The First-tier Tribunal allowed a landlord to bypass the usual consultation process for urgent roof repairs, ensuring the safety and integrity of the building without causing harm to the leaseholders.

⚖️ Legal holding

A landlord may be dispensed from consultation requirements if the Tribunal finds it reasonable.

Topics

tenancy disputesroof repairs

Provisions

Landlord and Tenant Act 1985 s.20ZAService Charges (Consultation Requirements) (England) Regulations 2003

📖 What the law says

Landlord and Tenant Act 1985 s.20ZA

The First-tier Tribunal can grant an exemption from consultation requirements if it determines that it is reasonable to do so. Consultation requirements refer to the obligations placed on landlords to consult tenants before undertaking certain works or entering into long-term agreements.

Plain-English explanation — does not replace advice from a solicitor.

📖 Technical summary

The Tribunal granted dispensation from consultation requirements for urgent roof repairs.

📜 Headnote Official document

The First-tier Tribunal granted dispensation from consultation requirements for urgent roof repairs, finding it reasonable to do so given the urgency of the work and lack of prejudice to the leaseholders.

📚 Full judgment Official document

OUTCOME: Allowed

© CROWN COPYRIGHT 2022

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

Case Reference

: LON/00BD/LDC/2025/0908.

Property

:

203C [APPELLANT], London [POSTCODE]

Applicant: [redacted]

:

[COMPANY]

Respondent: [redacted]

The 3 leaseholders in accordance with schedule attached the application.

Type of Application

: To dispense with the requirement to consult lessees about major works section 20ZA of the Landlord and Tenant Act 1985.

Tribunal Members

:

Mr [APPELLANT] of Decision

:

27 January 2026

Decision

2 Decisions of the Tribunal (1) The Tribunal grants the application for the dispensation of all or any of the consultation requirements provided for by section 20 of the Landlord and Tenant Act 1985 (Section 20ZA of the same Act). (2) This decision does not affect the Tribunal’s jurisdiction upon any future application to make a determination under section 27A of the Act in respect of liability to pay, for a reason other than non-consultation in respect of the insurance premiums and the reasonableness and/or the cost of the premiums (3) The reasons for the Tribunal’s decision are set out below. The background to the application 1. The property is a three storey semi detached Victorian building with render elevations under a pitched and tiled roof which comprises 3 converted flats in the subject building. The property forms part of a larger building containing 9 shareholders.

2. The Tribunal did not inspect the property as it considered the documentation and information before it in the set of documents prepared by the Applicant enabled the Tribunal to proceed with this determination.

3. This has been a paper hearing which has been consented to by the parties. The documents that were referred to are prepared by the Applicant, plus the Tribunal’s [NAME] dated 11 November 2025.

4. The Applicant seeks dispensation under section 20ZA of the Landlord and Tenant Act 1985 (“the 1985 Act”) from all the consultation requirements imposed on the landlord by section 20 of the 1985 Act, (see the Service Charges (Consultation Requirements) (England) Regulations 2003 (SI2003/1987), Schedule 4). The request for dispensation is in respect of urgent works to the roof structure as there is ongoing penetrating damp.

5. The landlord has applied for dispensation from the statutory consultation requirements in respect of urgent remedial works to the pitched and tiled roof following the initial installation of a replacement velux window and a structural engineers report from [NAME] which recommended stripping the roof in this area and providing insulation. It is stated in the application that the roof has suffered significant water ingress which has caused rot infestation to the timber roof frame. The planned repair works are scheduled to be undertaken by [COMPANY] who have provided various

3 quotations for the preliminaries, scaffolding, roof works and the velux roof light.

6. Section 20ZA relates to consultation requirements and provides as follows: “(1) Where an application is made to a leasehold valuation tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long term agreement, the tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.

(2) In section 20 and this section— “qualifying works” means works on a building or any other premises, and “qualifying long term agreement” means (subject to subsection (3)) an agreement entered into, by or on behalf of the landlord or a superior landlord, for a term of more than twelve months. …. (4) In section 20 and this section “the consultation requirements” means requirements prescribed by regulations made by the Secretary of State. (5) Regulations under subsection (4) may in particular include provision requiring the landlord— (a) to provide details of proposed works or agreements to tenants or the recognised tenants’ association representing them, (b) to obtain estimates for proposed works or agreements, (c) to invite tenants or the recognised tenants’ association to propose the names of persons from whom the landlord should try to obtain other estimates, (d) to have regard to observations made by tenants or the recognised tenants’ association in relation to proposed works or agreements and estimates, and (e) to give reasons in prescribed circumstances for carrying out works or entering into agreements.

7. The [NAME] on 11 November 2025 required any of the leaseholders who opposed the application to make their objections known on the reply form produced with the [NAME]. No objections were received from the leaseholders. 8. By the same [NAME] of the Tribunal dated 11 November 2025 it was decided that the application be determined without a hearing by way of a paper case. The issues

4 9. The only issue for the Tribunal to decide is whether or not it is reasonable to dispense with the statutory consultation requirements. This application does not concern the issue of whether or not service charges will be reasonable or payable. Findings 10. Having read the comprehensive evidence and submissions from the Applicant and having considered all of the documents and grounds for making the application provided by the Applicant, the Tribunal determines the dispensation issues as follows.

