First-tier Tribunal Rejects Claim for Code Agreement Due to Lack of Redevelopment Intent
📌 In brief
In a recent case, the First-tier Tribunal (Property Chamber) ruled on a dispute regarding a telecommunications site. The claimant wanted to impose a a person agreement under the Electronic Communications a person, while the respondent claimed they had plans to redevelop the site. The tribunal decided that the respondent did not meet the criteria for redevelopment, thus rejecting the claimant's request.
⚖️ Legal holding
The Telecommunications Act requires a genuine intention to redevelop the land to which the agreement relates.
📖 Technical summary
The tribunal dismissed the claim due to the respondent's failure to demonstrate a genuine intention to redevelop the site as per the Telecommunications Act requirements.
📜 Headnote Official document
The claimant sought to impose a code agreement under the Electronic Communications Code on a telecommunications site. The respondent argued they had an intention to redevelop the site. The First-tier Tribunal (Property Chamber) ruled that the respondent failed to establish an intention to redevelop the site within the meaning of Paragraph 21(5) of the Electronic Communications Code.
📚 Full judgment Official document
OUTCOME: Dismissed
1
FIRST-TIER TRIBUNAL
PROPERTY CHAMBER
(RESIDENTIAL PROPERTY)
Case Reference
: LC – 2019 – 000826
Property
: [NAME_1] at Queen’s Oak Farm, [ADDRESS], Yardley Gobion, Towcester, Northamptonshire [POSTCODE]
Claimant : [redacted] (formerly [NAME_4])
Representative : [NAME_5] KC, [NAME_7] instructed by [COMPANY_148] : AP Wireless II (UK) Limited (1) [COMPANY_11] (2)
Representative : [NAME_12] KC, [NAME_13] and [NAME_16] instructed by [COMPANY_20]
Application : Electronic Communications Code
Hearing : 29th, 30th September, 1st, 2nd, 6th and 7th October 2025 Birmingham Civil Justice Centre
Tribunal : Judge D Jackson Mr RP Cammidge FRICS
Date : 29th October 2025
DECISION
2
Background
1. This reference has a long and distinguished history. Its original title was [NAME_4] v AP Wireless II (UK) Limited [2020] UKUT 0195 (LC). Notice seeking an order under Paragraph 20 of the Code was served on 2nd July 2019 [A48- 78]. A reference was made to the Upper Tribunal on 20th August 2019. On 19th June 2020 Upper Tribunal Judge Cooke gave her decision on two preliminary jurisdictional issues. Judge Cooke found that [NAME_4] was a tenant at will. However, based on the decision of the Court of Appeal in Compton Beauchamp Judge Cooke held that the Tribunal had no jurisdiction to make an Order under Paragraph 20 of the Code.
2. The Claimant, [NAME_4], changed its name to [COMPANY_3] (“[NAME_2]”) in July 2020. The reference, by then titled, [COMPANY_3] (formerly known as Arqiva Services Ltd) v AP Wireless II (UK) Ltd [2022] UKSC 18, proceeded by way of leapfrog to join the appeal to the Supreme Court in Compton Beauchamp. The Supreme Court handed down judgement on 22nd June 2022. The Supreme Court held that [NAME_2] could seek imposition of code rights under Part 4 of the Code
3. The reference was thereafter remitted back to the Upper Tribunal and on 10th May 2024 Judge Cooke transferred the reference to the FTT. By that time the Respondent had transferred the [NAME_1] to its sister company, [NAME_10]. On 18th July 2024 the FTT added [NAME_10] as Second Respondent. In respect of the First Respondent the FTT directed:
“The First Respondent shall remain as a party to the Reference for the purpose of compliance with directions relating to disclosure and in respect of any residual costs to be determined post judgment.”
4. On 15th August 2024, following a case management hearing, the FTT ordered:
“The FTT will determine whether an agreement should be imposed under paragraph 20 of the Code by determining the following as preliminary issues:
3 (a) whether the Claimant can satisfy the first condition of paragraph 21 of the Code, namely: “that the prejudice caused to the relevant person by the order is capable of being adequately compensated by money”
(b) whether the Claimant can satisfy the second condition of paragraph 21 of the Code, namely:“…the public benefit likely to result from the making of the order outweighs the prejudice to the relevant person. in deciding whether the second condition is met, the court must have regard to the public interest in access to a choice of high- quality electronic communications services”
(c) whether the Second Respondent intends to redevelop all or part of the land to which the code right would relate, or any neighbouring land, and could not reasonably do so if the order were made.”
