Landlord Granted Urgent Roof Repairs Dispensation Without Consultation
📌 In brief
The First-tier Tribunal allowed a landlord to bypass the usual consultation process for urgent roof repairs. The repairs were deemed necessary to prevent further damage to the building.
⚖️ Legal holding
A landlord may be dispensed from consultation requirements if the works are urgent and necessary to prevent damage.
📖 What the law says
The First-tier Tribunal can grant a request to waive consultation requirements for certain works if it determines that waiving these requirements is reasonable.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal granted dispensation from consultation requirements for urgent roof repairs.
📜 Headnote Official document
The First-tier Tribunal granted a landlord dispensation from consultation requirements under s.20ZA of the Landlord and Tenant Act 1. The works were urgent remedial works to the roof, including the removal of defective slate coverings and repair to defective brickwork and parapet walls. The Tribunal found that the works were urgent and necessary to prevent damage to the property.
📚 Full judgment Official document
OUTCOME: Allowed
© CROWN COPYRIGHT
PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case reference : LON/00AW/LDC/2025/0860 Property :
Flats 1 to [ADDRESS], [APPELLANT], London [POSTCODE] Applicant: [redacted]
[COUNSEL] [NAME] Respondent: [redacted]
The long leaseholders of the flat 1 to [ADDRESS] listed in the schedule to the [NAME] : - Type of [NAME] : To dispense with the statutory consultation requirements under section 20ZA Landlord and Tenant Act 1985 (the ‘Act’) Tribunal members :
Judge Pittaway Date of decision :
25 October 2025
DECISION
2
DECISION Description of hearing This has been a remote hearing on the papers which has been consented to by the Applicant and not objected to by any Respondent. The form of remote hearing was P:PAPERREMOTE. A face-to-face hearing was not held because no-one requested a hearing and all issues could be determined on paper. The documents to which the Tribunal was referred are in a bundle of 156 pages which included the [NAME] dated 1 November 2024, a lease of one of the flats and the leaseholders’ contact details. The Tribunal has had regard to the above documents and its directions of 29 November 2025 in reaching its decision set out below.
DECISION The Tribunal grants the [NAME] for retrospective dispensation in respect of the subject works (‘the works’), namely urgent remedial works to the roof at the Property, including the removal of defective slate coverings, replacement of underlay and battens, renewal of lead flashings and repair to defective brickwork and parapet walls. This decision does not affect the Tribunal’s jurisdiction upon any future [NAME] to make a determination under section 27A of the Act in respect of liability to pay, for a reason other than non- consultation in respect of the subject works, and the reasonableness and/or the cost of the subject works. The [NAME]
1. The Applicant seeks a determination pursuant to section 20ZA of the Landlord and Tenant Act 1985 (the ‘Act’) for retrospective dispensation from consultation in respect of the works to the Property.
2. The Applicant seeks dispensation from the consultation requirements on the ground that the works were urgent because of ongoing leaks and potential damage to the Property.
3. The [NAME] states that the contractor [COMPANY] was identified as the preferred contractor following a review of competitive quotations. The [NAME] costed the works at £19,146.96 plus professional fees and VAT.
3 4. The [NAME] stated that the Applicant have not provided any consultation notices, as required under Section 20 of the Landlord and Tenant Act 1985, due to the urgency of the works.
5. By directions dated 10 October 2025 (the ‘directions’) the Tribunal directed that the Applicant by 17 October 2025 to send each [NAME], any residential sublessees and any [COMPANY] the [NAME], a brief statement to explain the reason for the [NAME] (if not contained in the [NAME]) and the directions and display a copy in a prominent place in the common parts of the property, and to confirm to the Tribunal by 20 October 2025 that this had been done. On 20 October 2025 the Applicant confirmed that the [NAME] had been posted by first class post and e mailed to all the leaseholders on 17 October 2025 and that the documents had been displayed in a prominent place in the common parts of the Property.
6. The directions provided that if any [NAME]/sublessee objected to the [NAME] he/she should do so, to the Applicant and the Tribunal, by 31 October 2025. The Tribunal received no objections and on 3 November 2025 the Applicant stated that it had received none.
7. The directions provided that the Tribunal would decide the matter on the basis of written representations unless any party requested a hearing. No such request has been made.
The Applicant’s case
8. The bundle contains a statement of case by the Applicant’s solicitors [APPELLANT].
9. The Property is described as comprising ten long leasehold residential flats, including flats 1-8 and basement stores. The ground floor houses 8 commercial units. The Property is a five-storey block (excluding the lower ground floor) with a distinctive roofscape featuring Dutch gables and turret detailing.
10. [NAME], Chartered Surveyors, inspected the Property on 7 March 2025. They identified that multiple small or temporary repair jobs had been completed in the past but which were no longer effective. It was not possible to identify one cause of the water ingress. They advised that the only way to ensure full repair and guarantee was to remove and reinstate the mansard felt, batten, tiles, leadwork and render.
