VadeLab
AllowedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Grants Dispensation From Consultation Requirements

Case No.

📌 In brief

The First-tier Tribunal allowed the landlord to bypass the usual consultation process with leaseholders regarding major works, specifically the installation of an audible fire alarm system, due to the lack of objections from the leaseholders and the absence of proven harm to them.

⚖️ Legal holding

A landlord may be dispensed from the consultation requirements under Section 20ZA of the Landlord and Tenant Act 1985 if it is reasonable to do so.

Topics

tenancy disputesfire safety measures

Provisions

Landlord and Tenant Act 1985 s.20ZA

📖 What the law says

Landlord and Tenant Act 1985 s.20ZA

Under this section, a tribunal can decide to waive the consultation requirements for certain works or long-term agreements if it finds it reasonable to do so. The consultation requirements themselves are defined by regulations set by the Secretary of State, which can include providing details to tenants, obtaining estimates, considering tenant feedback, and giving reasons for actions.

Plain-English explanation — does not replace advice from a solicitor.

📖 Technical summary

The Tribunal granted dispensation to the claimant from the consultation requirements under Section 20ZA of the Landlord and Tenant Act 1985.

📜 Headnote Official document

The First-tier Tribunal granted dispensation to the landlord from the consultation requirements under Section 20ZA of the Landlord and Tenant Act 1985, allowing the landlord to proceed with installing an audible fire alarm system without consulting the leaseholders. The decision was based on the lack of opposition from the leaseholders and the absence of demonstrated prejudice.

📚 Full judgment Official document

OUTCOME: Allowed

© CROWN COPYRIGHT 2024

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

Case Reference

:

HAV/00HQ/LDC/2024/0612

Property

:

[NAME] 1 – 55, 57 St Peter’s Road, Bournemouth. [POSTCODE]

Applicant: [redacted]

[COMPANY] : [NAME]

Respondents

:

[redacted] Property

Type of Application

:

To dispense with the requirement to consult [NAME] about major works section 20ZA of the Landlord and Tenant Act 1985

Tribunal

:

Judge C A Rai

Date of Decision

:

10 December 2024

DECISION

2 This is a formal order of the Tribunal which must be complied with by the parties. Communications to the Tribunal MUST be made by email to [EMAIL]. All communications must clearly state the Case Number and address of the premises.

Summary of the Decision

1. The Applicant is granted dispensation under Section 20ZA of the Landlord and Tenant Act 1985 from the consultation requirements imposed on the landlord by Section 20 of the 1985 Act in relation to the works outlined in the notice of intention to leaseholders dated 9 September 2024. The Tribunal has made no determination on whether the costs of the works are reasonable or payable.

Background

2. The Applicant seeks dispensation under Section 20ZA of the Landlord and Tenant Act 1985 and from the consultation requirements imposed on the landlord by Section 20 of the same Act. The application was received on 11 October 2024.

3. The Property is described in the application as:

A multi occupancy building located in St Peter’s Road Bournemouth built in approximately 2002. It is a detached purpose built block. The majority of the external walls of the building are constructed from a Sto EPS insulated render system over a masonry inner wall with areas of the window walling on the top floor and gabion walling to the car park. The building has a flat roof. 1 x main exit/entrance. 8 x Floors. 55 x Flats. Protected concrete stairs as the sole escape for residents above the ground floor. 1 x lift servicing all floors (not an evacuation lift). Lift opens into lobbied area on each floor. Car park on two levels accessed from the ground floor and the first floor with 60 minute protection. Smoke extraction system installed with vents in each flat lobby area. 2 door lobby protection to flats on all floors. Timber decked balconies. Approx size 47m x 24m. The building operates a stay put policy with a single stair and two exits. Fire Safety Height - 20.4 meters. Height of topmost storey >18. [Construction details written by the Fire Assessor]

4. The Applicant explains in the application that currently there are proposed rectification works being agreed with the original developer ([NAME]), but the full scope of the works has not yet been agreed. • A Fire Risk Assessment (FRA) stated that an audible fire alarm system should be installed as a temporary measure. Currently there is no audible system although there is an extraction system to remove smoke from the lobbies.