5. At a PTR held remotely on 4th September 2025 [NAME_10] withdrew Preliminary Issues (a) and (b). Accordingly, the only matter for remaining for determination is [NAME_21] intention to redevelop.
6. The remaining Preliminary Issue was heard in Birmingham on 29th September – 7th October 2025. [NAME_5] KC, [NAME_7] appeared for [NAME_2]. [NAME_12] KC, [NAME_13] and [NAME_16] appeared for [NAME_10]. We are grateful to [NAME_5] KC and Imogen Dodds for their Skeleton Argument on behalf of the Claimant dated 22nd September 2025 and to [NAME_12] KC, [NAME_13] and [NAME_16] for Second Respondent’s Skeleton Argument also dated 22nd September 2025. The Tribunal has considered Bundles of documents [ A 1-243, B 1-790, C 1-45, D 1-138, E 1-392, F 1-82, G 1-53 and H 1- 477].
7. The Tribunal received oral evidence from [NAME_22] (Acquisitions Director at [NAME_10] – Witness Statements dated 28th April 2025 [C17-24] and 27th August 2025 [C32-40]) and [NAME_25] (Head of Structural Design at [NAME_10] –Witness Statement dated 28th April 2025 [C25-31]). The Tribunal also received oral evidence from [NAME_81] (Head of Infrastructure at [NAME_2] –Witness Statements dated 28th April 2025 [C6-16] and 15th September 2025 [H12-15]). [NAME_30] (Asset Protection Manager for [NAME_2]) has made two Witness Statements (28th April 2025 [C2-5] and
4 27th August 2025 [C41-45). [NAME_30]’s evidence was agreed, and accordingly he did not give oral evidence at the hearing.
8. By Directions dated 15th August 2024 the FTT gave permission for parties to rely on expert evidence, one expert for each party, in the fields of planning and technical telecommunications. On 30th May 2025 the Tribunal ordered that the parties’ experts respond to questions.
9. The Tribunal received expert planning evidence from [NAME_33] (Panning Director at [COMPANY_35] – report dated 31st July 2024 [D81-121]) on behalf of [NAME_159] (Group Partner at [COMPANY_38] – report dated August 2025 [D48-80]) on behalf of [NAME_10]. Both planning experts gave oral evidence at the hearing. The planning experts have prepared a Joint Statement dated 2nd September 2025 [D122-138].
10. In respect of technical telecommunications [NAME_2] relies on the expert evidence of [NAME_39] (Head of Build and Construction at [COMPANY_41] – report dated 1st August 2025 [D15-42] and Supplementary Evidence dated 12th September 2025 [H6- 11]). [NAME_10] relies on the expert evidence of [NAME_42] (Director at [COMPANY_155] – report dated 31st July 2025 [D2-14]). The technical telecommunications experts have prepared a Joint Statement dated 1st September 2025 [D43-47].
The parties ultimately reached broad agreement on the technical evidence and neither Mr Head nor Mr [NAME_44] gave oral evidence at the hearing.
