VadeLab
AllowedFirst-tier Tribunal (Property Chamber)·

First-tier Tribunal Grants Dispensation From Consultation Requirements Due To Urgent Repairs

Case No.

📌 In brief

The First-tier Tribunal allowed a landlord to bypass consultation requirements because urgent repairs were needed to fix water damage. The building wasn't watertight, and waiting for consultations would have caused more harm.

⚖️ Legal holding

A landlord may be dispensed from consultation requirements if urgent repairs are necessary and there is insufficient time for consultation.

Topics

tenancy disputesurgent repairsdispensation from consultation

Provisions

Landlord and Tenant Act 1985 s.20ZALandlord and Tenant Act 1985 s.20

📖 What the law says

Landlord and Tenant Act 1985 s.20ZA

This section allows a tribunal to grant dispensation from consultation requirements if it finds it reasonable to do so. The consultation requirements refer to obligations placed on landlords to consult tenants before undertaking certain works or entering into long-term agreements.

Plain-English explanation — does not replace advice from a solicitor.

📖 Technical summary

The tribunal granted dispensation from consultation requirements due to urgent repairs needed for water damage.

📜 Headnote Official document

The First-tier Tribunal granted dispensation from consultation requirements to the landlord due to urgent repairs needed for water damage. The Tribunal found that the building was not watertight and further damage would occur if the repairs were delayed.

📚 Full judgment Official document

OUTCOME: Allowed

© CROWN COPYRIGHT

FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY)

Case Reference

:

CHI/ 00HN/LDC/2020/0065

Property

:

[ADDRESS] [POSTCODE]

Applicant: [redacted]

[COMPANY]

:

[COUNSEL]

Respondents

:

[redacted]

:

-

Type of Application

:

To dispense with the requirement to consult lessees about major works

Tribunal Member(s)

:

Judge Tildesley OBE

Date and Venue of Hearing

:

Determination on Papers

Date of Decision

:

9 November 2020

DECISION

2 The Application

1. The Applicant seeks dispensation under Section 20ZA of the [NAME] from the consultation requirements imposed on the landlord by Section 20 of the 1985 Act.

2. The Applicant explains that during works for which a full section 20 consultation had been carried out additional defects were discovered requiring further extensive repairs. The building was not watertight and at least some of the further repairs have been undertaken on an emergency basis to protect against further damage.

3. The Application for dispensation was received on 28 August 2020.

4. On 11 September 2020 the Tribunal directed the Applicant to serve the application and directions on the [NAME] which was done on 25 September 2020

5. The Tribunal directed that the Application would be heard on the papers unless a party requested an oral hearing. No party made such a request.

6. The Tribunal required the [NAME] to return a pro-forma to the Tribunal and the Applicant by 12 October 2020 indicating whether they agreed or disagreed with the application.

7. [NAME] (Flats 2, 10 and 15) returned the pro-forma stating their agreement to the application.

8. The Applicant was obliged to provide a hearing bundle by 26 October 2020. Unfortunately the Applicant failed to do this and the application was struck out. The Applicant applied for reinstatement of the application which was granted by Judge Tildesley OBE

. Determination

9. The Tribunal is satisfied from the Application and the documents that the additional defects only became apparent when the works were started for which the [NAME] had been consulted about. The additional defects related to the timber deck below the waterproofing which had been severely affected by water damage and that extensive repair works would be required in order to provide a safe balcony structure.

10. The Tribunal finds that the Applicant did not have time to carry out further consultation on the works to remedy the additional defects because the building was not watertight and it would have suffered further damage if the new works had not been carried out in a timely manner.

3 11. The Applicant asked for updated tenders from the contractors who had tendered for the initial works. The contractor who had originally won the tender remained the most competitive at £27,460 plus VAT for the revised specification for the works with the next tender received at £48,652 plus VAT. The Applicant advised that the works are now nearing completion and it is anticipated that there will be a cost saving the region of £8,000. The Tribunal notes that all [NAME] who responded were in favour of the Application.

