Service Charge Determination for Water Supply Improvements
📌 In brief
In this case, the First-tier Tribunal decided on whether a service charge for water supply improvements was reasonable and payable. The Tribunal ruled that the cost of the necessary works could be recovered from all lessees as a service charge.
⚖️ Legal holding
The cost of works reasonably required to remedy the water pressure problem is recoverable from all lessees as a service charge.
📖 What the law says
This section states that when determining the amount of a service charge, only relevant costs that are reasonably incurred should be considered. Additionally, if these costs are for providing services or carrying out works, they must be of a reasonable standard.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal ruled on the payability and reasonableness of a proposed service charge for water supply improvements.
📜 Headnote Official document
The Tribunal considered an application for a determination as to the payability and reasonableness of a service charge proposed to be levied in respect of fitting a pump to boost the water supply to certain flats. The Tribunal concluded that the cost of works reasonably required to remedy the water pressure problem is recoverable from all lessees as a service charge.
📚 Full judgment Official document
OUTCOME: Allowed
© CROWN COPYRIGHT 2019
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
Case Reference
:
CHI/00MR/LIS/2019/0011
Property
:
Courtlands, 29C Clarence Parade, Southsea, Hampshire [POSTCODE]
Applicants
:
[redacted]
:
[COMPANY], ([NAME])
Respondents
:
[redacted] [NAME] [NAME] and [NAME] [NAME] DF [NAME] Mrs [NAME] [NAME] and Mrs [NAME] [NAME] [NAME] [NAME] [COUNSEL] and [NAME] [COUNSEL] [NAME]
:
Type of Application
: Service charges
Tribunal Member(s)
:
Judge D. [NAME] [NAME] of Decision
: 1st July 2019
DETERMINATION
2
Background 1. On By an application dated 22nd January 2019 the [NAME] applied to the Tribunal under section 27A(3) of the Landlord and Tenant Act 1985 (“the Act”) for a determination as to the payability and reasonableness of a service charge proposed to be levied in respect of fitting a pump to boost the water supply particularly to flats 7 and 9 at the Property.
2. Directions were issued on 15th February 2019 providing that the matter be determined by way of a paper determination rather than an oral hearing unless any party objected. No party did object.
3. The directions also provided for the exchange of statements of case.
4. The Tribunal received a response from the lessees of Flats 1,2,8, and 10 all who opposed having to pay for the proposed works and in the papers supplied by the Applicant the [NAME] wanted the work to proceed and there was a complaint about water pressure from the [NAME] in 2013 but as their name was omitted from the email stream it is not possible to identify whether the complainant at that time was the same as the current owner, Ms [NAME]. Ms [NAME] has not responded to the current application.
5. In view of the opposition from a number of lessees to paying for the proposed works the Respondent’s [NAME] agent seeks a determination from the Tribunal as to whether, if they went ahead, the cost would be recoverable from the lessees by way of service charge. Inspection 6. The Tribunal [NAME] 7 at the invitation of the [NAME] on 25th June 2019. The Tribunal saw for itself the poor flow of both hot and cold water to the sinks in the kitchen and bathroom and to the bath. The Applicant’s evidence 7. The problem at the Property that the proposed works is intended to address is the lack of water pressure to the two topmost flats at the front of the building. There are ten flats in all: five at the front of the building one on top of the other and five at the rear. There seems to be no problem with the flats at the rear of the building. This may indicate that there are two mains supplies or separate risers for the front and rear of the building but this has not been established. There appears to be no problem with the water pressure to the flats on the lower floors, either at the front or the rear of the building.
8. The complaint is principally from [NAME] 7, which is on the second floor at the front of the building. The [NAME] complains that the water pressure to the kitchen sink and the wash basin and bath in the bathroom is even worse at certain times of the day. He is unable to fill his bath to m
3 an adequate depth. In 2013 the [NAME] was complaining that at certain times of day and at other irregular periods they receive no water supply at all from the mains. The water company say that they are only obliged to provide 1 bar of pressure to properties which is adequate only to supply to a height of 9 metres above the point of the main entering the building.
9. There is a preliminary report from [NAME](Hons) CENG FCIBSE of [COMPANY], [COMPANY] carried out for the [NAME] agents in April 2015 which confirms the pressure problem pointing out that “some old pipework may have reduced the diameter due to scale build up” and possibly the pipes are undersized. The report is not very detailed but does suggest remedial action of installing a break tank and pump, replacing the cold water main from the inlet to the building throughout the common parts. It also indicates a possible cost for this work of approximately £40,000. The hot water is addressed separately but is even vaguer in its findings and recommendation.
