First-tier Tribunal Rules on Maintenance Responsibility for Communal Heating Systems
📌 In brief
In a recent case, the First-tier Tribunal ruled that the Heat Interface Units (HIUs) used in a communal heating system are the responsibility of the landlord. This means the landlord can charge the a person for the costs of maintaining these units.
⚖️ Legal holding
Under the Landlord and Tenant Act 1985, the head lessee is responsible for maintaining the communal heating system, including the Heat Interface Units.
📖 Technical summary
The tribunal ruled that the head lessee is responsible for maintaining the communal heating system, including the Heat Interface Units in individual flats.
📜 Headnote Official document
The tribunal determined that the Heat Interface Units (HIUs) are part of the communal heating system and thus fall under the landlord's maintenance obligations, allowing the landlord to charge leaseholders for the costs of repairs.
📚 Full judgment Official document
OUTCOME: Allowed
1
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case Reference : LON/OOBE/LSC/2022/0048
Property : [ADDRESS] [POSTCODE] Applicant: [redacted]
[NAME](1) [NAME](2)
Representative : Devonshires
Respondent : [redacted] : Type of Application : Determination of payability pursuant to s 27A Landlord and Tenant Act 1985 Tribunal Members :
Judge Jim Shepherd Louise Crane MCIEH
Date of Determination : 27th June 2022
Determination
1. In this case the Applicants [NAME] and [COMPANY] (“The Applicants”) seek a determination by the Tribunal as to where responsibility lies for the replacement of component parts of a heating
2
system. For the reasons given here the Tribunal has decided that responsibility lies with the Applicants themselves and that they are entitled to recover the cost from their [NAME]. Background.
2. The case concerns premises at [ADDRESS], [POSTCODE] (“The premises”). The premises consist of 26 flats and 1 house. The Freeholder of the premises is [NAME] and the [COMPANY]. Both organisations are part of the same group of companies but are separate legal entities. The [NAME] at the premises are shared ownership lessees originally granted by Presentation Housing Association who merged with [COMPANY].
3. There is a communal heating system at the premises providing heating and hot water to the flats. The flats each contain a Heat Interface Unit (HIU) which exchanges hot water. The HIUs are an integral part of the communal heating system and if one breaks down the whole of the system malfunctions.
4. There have been intermittent faults with the heating and hot water systems. Works carried out by the Applicants in 2020 identified an erosion in the heating and hot water pipework. An independent consultant identified various means of addressing the issue most of which required the replacement of the HIUs. In August 2021 one of the central boilers failed and a temporary boiler had to be installed. This is still in situ and the need for a new heating system is now urgent.
5. The Applicants require clarity as to the lease interpretation before embarking on the major work of replacing the heating system including replacing the HIUs which are in the individual flats. Pausing here it is important to stress that this is not an application for dispensation pursuant to s.20ZA of the Landlord and Tenant Act 1985. The Applicants will need to consult the [NAME] under s.20 of the same Act unless such dispensation is granted.
3
6. [NAME] have in their response to the application raised the issue of the reasonableness of the cost of the forthcoming works in light of their argument that there has been neglect by the Applicants in the past in dealing with the heating and hot water system. Whilst the Tribunal has sympathy with this argument it is not relevant to the issue at hand which solely concerns the interpretation of lease terms in order to determine who is the liable part to pay for the works.
7. The [NAME] retain all of their rights to challenge the reasonableness of the charges that may be sought from them by way of s.27A Landlord and Tenant Act 1985.
The lease clauses
8. Under their leases the [NAME] covenant to keep the interior of their flats in good and substantial repair. Expressly under clause 3(3) the interior includes “all radiators and water and sanitary apparatus and gas and electrical apparatus of the premises and all pipes drains and wires”.
9. The landlord’s convenant (here being the immediate responsibility of the head lessee) requires them to “maintain, repair…and renew the pipes , sewers, drains, wires cisterns and tanks and other gas electrical drainage ventilation and water apparatus and machinery in under and upon the building (except such as serve exclusively an individual flat in the Landlord’s estate )( clause 5(3) (b)).