3 • During discussions with [NAME], it advised that they were not seeking quotes for this as the rectification works would be carried out shortly. • [NAME] rectification works were put on hold. We contacted them to remind them that if they didn’t do the rectification works, then this fire alarm needed to be installed. • [NAME] then confirmed that they are not responsible for any fire alarm system. • [NAME] have instructed [NAME] of [NAME] to obtain estimates for a new audible fire alarm system for [NAME]. • The Applicant received the revised Fire Risk Assessment document PAS9980 from [NAME] (produced by their fire engineers MAF). Within this document, the risk level for the block was changed from ‘medium’ to high.’ • The Applicant sent a copy of this revised report to the fire risk assessor, and they have confirmed that this change to the risk level means that it has no choice but to advise that the development needs a ‘[NAME]’ until the new fire alarm system has been installed. • The Applicant expected that the new fire risk assessment would be sent to it during the following week. Thereafter it would then need to implement the recommendations and [NAME] as soon as possible with an anticipated cost for this of around £15,000 per week. It stated it would require a minimum of six weeks. • Fire alarm upgrade: It expected that the fire alarm test would be carried out on Wednesday 16th October 2024 (those flats chosen) have been contacted and notices have been put through doors. It is now critical to obtain the fire alarm quote back as quickly as possible. The Applicant stated “so I truly hope that residents (sic) give access to the contractors on Wednesday. Once this test has been carried out, we hope to have the fire alarm quote back within 7 days. The fire alarm will need detectors and sounders in each flat and [NAME] will continue to charge and attend until these have all been installed. Acces (sic) into flats will be critical. [NAME] will be responsible for organising and paying for the fire alarm, certainly in the first instance”.

And further AGM INFORMATION SHARED RECENTLY:

EWS1 – Following the suspension of the EWS1 certificate, [NAME] – the parent company of the original developer – were contacted. After initial discussions they agreed to carry out an investigation into whether there are latent safety defects around the windows and behind the cladding. [NAME] have confirmed that they will undertake the following works:

4 • External façade – provide a new fire barrier and water proofing detail along the compartment floor slab level, behind the aluminium spandrel panels. • Replacing timber decking on the balconies with non-combustible materials. • Replace and upgrading communal doors • Renewing the fire stopping around all flat front door frames and adjusting the gaps. Access will be required to your flat front doors to facilitate this. • Internal compartmentation and fire stopping to the communal areas. • The Management Company have appointed a local Chartered Building Engineer, [NAME] of [NAME], and he has provided a report which basically states that in his opinion, the windows need further investigation. [NAME] had initially provided a report that stated that the windows themselves formed a cavity closer to prevent the spread of fire. Mr [NAME] report disagrees with this assessment and requests that [NAME] undertake further investigations. The report, undertaken in April 2024 and passed to [NAME] in May 2024 stated that the current installation of the windows does not comply with Approved Document Part B Volume 1, nor earlier versions at the time of construction. His recommendation is that that fire barriers should be installed around each window and door to ensure full fire resistance. To date, we have not had a reply from [NAME] on this report. [NAME] have stated that they have passed the report to their own advisors and are awaiting their instructions. • The Management Company have appointed [COMPANY] of [ADDRESS], London as their appointed solicitor to provide advice to [NAME] and to assist [COMPANY] in their role as advisor to the management company.

5. The Applicant stated in the Application that the Notice of Intention under section 20 letter was issued on 9 September 2024.

6. The Tribunal gave Directions on 21 October 2024 listing the steps to be taken by the parties in preparation for the determination of the dispute, if any.

7. The Directions stated that Tribunal would determine the application on the papers received unless a party objected in writing to the Tribunal within 7 days of the date of receipt of the Directions. No party has objected to the application being determined on the papers.

8. The only issue for the Tribunal is whether or not it is reasonable to dispense with the statutory consultation requirements. This application is not about the proposed costs of the works, and whether they are recoverable from the leaseholders as service charges or the possible application or effect of the Building Safety Act 2022. The leaseholders have the right to make a separate application to the Tribunal under

5 section 27A of the Landlord and Tenant Act 1985 to determine the reasonableness of the costs, and the contribution payable through the service charges.

The Law

9. Section 20 of the Landlord and Tenant Act 1985 (“the Act”) and the related Regulations provide that where [NAME] undertakes qualifying works with a cost of more than £250 per lease, the relevant contribution of each [NAME] (jointly where more than one under any given lease) will be limited to that sum unless the required consultations have been undertaken or the requirement has been dispensed with by the Tribunal. An application may be made retrospectively.

10. The relevant section of the Act reads as follows:

S.20 ZA Consultation requirements: Where an application is made to a Leasehold Valuation Tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long-term agreement, the Tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.

11. The appropriate approach to be taken by the Tribunal in the exercise of its discretion was considered by the Supreme Court in the case of [COMPANY] v [NAME] et al [2013] UKSC 14.

12. The leading judgment of Lord [NAME] explained that a Tribunal should focus on the question of whether the [NAME] will be or had been prejudiced in either paying where that was not appropriate or in paying more than appropriate because the failure of [NAME] to comply with the regulations. The requirements were held to give practical effect to those two objectives and were a means to an end, not an end in themselves.