10. Before this, however, the [NAME] agents had commenced the consultation procedure under section 20 of the Act. They served a Notice of Intent and obtained estimates and issued a Statement of Estimates in December 2014. Two estimates were received. There was a large difference between the estimates: one being for £18,021 and the other for £55,400. The consultation process went no further and no works were put in hand. The opposition case 11. Quite simply, the lessees who do not suffer from water pressure problems and who would not directly benefit from the works do not see why they should have to contribute towards paying for the works to be done. The lease 12. Clause 1 of the lease contains the charging clause whereby the [NAME] is to pay “by way of additional rent in respect of the expenses set out in the Fourth schedule …the amounts (hereinafter called the maintenance and supply charges) calculated in accordance with the provisions of the Fifth schedule and at the times and in the manner therein specified” 13. In Part A of the Fourth Schedule under the heading “ Expenses and matters in respect of which the [NAME] is to contribute there are the following provisions:- 1. The expense of maintaining repairing making up cleansing decorating and renewing: (b) the hot water system the gas and water pipes cylinders and tanks main drains and sewers …..and apparatus available for general or communal in under or upon Courtlands”
4 6. All other expenses normally incurred in the management of a block of flats”.
14. By the Fifth Schedule subparagraph 1(6) “the maintenance charge” means twelve per cent of the total costs certified by the Accountant and incurred by the landlord in respect of the matters set out in Part A of the Fourth schedule in the year to which the certificate relates and payable to the Landlord by the [NAME].
15. By Clause 4(2) of the lease the Landlord covenants (subject to contribution and payment as hereinbefore provided) the landlord will (i) keep and maintain in good and tenantable repair make up clean redecorate and renew… (b) the gas and water pipes the communal gas fired boiler supplying the domestic hot water(hereinafter called “the hot water system”)(or other system for the time being installed)all cylinders and ….and apparatus available for general or communal use in under and upon Courtlands.
16. In paragraph 3 of the Second Schedule to the lease one of the easements rights and privileges granted to the [NAME] is “ the free and uninterrupted passage and running of water ….through the sewers drains gutters and watercourses cables pipes and wires which now are or may within eighty years be in under or passing through Courtlands or any part thereof”. (The lease is dated 28th November 1985). The law 17. By section 19 of the Act:- 18. “ Where a service charge is payable before the relevant costs are incurred, no greater amount than is reasonable is payable, and, after the relevant costs have been incurred, any necessary adjustment shall be made by repayment, reduction or subsequent charges or otherwise. 19..By Section 27A of the 1985 Act it is provided that:- (1) An application may be made to a Leasehold Valuation Tribunal for a determination whether a service charge is payable and, if it is, as to – (a) the person by whom it is payable, (b) the person to whom it is payable, (c) the amount which is payable, (d) the date at or by which it is payable, and (e) the manner in which it is payable. (2) Subsection (1) applies whether or not any payment has been made. (3) An application may also be made to a Leasehold Valuation Tribunal for a determination whether, if costs were incurred for services, repairs, maintenance, improvement, insurance or management of any specified description, a service charge would be payable for the costs and, if it would, as to – (a) the person by whom it is payable, (b) the person to whom it is payable, (c) the amount which is payable,
5 (d) the date at or by which it is payable, and (e) the manner in which it is payable.
Discussion and determination 20. Unfortunately in this case there is a dearth of detailed technical analysis of the water supply system at Courtlands, the current deficiencies that exist to the system, the cause of that deficiency and the solution to the problems that exist and the cost thereof. Without this evidence it is not possible for the Tribunal to provide a definitive answer to the application in this case. The best that the Tribunal can do is to construe the lease and determine whether the lease provides for the recovery of the cost of any necessary works in certain circumstances that might be found by expert analysis.
21. The section 20 consultation and the estimates obtained are now so old that a new section 20 consultation would have to be undertaken and up to date estimates obtained. The Tribunal cannot possibly say, on the current evidence, whether any particular amount of expenditure would be reasonable for the landlord to incur and recover from the lessees by way of service charge.
22. The report from [NAME] is now five years old. There is no evidence of a problem in [NAME] 9 since 2013. What has been happening there in the meantime? 23. What the Tribunal can say, in construing the lease, is that if the cause of the problem of the lack of water pressure, or a significant contributory cause of the problem, is inadequate size of pipe or a constriction of the bore of the pipework due to furring or a build up of sediment, then replacement of the pipework or descaling of the pipework would be a service charge item under paragraph 1(6) of the Fifth Schedule and paragraph 1(b) of part A of the Fourth Schedule.
24. If that is not the problem but it is simply that the pressure coming from the main is not sufficient to supply water at an adequate rate to the top floors then unless this would come under paragraph 6 of Part A of the Fourth Schedule (“all other expenses normally incurred in the management of a block of flats) then this would not be covered under any other part of the Fourth Schedule.