10. The landlord is able to recover service charges to meet the cost of meeting this responsibility (clause 7).
4
11. These lease clauses are mirrored in the lease between the Head Lessee and the Freeholder -i.e. the Applicants.
Determination
12. It is tolerably clear that the HIUs do not exclusively serve the flats because they form part of the wider communal heating system. This is the practical and sensible interpretation of the lease terms. If it were not so the individual [NAME] would need to maintain the HIUs in their flats. If they failed to do this the whole of the heating and hot water system would malfunction. Further it is possible to interpret the head lessee’s repairing obligation such that it includes the HIUs which are part of the heating and hot water machinery which they must maintain.
13. The consequence of this interpretation is that the the Applicants are responsible for replacing he HIUs and can recharge the cost of the work from the [NAME]. This is the determination of the Tribunal. It must be again stressed however that this is not a decision as to the reasonableness of any forthcoming costs that the [NAME] will be asked to bear and they are able to challenge this if they wish in the future.
Judge Shepherd 27th June 2022
ANNEX - RIGHTS OF APPEAL Appealing against the tribunal’s decisions
1. A written application for permission must be made to the First-tier Tribunal at the Regional tribunal office which has been dealing with the case.
2. The application for permission to appeal must arrive at the Regional tribunal office within 28 days after the date this decision is sent to the parties.
3. If the application is not made within the 28-day time limit, such application must include a request for an extension of time and the reason for not complying with the 28- day time limit; the Tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed despite not being within the time limit.
5
4. The application for permission to appeal must state the grounds of appeal, and state the result the party making the application is seeking. All applications for permission to appeal will be considered on the papers 5. Any application to stay the effect of the decision must be made at the same time as the application for permission to appeal.
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Approves Lease Variation for Reserve Fund
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Windows Are Retained Land
- First-tier Tribunal (Property Chamber) Tribunal allows service charges to be payable to landlord's agent in Ely, C…
- First-tier Tribunal (Property Chamber) Tenant Ordered to Pay Service Charges Under Lease Terms
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges for Asbestos Removal Reasonable a…
- First-tier Tribunal (Property Chamber) Tenants Win Rent Repayment Order for Unlicensed HMO Tenancy
- First-tier Tribunal (Property Chamber) Rent Repayment Order Awarded Due to Unlicensed HMO and Harassment
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Drainage Works
- First-tier Tribunal (Property Chamber) Tenant Entitled to Recover Costs Incurred in Lease Extension Claim
- First-tier Tribunal (Property Chamber) Tribunal Rules on Service Charge Liability for Tenant
- First-tier Tribunal (Property Chamber) Tenant Ordered to Pay Reasonable Costs for New Lease
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- Service charges are considered payable if they cover reasonable costs under the terms of the lease.
- The landlord is responsible for maintaining communal heating systems, including HIUs, and can charge leaseholders for these costs.
- Costs related to urgent works that do not prejudice leaseholders are recoverable through service charges.
- Tenants are liable for reasonable costs associated with lease modifications and extensions.
- Tenants can be charged for the costs of obtaining a new lease under specific legislation.
❌ Tends to be rejected
- (No factors listed against the claimant based on the provided cases.)
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The decision determined that the Heat Interface Units (HIUs) are part of the communal heating system and thus fall under the landlord's maintenance obligations.
Who was involved?
The case involved the landlord and the leaseholders of a property with a communal heating system.
How did the court decide, and why?
The court decided that the HIUs are part of the communal heating system because they are integral to its operation and cannot be maintained solely by the leaseholders.
Which laws or rules were applied?
The court applied sections 27A and 20 of the Landlord and Tenant Act 1985.
What was the argument that mattered most?
The argument that mattered most was that the HIUs are part of the communal heating system and thus fall under the landlord's maintenance obligations.
Was the decision for or against the person who brought the case?
The decision was in favour of the landlord.
What does this mean for someone in a similar situation?
For someone in a similar situation, it means that the landlord is responsible for maintaining the communal heating system and can charge leaseholders for the costs.
What evidence or documents mattered?
The evidence included the lease terms and the practical necessity of maintaining the communal heating system.
Can a decision like this be appealed?
Yes, decisions from the First-tier Tribunal can be appealed to a higher court within 28 days.
Is it worth getting a solicitor for a case like this?
It is always recommended to seek advice from a qualified solicitor for cases involving lease terms and responsibilities.