13. The factual burden of demonstrating prejudice falls on the [NAME]. The [NAME] must identify what would have been said if able to engage in a consultation process. If the [NAME] advances a credible case for having been prejudiced, [NAME] must rebut it. The Tribunal should be sympathetic to the [NAME].

14. Where the extent, quality and cost of the works were in no way affected by [NAME]’s failure to comply, Lord [NAME] said as follows:

I find it hard to see why the dispensation should not be granted (at least in the absence of some very good reason): in such a case the tenants would be in precisely the position that the legislation intended them to be- i.e. as if the requirements had been complied with.

6 15. The main, indeed normally, the sole question, as described by Lord [NAME], for the Tribunal to determine is therefore whether, or not, the [NAME] will be or has been caused relevant prejudice by a failure of the Applicant to undertake the consultation prior to the major works and so whether dispensation in respect of that should be granted.

16. The question is one of the reasonableness of dispensing with the process of consultation provided for in the Act, not one of the reasonableness of the charges of works arising or which have arisen.

17. If dispensation is granted, that may be on terms.

18. There have been subsequent Decisions of the higher Courts and Tribunals of assistance in the application of the Decision in Daejan, but none are relied upon or therefore require specific mention in this Decision.

Consideration

19. The Directions attached a reply form for the Respondents to complete to confirm whether they agreed with the application or not and if opposed, to provide a statement setting out why they oppose.

20. The Tribunal has not received replies from any of the [NAME].

21. Having considered the application and prior to undertaking this determination, I am satisfied that a determination on the papers remains appropriate, given that the application remains unchallenged.

22. The reason why dispensation from consultation requirements is to enable the Applicant to reduce the section 20 procedure to enable the Applicant to install the audible fire alarm system thus reducing the cost to the [NAME] of putting in place, retaining and funding a “[NAME]”.

23. There has been no objection to the dispensation of the consultation requirements from any of the [NAME].

24. None of the [NAME] have therefore asserted that any prejudice has been caused to them. The Tribunal finds that nothing different would be done or achieved in the event of a full consultation with the [NAME], except for the potential delays and potential problems.

25. The Tribunal finds that the Respondents have not suffered any prejudice by the failure of the Applicant to follow the full consultation process.

26. The Tribunal consequently finds that it is reasonable to dispense with all the formal consultation requirements in respect of the major works to the building described in this Decision.

7 27. This Decision is confined to determination of the issue of dispensation from the consultation requirements in respect of the qualifying works to install the audible fire alarm system as outlined at paragraph 4. The Tribunal has made no determination on whether the costs are payable or reasonable. If a [NAME] wishes to challenge the payability or reasonableness of those costs, then a separate application under section 27A of the Act would have to be made.

28. In reaching my decision I have taken account of the fact that no party has objected to the application. The [NAME] have had opportunity to raise any objection, and they have not done so.

Judge C A Rai

RIGHTS OF APPEAL

1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application to the First-tier Tribunal at the Regional office which has been dealing with the case by email at [EMAIL]

2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.

3. If the person wishing to appeal does not comply with the 28- day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28- day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.

4. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The tribunal found it reasonable to grant dispensation from consultation requirements.
  • No leaseholders objected to the application for dispensation.
  • The proposed works are urgent to install an audible fire alarm system.
  • The leaseholders did not demonstrate any prejudice from the lack of full consultation.
  • Full consultation would only cause potential delays and problems without achieving anything different.

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The decision allowed the landlord to bypass the consultation process with leaseholders regarding the installation of an audible fire alarm system.

Who was involved?

The landlord and the leaseholders of the property were involved.

How did the court decide, and why?

The court decided that it was reasonable to dispense with the consultation requirements because the leaseholders did not object and no prejudice was shown.

Which laws or rules were applied?

The Landlord and Tenant Act 1985, specifically Section 20ZA, was applied.

What was the argument that mattered most?

The argument that mattered most was that the leaseholders did not assert any prejudice from the failure to consult them.

Was the decision for or against the person who brought the case?

The decision was for the landlord who brought the case.

What does this mean for someone in a similar situation?

Someone in a similar situation might also be able to bypass the consultation process if there is no opposition from the leaseholders and no proven prejudice.

What evidence or documents mattered?

The lack of response from the leaseholders to the application was a key factor.

Can a decision like this be appealed?

Yes, a decision like this can be appealed to the Upper Tribunal within 28 days of receiving the written reasons for the decision.

Is it worth getting a solicitor for a case like this?

It is always recommended to get advice from a qualified solicitor for cases involving legal disputes.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.