after the inspection, Mrs [COUNSEL] appeared for the Applicant and the Respondents were represented by Mr [APPELLANT], a resident at the Park.

14. Each party supplied a number of documents, including some 38 individual statements from residents of the Park. Most of the documents and almost all of the witness statements dealt with the unfortunate hostility between the Respondents and [NAME], and were irrelevant to the issue before the Tribunal, ie whether repairs and improvements to the [NAME] and sewerage system justified the additional pitch fee increase.

15. At the hearing Mr [NAME], a resident on the Park, gave evidence as to how the sewerage system worked, and the history of maintenance and replacement of its parts.

16. The Tribunal established at the hearing that there were at that time 68 Respondents out of a total of 90 residents at the Park, of which 84 were members of the Qualifying Residents Association. Of the Respondents, 40 had originally contracted with the Park owner to pay a pitch fee which did not include the cost of the sewerage service, and 28 had agreements which indicated that their pitch fee included the cost of sewerage.

THE APPLICANT’S CASE 17. Mrs [APPELLANT] sought to justify the additional pitch fee increase by reference to three new pumps that the Applicant had had installed in the [NAME] tanks in February 2019. The cost of the three pumps was £4,368. To this figure the Applicant had added £298 representing the cost of materials for additional work to the sewerage system which had been carried out by Mr [NAME]. The total expenditure of £4,666 had been divided equally between the 90 residents (£4.32 per month per resident) and it was proposed that these payments be added to the pitch fees, with a view to recovery of the cost of the work over a period of 12 months.

18. As to whether the new pumps and other work constituted an improvement to the Park, Mrs [NAME] said that the new pumps were “more robust maybe”. Two pumps had failed and had been replaced during the year ending 31 March 2018. In February 2020 three pumps, including one or more of those installed in February 2019, had had to be replaced again at a cost of £3,188 plus VAT.

19. It was accepted by the Respondents that the reason for repeated failures of the pumps is the disposal of inappropriate material into the sewerage system. Over a period of years during which this problem has persisted, it has not proved possible to ensure that only permitted material enters the system. Mrs [NAME] took the view that in these circumstances the Park residents as a whole must take responsibility and bear the repeated repair costs.

20. Mrs [NAME] told the Tribunal that she had obtained costings for joining the Park to mains sewerage, which would transfer responsibility for maintaining the system to Yorkshire Water. However a majority of the residents had opposed the plan.

THE RESPONDENTS’ CASE 21. Mr [NAME] for the Respondents told the Tribunal that since 2004 the Park owners had borne the cost of repairs to the [NAME], and that there was no reason why the residents should now be expected to pay. He said that it had not been possible to identify those people who were misusing the sewerage system, but that it was unfair to expect those residents who only dispose of permitted material to pay costs caused by those who flout the rules.

22. Mr [NAME] also claimed that there had been no effective consultation with the residents and the [COMPANY] prior to the pumps being replaced in February 2019. The Applicant had sent a letter dated 28 January 2019 to each resident which complied with paragraph 24(a)(i) and (ii) of the Implied Terms but, he said, the third page (which in the copy provided to the Tribunal by the Applicant explained to the residents how they could make representations to the Applicant) was missing. In any event, the work was carried out before expiry of the 28 day consultation period provided for by paragraphs 24(a) and 25(a) of the Implied Terms.

23. On this point Mrs [NAME] said that the work had had to be carried out within the consultation period because the pumps had failed, the sewerage system was not working, and the Applicant was in breach of its licence until the repair was effected. She denied that the third page was missing from the letter dated 28 January 2019 when it was served on the Respondents.

24. Finally, Mr [NAME] told the Tribunal that the tanks were emptied 3 or 4 times a year prior to 2017, but that the Applicant was now having them emptied less often. The Respondents considered that this was causing the tanks to

overflow, and damaging the pumps.

25. In response to this last point, Mrs [APPELLANT] said that the Applicant managed the [NAME] and emptied the tanks as advised by their engineer Mr [NAME] and approved by the Environment Agency.

FINDINGS 26. The Tribunal finds that 26.1 no consultation with the Respondents took place as required by the Implied Terms, as the work was carried out as an emergency within the 28 day consultation period; 26.2 although in the circumstances the Tribunal might have overlooked the lack of consultation, the replacement of the pumps in February 2019 was a repair and not an improvement to the [NAME], as evidenced by the fact that the pumps had failed again within 12-13 months, and for the same reasons; 26.3 the cost of repairs to the sewerage system was included in the pitch fees of 28 residents. Those residents were not identified by the parties in these proceedings. 26.4 although paragraph 18(1) of the Implied Terms allows for an increase in pitch fee over and above the RPI percentage for reasons other than park improvements in exceptional cases, no such exceptional circumstances were relied upon by the Applicant or identified by the Tribunal; 26.5 in any event the additional pitch fee increase would have enabled the Applicant to recover the whole cost of the works within a year, whereas a pitch fee increase to reflect an improvement to a park would normally be spread over the expected life of the improvement; 26.6 the Applicant has a potential remedy for its difficulties with the [NAME]: namely an application to the Tribunal for an order under paragraph 18(a)(iii) that the cost of connection to mains drainage could be taken into account when determining a pitch fee.

27. In the circumstances the increase in the Respondents’ pitch fee for the period 1 April 2019 to 31 March 2020 is to be limited to the agreed 2.5% RPI related uplift.

📊 How courts decide similar cases

Among 10 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The pitch fee increase was limited to the RPI percentage because the additional charge was not justified by actual improvements.
  • The work on the sewage system was considered a repair, not an improvement, as the pumps failed again within a year for the same reasons.
  • No proper consultation with residents took place because the work was carried out as an emergency within the 28-day consultation period.
  • The proposed additional fee would have recovered the full cost of the works within a year, which is not typical for improvements.
  • The applicant did not rely on any exceptional circumstances to justify an increase above RPI for reasons other than park improvements.

❌ Tends to be rejected

  • The applicant's argument that residents should bear repeated repair costs due to misuse of the sewerage system was not accepted.
  • The applicant's claim that the new pumps were "more robust maybe" did not convince the Tribunal they constituted an improvement.
  • The applicant's argument that the work had to be carried out within the consultation period due to pump failure was not accepted as a justification for lack of consultation.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The decision rejected the proposed increase in the pitch fee for a mobile home park.

Who was involved?

The decision involved the owner of a mobile home park and the residents of the park.

How did the court decide, and why?

The court decided that the proposed increase was not justified because the improvements were not substantial and there was no proper consultation with the residents.

Which laws or rules were applied?

The Mobile Homes Act 1983, specifically Schedule 1, Part 1, Chapter 2, was applied.

What was the argument that mattered most?

The argument that mattered most was that the proposed changes did not constitute significant improvements to the park.

Was the decision for or against the person who brought the case?

The decision was against the person who brought the case, the owner of the mobile home park.

What does this mean for someone in a similar situation?

For someone in a similar situation, it means that any proposed increase in the pitch fee must be justified by significant improvements and proper consultation with residents.

What evidence or documents mattered?

Evidence and documents showing the nature of the proposed improvements and the consultation process with residents mattered.

Can a decision like this be appealed?

Yes, decisions like this can be appealed to a higher court.

Is it worth getting a solicitor for a case like this?

It is always recommended to seek advice from a qualified solicitor for such cases.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.