11. Section 20 of the Landlord and Tenant Act 1985 (as amended) and the Service Charges (Consultation Requirements) (England) Regulations 2003 require a landlord planning to undertake major works, where a leaseholder will be required to contribute over £250 towards those works, to consult the leaseholders in a specified form.

12. Should a landlord not comply with the correct consultation procedure, it is possible to obtain dispensation from compliance with these requirements by an application such as this one before the Tribunal. Essentially the Tribunal must be satisfied that it is reasonable to do so.

13. In the case of [COMPANY] v Benson [2013] UKSC 14, by a majority decision (3-2), the Supreme Court considered the dispensation provisions and set out guidelines as to how they should be applied.

14. The Supreme Court came to the following conclusions: a. The correct legal test on an application to the Tribunal for dispensation is: 

“Would the flat owners suffer any relevant prejudice, and if so, what relevant prejudice, as a result of the landlord’s failure to comply with the requirements?” b. The purpose of the consultation procedure is to ensure leaseholders are protected from paying for inappropriate works or paying more than would be appropriate. c. In considering applications for dispensation the Tribunal should focus on whether the leaseholders were prejudiced in either respect by the landlord’s failure to comply. d. The Tribunal has the power to grant dispensation on appropriate terms and can impose conditions. e. The factual burden of identifying some relevant prejudice is on the leaseholders. Once they have shown a credible case for prejudice, the Tribunal should look to the landlord to rebut it.

5 f. The onus is on the leaseholders to establish: i. what steps they would have taken had the breach not happened and ii. in what way their rights under (b) above have been prejudiced as a consequence.

16.

Accordingly, the Tribunal had to consider whether there was any prejudice that may have arisen out of the conduct of the applicant and whether it was reasonable for the Tribunal to grant dispensation following the guidance set out above.

17. The whole purpose of Section 20ZA is to permit a landlord to dispense with the consultation requirements in Section 20 of the Act if the Tribunal is satisfied that is necessary for them to be dispensed with.

18. The one issue for the Tribunal is to determine whether or not it is reasonable to dispense with the statutory consultation requirements and if so was there any relevant financial prejudice suffered by the 3 leaseholders as a result of a failure to consult.

19. The Tribunal’s focus should be on any prejudice caused by the proposed works. The overarching question is not whether the Landlord acted reasonably but is whether the Tribunal is satisfied that it is reasonable to dispense with compliance.

20. On the balance of the evidence provided by the applicant it could not find prejudice to any of the leaseholders of the property by the granting of dispensation relating to the urgent roof works as set out in the documentation in the bundle submitted in support of the application.

21. This decision does not concern the reasonableness of the cost of the works, as set out in the quotations received from [COMPANY] and the respondents are not precluded from submitting an application under Section 27A of the Act to contest whether the service charge cost is reasonable or payable if they so wish.

22. On the evidence before it, the Tribunal believes that it is reasonable to allow dispensation in relation to the subject matter of the application. The Applicant is required to the maintain the structure and fabric of the building in accordance with the terms of the lease.

23. Rights of appeal made available to parties to this dispute are set out in an Annex to this decision.

24. The Applicant shall be responsible for formally serving a copy of the Tribunal’s decision on the 3 leaseholders named on the schedule attached to the application. Furthermore, the Applicant shall place a copy of the

6 Tribunal’s decision on dispensation together with an explanation of the leaseholders’ appeal rights on its website (if any) within 7 days of receipt and shall maintain it there for at least 3 months, with a sufficiently prominent link to both on its home page. It should also be posted in a prominent position in the communal areas. In this way, leaseholders who have not returned the reply form may view the Tribunal’s eventual decision on dispensation and their appeal rights.

[NAME]. 27 January 2026

ANNEX - RIGHTS OF APPEAL

1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application by email to [EMAIL]

2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.

3. If the person wishing to appeal does not comply with the 28 day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The works are urgent.
  • There is no relevant prejudice to the leaseholders.
  • The works are critical for residents' safety.
  • The works are necessary to ensure the safety of the building.
  • The Tribunal finds it reasonable.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

It decided to grant dispensation from consultation requirements for urgent roof repairs.

Who was involved?

The landlord and the leaseholders of a multi-unit building.

How did the court decide, and why?

The court decided to grant dispensation because the work was urgent and there was no evidence of prejudice to the leaseholders.

Which laws or rules were applied?

The Landlord and Tenant Act 1985 and the Service Charges (Consultation Requirements) (England) Regulations 2003.

What was the argument that mattered most?

The argument that the work was urgent and necessary to prevent further damage to the building.

Was the decision for or against the person who brought the case?

The decision was for the landlord.

What does this mean for someone in a similar situation?

Someone in a similar situation may also be able to get dispensation if the work is urgent and there is no prejudice to the leaseholders.

What evidence or documents mattered?

Evidence of the urgency of the work and the lack of prejudice to the leaseholders.

Can a decision like this be appealed?

Yes, decisions like this can be appealed to the Upper Tribunal (Lands Chamber).

Is it worth getting a solicitor for a case like this?

Yes, it is always advisable to seek legal advice from a qualified solicitor for cases involving property law.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.