Conventions
[NAME_2] – Claimant [NAME_45] – parent company of [NAME_2] [NAME_10] – Second Respondent [NAME_46] - AP Wireless (UK) Limited; parent company of [NAME_10] and the First Respondent (AP Wireless II (UK) Limited)
5 [NAME_47] – [COMPANY_48]. overall parent company of [NAME_46] and [NAME_10] WIP – wholesale infrastructure provider The [NAME_1] [NAME_1] at Queen’s Oak Farm, [ADDRESS], Yardley Gobion, Towcester, Northamptonshire [POSTCODE] registered at HMLR Title Number NN329963 [B12-15] as shown edged red on the plan at [B17] The [NAME_2] [NAME_1] – edged blue on plan at [B385] The [NAME_2] – the existing 22.5m mast on the [NAME_2] [NAME_1] The [NAME_50] [NAME_1] – edged pink on plan at [B385] lying approximately 30m to the east of the [NAME_2] The [NAME_10] [NAME_1] – edged green on plan at [B385] lying approximately 100m to the east of the [NAME_2] mast [NAME_51] – [COMPANY_52] [NAME_53] – [COMPANY_54] [NAME_55] –[COMPANY_57] (merged with [NAME_53] to form [NAME_58] in 2025) [NAME_59] – [COMPANY_60] trading as [NAME_62] [NAME_65] ([NAME_51], [NAME_53], [NAME_55] and [NAME_59]) [NAME_66] – [COMPANY_67]. WIP, acting as agent at this [NAME_1] for [NAME_55] and [NAME_59] [NAME_68] Limited (agents for [NAME_51] and [NAME_53]) [NAME_4] – a sharer of the [NAME_2] mast on behalf of [NAME_149] (under its previous name of [NAME_4]) was a part of the [NAME_4] Group until 2021 when [NAME_2] was acquired by [NAME_45]. LPA –West Northamptonshire Council 2024 Prior Approval – relating to [NAME_21] proposed redevelopment of the [NAME_10] [NAME_1]. Granted on 2nd September 2024 2025 [NAME_21] revised redevelopment of the [NAME_2] [NAME_1] involving removal of the [NAME_2] and replacement with [NAME_21] own 25m mast. On 24th July 2025 LPA determined that Prior Approval was not required. Undertaking – a Unilateral Undertaking given by [NAME_10] to the LPA in connection with the 2025 Prior Approval
6 The [NAME_1]
11. [NAME_10] is the freeholder of the [NAME_1] at [NAME_70]. The [NAME_1] is a rural greenfield [NAME_1] a little over 1 km from the village of Yardley Gobion to the east and approximately 6 km from Towcester. The surrounding area is predominantly agricultural with scattered residential and commercial uses. The [NAME_1] extends to approximately 2,800 sq. m. The [NAME_1] is surrounded by agricultural fields and is accessed off a single track lane running from the nearby A5. Land to the north is in equestrian use beyond which is a menage. There is also a solar farm located to the north. To the south of the [NAME_1] is agricultural land beyond which is [COMPANY_71], [NAME_144]. To the west is a yard and buildings associated with [NAME_70]. To the east there is land laid to grass and a bund beyond which are a number of paddocks. The [NAME_1] is set well back from the A5.
12. The [NAME_2] [NAME_1] is at the southwestern corner of the [NAME_1]. The [NAME_2] is 22.5m in height. There is another mast (20m in height), approximately 30 m to the east of the [NAME_2] [NAME_1] which is operated by [NAME_50] who provide communications coverage to the emergency services.
Title
13. The [NAME_2] [NAME_1] comprises land demised by three leases granted in 1997, 2000 and 2005. By lease dated 14th January 1997 made between [NAME_72] and [NAME_160] (1) and Mercury Personal Communications part of the [NAME_2] [NAME_1] was demised for a term of 20 years from 21st October 1996 [B18-34]. The lease was assigned to [NAME_2] (at that time known as [COMPANY_77]) on 26th April 2000 [B35-44]. By a Supplemental Lease dated 11th December 2000 made between [NAME_78] (1) and [COMPANY_77] (2) an additional part of the [NAME_2] [NAME_1] was demised for the residue of the term [B53-58]. [NAME_2] acquired the final part of its [NAME_1] by a further Supplemental Lease dated 4th July 2005 again made between [NAME_78] (1) and [COMPANY_77] (2) [B79-86].
7 14. Each of the [NAME_2] were contracted out of 1954 Act protection. The contractual term expired on 20th October 2016. As held by Judge Cooke in her 2020 decision, [NAME_2] occupies the [NAME_2] [NAME_1] as a tenant at will.
15. The First Respondent acquired the freehold of the [NAME_1] by transfer dated 30th October 2014 [B87-95]. The First Respondent transferred the [NAME_1] to [NAME_10] by transfer dated 9th May 2024 [B96-102].