11. The only quote in the bundle before the Tribunal is that of [COMPANY] but e mails in the bundle indicate that other quotes were obtained.
4
12. On 17 February 2025 [APPELLANT], the Applicant’s managing agents, served a letter on the Respondents notifying them of the Applicant’s intention to apply to the Tribunal for dispensation from the consultation requirements under s20ZA, explaining that urgent works were necessary, due to ineffective earlier works and to stop the water ingress affecting Flats 5 and 7. A further (undated) letter explained that the state of the roof was worse than initially assessed, with water ingress affecting habitable areas and parts of the roof structure, not visible during prior works. This stated that the contractor was to be instructed without delay and gave the leaseholders the opportunity of [NAME] comments before the [NAME] was made to the Tribunal.
13. No objections or representations were received from the Respondents in response to notification of the proposed [NAME] to the Tribunal.
14. The Applicant submitted that the scope and need for the works, and the urgency, had been independently verified by the surveyors, that the contract had been placed after obtaining multiple quotes for the works and that the Respondents had been kept informed and given an opportunity to respond meant that the Respondents had suffered no prejudice from the Applicant being unable to satisfy the statutory consultation requirements. The Respondents remain able to challenge the reasonableness and payability of the cost of the works.
Responses from the Respondents
15. The Tribunal received no responses from any Respondent and the Applicant stated that it had received none.
Determination and Reasons
16. Section 20ZA(1) of the Act provides: “Where an [NAME] is made to a leasehold valuation tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long term agreement, the tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.”
17. The purpose of section 20ZA is to permit dispensation with the consultation requirements of section 20 of the Act if the Tribunal is satisfied that it is reasonable for them to be dispensed with.
18. The Tribunal determines that the Respondents are not prejudiced by the works and it is reasonable to dispense with the consultation requirements.
5 19. In reaching its decision the Tribunal has considered the decision in [COMPANY] v [NAME] and others [2013] UKSC 14. It has had regard to the [NAME] and the documents provided, in particular the stated need for the works to be undertaken urgently.
20. Whether or not the Respondents are liable for the cost of the works by reason of the terms of their leases, any statutory provision other than section 20ZA, and whether the works are carried out to a reasonable standard and at a reasonable cost are not matters which fall within the jurisdiction of the Tribunal in relation to this present [NAME]. This decision does not affect the Tribunal’s jurisdiction upon any future [NAME] to make a determination under section 27A of the Act in respect of liability to pay and the reasonableness and /or cost of the works.
Name: Judge Pittaway Date: 25 November 2025
ANNEX - RIGHTS OF APPEAL
1. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber) then a written [NAME] for permission must be made to the First-tier Tribunal at the [NAME] which has been dealing with the case.
2. The [NAME] for permission to appeal must arrive at the [NAME] within 28 days after the Tribunal sends written reasons for the decision to the [NAME].
3. If the [NAME] is not made within the 28-day time limit, such [NAME] must include a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then look at such reason(s) and decide whether to allow the [NAME] for permission to appeal to proceed despite not being within the time limit.
4. The [NAME] for permission to appeal must identify the decision of the Tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal, and state the result the party [NAME] the [NAME] is seeking.
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) Landlord Allowed to Bypass Consultation for Urgent Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Window Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Lift Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Fire Safety Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Fire Safety Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Urgent Roof Repairs Dispensation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Urgent Repairs Dispensation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Major Works
- First-tier Tribunal (Property Chamber) Landlord Granted Dispensation for Urgent Roof Repairs
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The works were urgent due to ongoing leaks and potential damage to the property.
- The need for the works and their urgency were confirmed by independent surveyors.
- The contractor was chosen after getting multiple quotes for the works.
- The leaseholders were informed and given a chance to respond, so they suffered no disadvantage.
- No leaseholders objected to the application for dispensation.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The decision allowed the landlord to bypass the usual consultation process for urgent roof repairs.
Who was involved?
The landlord and the long leaseholders of the flats were involved.
How did the court decide, and why?
The court decided that the landlord could bypass the consultation process because the repairs were urgent and necessary to prevent damage.
Which laws or rules were applied?
The Landlord and Tenant Act 1985, specifically section 20ZA, was applied.
What was the argument that mattered most?
The argument that mattered most was that the repairs were urgent and necessary to prevent damage to the property.
Was the decision for or against the person who brought the case?
The decision was for the landlord.
What does this mean for someone in a similar situation?
Someone in a similar situation may also be able to bypass the consultation process if they can prove that the repairs are urgent and necessary.
What evidence or documents mattered?
Evidence of the urgency and necessity of the repairs, including inspection reports and quotes from contractors, mattered.
Can a decision like this be appealed?
Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
It is always recommended to seek advice from a qualified solicitor for cases involving property disputes.