25. The question, then, is can paragraph 6 of the Fourth Schedule be construed to cover that situation? In the Tribunal’s view, although the paragraph as worded is very vague and general, it does encompass expenditure that would be incurred by a landlord or its [NAME] agent in ensuring an adequate pressure of water for the normal expectations for everyday living. This would be part and parcel of the management of a block of flats.
26. The Tribunal did consider whether “management” in paragraph 6 is restricted to the actual act of management rather than carrying out repairs or maintenance but [NAME] agents’ and accountants’ fees are
6 specifically covered by paragraph 7, so the tribunal does not consider that paragraph 6 is restricted in this way.
27. This means that the reasonable cost of works reasonably required to remedy the water pressure problem would be recoverable from all the lessees as a service charge in the proportions set out in their individual leases.
28. It very often happens, as here, that lessees who do not directly benefit from repairs or maintenance feel that they should not be required to contribute to the costs as they do not directly benefit. One sees this, for example, where ground floor tenants object to paying for lift repairs or where only top floor flats are affected by a leaking roof. The Tribunal understands this. However, if the lease says that all lessees must contribute then it does not matter that a particular [NAME] does not benefit from the necessary works. That is the case here.
29. The Tribunal is concerned that there has not been a proper report to identify the problem and its extent or for there to be a proper specification for the recommended works drawn up and for up to date tenders to be acquired. The Tribunal is also concerned that there is such a disparity in the two estimates that were obtained in 2014. At least one of them must be wrong, or unreasonable. 30. [NAME] [NAME] has been extremely tolerant of this situation for many years and who knows what the lessees of [NAME] 9 have had to endure since 2013. One would have thought that if the situation has continued to be as it was seemingly in 2013 that they would have been clamouring for the situation to be rectified.
31. Hopefully, the limited amount that the Tribunal has been able to do under the current application in construing the lease as we have will enable the [NAME] agents now to press ahead as quickly as possible to obtain a proper expert’s report and proceed with a proper section 20 consultation. Once this has been done the Applicant may, if it so wishes, make a fresh application to the Tribunal under section 27A(3) of the Act for a determination as to whether the newly proposed costs would be reasonably incurred and be reasonable in amount. Dated the 1st July 2019 Judge D. [NAME] (Chairman)
7 APPEALS
1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application to the First-tier Tribunal at the Regional office which has been dealing with the case.
2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.
3. If the person wishing to appeal does not comply with the 28-day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28- day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.
4. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking Appeals
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) First-tier Tribunal Appoints New Manager for Lease Issues
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules on Service Charge Recovery
- First-tier Tribunal (Property Chamber) Manager Granted Power to Revoke Consents and Licenses
- First-tier Tribunal (Property Chamber) Tribunal Excludes Unreasonable Costs from Residential Service Charges
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Tenant Breached Lease Conditions
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Ventilation System Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Appoints Property Manager for Poorly Maintained Buildin…
- First-tier Tribunal (Property Chamber) Tribunal Appoints Property Manager to Address Mismanagement and Disrepair
- First-tier Tribunal (Property Chamber) First-tier Tribunal Appoints Property Manager Under Landlord and Tenant Act
- First-tier Tribunal (Property Chamber) Tribunal Appoints Manager Due to Breach of Lease Obligations
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charge Costs Recoverable
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation from Consultation Requirements
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The cost of works to fix a water pressure problem is considered reasonable and recoverable.
- Service charges are allowed if they are specified in the lease and deemed reasonable.
- Appointing a manager to resolve issues is seen as just and convenient.
- Landlords can bypass consultation if the works are urgent and necessary for safety.
- Tenants are entitled to exclude unreasonable costs from service charges.
❌ Tends to be rejected
- (No factors listed against the claimant based on the provided cases.)
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Tribunal ruled that the cost of works reasonably required to remedy the water pressure problem is recoverable from all lessees as a service charge.
Who was involved?
The case involved a landlord's managing agent and several lessees of flats in a residential property.
How did the court decide, and why?
The court decided that the cost of the works was recoverable because it falls under the lease agreement and is necessary for the management of the block of flats.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 sections 19 and 27A were applied.
What was the argument that mattered most?
The argument that mattered most was that the cost of the works was necessary for the management of the block of flats and thus recoverable under the lease agreement.
Was the decision for or against the person who brought the case?
The decision was in favour of the landlord's managing agent.
What does this mean for someone in a similar situation?
Someone in a similar situation should ensure that the proposed works are necessary and reasonable under their lease agreement.
What evidence or documents mattered?
Evidence such as the lease agreement, previous complaints about water pressure, and expert reports on the water supply system were important.
Can a decision like this be appealed?
Yes, a person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so within 28 days of receiving written reasons for the decision.
Is it worth getting a solicitor for a case like this?
It is always advisable to seek advice from a qualified solicitor for cases involving lease agreements and service charges.