16. Accordingly, [NAME_10] is [NAME_2]’s landlord. The passing rent is £6,402.12 (exclusive of VAT), in addition to which the lease contains provisions for payaway at 30% of the net annual income received from third parties.
The [NAME_2] [NAME_1]
17. [NAME_2] is part of the [COMPANY_80]. [NAME_45] operates approximately 9,000 sites in the UK. [NAME_2] hosts all four [NAME_65]. [NAME_2] is an operator pursuant to a s106 OFCOM direction.
18. The [NAME_2] [NAME_1] measures 27.1m x 7.9m. The [NAME_2] infrastructure is used by [NAME_51], [NAME_53], [NAME_55] and [NAME_59]. The original mast at the [NAME_2] [NAME_1] was 15m in height and built around 1997. The present 22.5m mast was built in 2002 following grant of planning permission. [NAME_51] and [NAME_61] carried out upgrade works in 2022. [NAME_51] has deployed base 5G configuration for a rural [NAME_1] and [NAME_61] have implemented 5G capacity. There is no pending demand, in terms of customer enquiries, for new sharers.
19. [NAME_81], Head of Infrastructure at [NAME_2], explains in his Witness Statement that there are two maintenance regimes: Reactive Maintenance and Planned Preventative Maintenance. Greenfield sites are considered medium risk and are inspected every two years. Maintenance is carried out by Facilities Management Partner (MML), Inspection Partner (RJC) and Structural Engineering Partner (MITIE).
8 20. The most recent inspection in 2023/24 revealed “Latchway/other fall arrest – rusty washers will need replacing with new flats springs and nuts, have treated rust as a temporary measure”. By way of explanation the Latchway is a fall arrest system to ensure that the tower remains safe to climb. A new Latchway was installed in March 2023 [B191-193]. Surface corrosion, identified in 2023/24 was resolved by painting minor coatings over small outbreaks of surface corrosion. The next inspection is planned for October 2026. [NAME_82] considers the mast to be in good condition.
[NAME_21] intention to redevelop
21. [NAME_10] is an operator for the purposes of paragraph 2 of the Code pursuant to a s106 OFCOM direction. [NAME_10] is a WIP. [NAME_10] is part of the AP Wireless Group which is a subsidiary of [COMPANY_48]. [NAME_10] has approximately 50 sites across the UK.
22. [NAME_10] had not found a “sufficient driver” in terms of increase demand for services to develop the [NAME_1]. However, in 2024, following the “restart” of proceedings [NAME_10] became aware of “Telecommunications Infrastructure Calculation Report” prepared by [NAME_83] for [NAME_45] dated 9th August 2022 [B328-358]. The [NAME_83] report (although subsequently discredited) indicated that as the mast was constructed in 1996 and was coming to the end of its estimated 30 year lifespan.
Accordingly, [NAME_10] identified a redevelopment opportunity.
23. [NAME_10] considered three potential redevelopment schemes. The first was to redevelop the [NAME_2] [NAME_1]. This is known as “going over”. The second scheme involved redeveloping the [NAME_50] [NAME_1]. The third option was to build a new [NAME_10] [NAME_1] about 100m to the east of the [NAME_2] [NAME_1].
24. [NAME_21] preferred development was to redevelop the [NAME_2] [NAME_1] as that would “maximise the likelihood of the [NAME_84] coming to our new mast.” However, the legal advice received by [NAME_10] was that “going over” the [NAME_2] [NAME_1] would not satisfy the legal test for redevelopment. Accordingly, [NAME_10] applied for planning permission to
9 build on the [NAME_10] [NAME_1] 100m to the east of the [NAME_2] [NAME_1]. The 2024 Prior Approval was granted on 2nd September 2024 [B111-112].
25. Following the handing down of the decision in Vodafone Limited v Icon Tower Infrastructure Limited (1) and AP Wireless II (UK) Limited [2025] UKUT 00058 (LC) (“[ADDRESS]”) on 20th February 2025 the legal advice given to [NAME_10] was revisited. [NAME_10] was advised is that “going over” the [NAME_2] [NAME_1] would be sufficient for redevelopment under the Code. On 3rd March 2025 the [NAME_85] approved a change of strategy [B470-472].