12. The Tribunal finds that the additional works were necessary and urgent and there was not sufficient time to carry out statutory consultation. The Tribunal further finds that the Applicant obtained three competitive tenders for the revised specification of works and chose the lowest tender. The Tribunal is, therefore, satisfied that the [NAME] would suffer no relevant prejudice if dispensation from consultation was granted.

13. The Tribunal, therefore, dispenses with the consultation requirements in respect of the additional works to the timber deck.

14. The Tribunal’s decision is confined to the dispensation from the consultation requirements in respect of the works. The Tribunal has made no determination on whether the costs of those works are reasonable or payable. If a [NAME] wishes to challenge the reasonableness of those costs, then a separate application under section 27A of the [NAME] would have to be made.

15. The Tribunal directs the Applicant to inform the [NAME] of the Tribunal’s decision and to display the written decision on a noticeboard in the common areas.

4

RIGHTS OF APPEAL

1. A person wishing to appeal this decision to the Upper Tribunal (Lands Chamber) must seek permission to do so by making written application by email to [EMAIL] to the First-tier Tribunal at the Regional office which has been dealing with the case.

2. The application must arrive at the Tribunal within 28 days after the Tribunal sends to the person making the application written reasons for the decision.

3. If the person wishing to appeal does not comply with the 28 day time limit, the person shall include with the application for permission to appeal a request for an extension of time and the reason for not complying with the 28 day time limit; the Tribunal will then decide whether to extend time or not to allow the application for permission to appeal to proceed.

4. The application for permission to appeal must identify the decision of the Tribunal to which it relates, state the grounds of appeal, and state the result the party making the application is seeking.

Due to the Covid 19 pandemic, communications to the Tribunal MUST be made by email to [EMAIL]. All communications must clearly state the Case Number and address of the premises.

📊 How courts decide similar cases

Among 12 similar decisions in this collection:

A snapshot of this collection — not a prediction of your case's outcome.

⚖️ What tends to weigh in cases like this

✅ Tends to be accepted

  • The landlord needs to demonstrate a clear and urgent need for repairs.
  • Urgent repairs must be necessary to prevent further damage.
  • Consultation would cause undue delay or financial hardship.
  • There is insufficient time for statutory consultation due to urgency.
  • All responding leaseholders agree that urgent repairs are necessary.

❌ Tends to be rejected

  • (No significant factors identified that went against the claimant in these cases.)

Patterns observed in similar cases in this collection — every case is unique.

❓ Frequently asked questions

What did this decision decide?

The decision allowed the landlord to bypass consultation requirements for urgent repairs needed due to water damage.

Who was involved?

The landlord and leaseholders were involved.

How did the court decide, and why?

The court decided that the landlord could bypass consultation requirements because the building was not watertight and further damage would occur if the repairs were delayed.

Which laws or rules were applied?

Section 20ZA and Section 20 of the Landlord and Tenant Act 1985 were applied.

What was the argument that mattered most?

The argument that mattered most was that the building was not watertight and further damage would occur if the repairs were delayed.

Was the decision for or against the person who brought the case?

The decision was for the landlord.

What does this mean for someone in a similar situation?

Someone in a similar situation might also be able to bypass consultation requirements if they can show that urgent repairs are necessary to prevent further damage.

What evidence or documents mattered?

Evidence showing that the building was not watertight and that further damage would occur if the repairs were delayed mattered.

Can a decision like this be appealed?

Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).

Is it worth getting a solicitor for a case like this?

It is always recommended to get advice from a qualified solicitor for a case like this.

Official source: First-tier Tribunal (Property Chamber) headnote and full judgment reproduced from the court's public records. View on the official source ↗Summary, holding, technical summary and questions: produced by Artificial Intelligence based on the official headnote and judgment. These are VadeLab’s own material and are not the work of the Court.This decision was issued by the First-tier Tribunal (Property Chamber) and is reproduced from its published records. VadeLab is not affiliated with, and this page is not endorsed by, that court or tribunal.