Accordingly, [NAME_21] decided to construct a new 25m tower on the [NAME_2] [NAME_1] which would require the removal of the [NAME_2]. [NAME_10] obtained the 2025 Prior Approval to proceed on 24th July 2025 [B178-179].
26. On 4th August 2024 [NAME_46] agreed to fund the redevelopment [B473-474]. The [NAME_107] approved the business case on 21st August 2025 [B449-450] and on 22nd August 2025 the [NAME_10] Board resolved to proceed with the redevelopment [B475-476]
Planning
27. We are grateful to [NAME_7] and [NAME_13] of counsel, who attended various parts of the hearing, for their assistance in respect of planning matters.
2024 [NAME_10] [NAME_1]
28. Prior approval was granted on 2nd September 2024 by the LPA (application number 2024/3540/PA) in respect of the following development [B111-112]:
“The installation of new sharable 25m lattice mast, which is collocated with 1no. existing compound approximately 55m to the west and 1no. existing compound approximately 100m to the west. The development will include a base station, 2.4m high palisade fencing, 6no. operator cabinets, 1 no. meter cabinet, 6no. antennas and ancillary development thereto”
10 29. The application was recommended for approval as the [NAME_1] is a long way back from the A5 and would not appear overly prominent. The [NAME_1] is outside a conservation area. The ICNIRP certificate was acceptable to Environmental Health and there were no neighbour objections (see Delegated Report [B113-116])
2025 [NAME_2] [NAME_1]
30. By application received on 16th May 2025, [NAME_10] sought prior approval for “going over” the [NAME_2] [NAME_1]. On 24th July 2025 the LPA (application number 2025/2005/PA) determined that prior approval was not required [B178-179] in respect of:
“The removal of existing 22.5m lattice mast and associated compound, and installation of 1no. lattice sharable mast (height 25m), antennas installed on headframes, operator cabinets & a multi-user electrical cabinet.”
The Unilateral Undertaking
31. The 2025 Prior Approval application was accompanied by a Unilateral Undertaking dated 27th May 2025 [B140-154]. Developer Covenants are set out at Schedule 1 to the Undertaking [B146]:
Developer Covenants
1. The Developer undertakes to the Council not to Implement the Original Prior Approval in the event that the Prior Approval relating to the Development as specified in the Prior Approval Application is granted and Implemented.
2. The Developer undertakes to the Council not to Implement the Prior Approval in the event that the Original Prior Approval has already been Implemented.
32. The decision of 24th July 2025 of the LPA was made under delegated powers in accordance with a Delegated Report prepared by a planning officer dated 22nd July
11 2025 and authorised on 24th July 2025 [B180-185]. That report expressly took the Undertaking into account as a material planning consideration (see paragraphs 9.5, 9.6 and 9.11).
“To this end, the applicant has provided a Unilateral Undertaking that confirms if this application is approved then the mast approved in 2024 (ref: 2024/340/PA) would not be installed on the [NAME_1], ensuring that there would only be two masts on [NAME_1]. Whilst this is a material consideration, this is a legal matter and would fall outside the realms of planning, however, the submitted plans for this application would supersede the previous application and such a development would unlikely be unimplementable.” (paragraph 9.5) [B183]
“Based on the fact this is an existing [NAME_1] used for telecommunications masts, the replacement mast is only 2.5m taller and the applicant has submitted a unilateral undertaking to ensure the mast granted permission under 2024/3540/PA is not installed. A 2.5m increase in height is not considered to have a material impact in visual terms and the increase would not be overly obvious. In any case a replacement mast of 25m is considered acceptable under the regulations.” (paragraph 9.6)
“It should be noted that the application for prior approval is made under Schedule 2, Part 16, Class A of the GPDO which sets out specific criteria against which applications for telecommunication mast and installations are assessed against. In this case the application is in effect a replacement of an existing mast which is 2.5m taller at 25m Schedule 2, Part 16, Class A allows for masts up to 25m, the application for a similar mast on a location nearby was granted last year for a mast of the same height and was considered acceptable. This application is supported by a Unilateral Undertaking that states in the event this current application is permitted and installed, the mast granted permission under 2024/3540/PA will not be implemented, thus preventing an over proliferation of masts on this [NAME_1].” (paragraph 9.11) [B184]
12 Joint Planning Statement
33. The parties planning experts [NAME_33] and [NAME_36] have prepared a Joint Statement dated 2nd September 2025 [D122-138]. The following determinative issues are agreed:
(1) [NAME_10] has obtained the 2025 Prior Approval (to the effect that prior approval was not required). No further planning permissions are required (Question 2 [D131])
(2) There is no planning impediment to [NAME_10] proceeding with the construction of its proposed 25m mast (Question 8 [D133])
(3) It is necessary to remove the mast currently in situ on the [NAME_2] [NAME_1] in order for [NAME_10] to construct its proposed 25m mast (Question 7 [D133]).
34. By the date of the hearing the parties had narrowed the planning issues remaining in dispute:
(1) There is no (relevant) conflict of opinion between experts on Q1, 2 and 5 - 10, and therefore no determination is needed by the Tribunal on those questions.
(2) There is a relevant conflict of opinion between the experts on Q3, 4 and Q11
Questions 3 and 4 – the Unilateral Undertaking and the 2025 Prior Approval
35. Question 3: What is the effect, if any, on the prospects of [NAME_10] obtaining Prior Approval for the new 25m mast pursuant to the [NAME_1] Application with the Proposed Undertaking?
Joint Statement:
The UU had a positive effect on the prospects of [NAME_10] obtaining the 2025 Prior Approval.
13
The experts agree that the UU had a positive effect on the prospects of [NAME_10] obtaining the 2025 Prior Approval but disagree on the importance of the UU in the Council’s decision-making process. [D132]
36. Question 4: What is the effect, if any, on the prospects of [NAME_10] obtaining Prior Approval for the new 25m mast pursuant to the [NAME_1] Application without the Proposed Undertaking?
Joint Statement:
It is agreed that the 2025 Prior Approval would, in all likelihood, have been granted. However, it is acknowledged that the decision would have been more finely balanced in the absence of the Unilateral Undertaking (UU).
Without the UU, the siting and appearance of the proposed mast would have constituted a materially weaker case.
The 2024 Other [NAME_1] establishes the acceptable principle of accommodating three masts within the field within which the 2025 [NAME_1] is located.
The experts agree that it is likely the 2025 [NAME_1] Application would have been granted without the UU.
There is disagreement between the experts on the importance of the UU in the decision making process of the Council, specifically with regard to the amount of positive weighing that may have been attributed to the UU in the Council’s planning balance exercise in determining the [NAME_1]. [D132]
37. The expert opinion of [NAME_21] planning expert, [NAME_36] is the Undertaking constitutes a planning benefit which mitigates cumulative impacts and proliferation of masts in accordance with NPPF Paragraph 120:
14 “The number of radio and electronic communications masts, and the sites for such installations, should be kept to a minimum consistent with the needs of consumers, the efficient operation of the network and providing reasonable capacity for future expansion. Use of existing masts, buildings and other structures for new electronic communications capability (including wireless) should be encouraged. Where new sites are required (such as for new 5G networks, or for connected transport and smart city applications), equipment should be sympathetically designed and camouflaged where appropriate.”
38. [NAME_33], [NAME_2]’s planning expert, is of the opinion that Undertaking was not strictly necessary for approval of the application and in [NAME_86]’s opinion the 2025 Prior Approval would have been granted without the Undertaking. In particular the grant of the 2024 Prior Approval demonstrates that even a third mast would be consistent with NPPF paragraph 120. The LPA decided in 2024 that three separate masts at [NAME_70] was acceptable in terms of “siting and appearance”.
39. The Undertaking is not referred to within the Decision Notice. It is however referred to in paragraphs 9.5, 9.6 and 9.11 of the Officer’s Report. Paragraph 9.5 is problematic. The following sentence is poorly expressed and contains an erroneous double negative:
“Whilst this is a material consideration, this is a legal matter and would fall outside the realms of planning, however, the submitted plans for this application would supersede the previous application and such a development would unlikely be unimplementable” [B183]
Clearly the officer was satisfied that the Undertaking was a material consideration. However, the officer has failed to appreciate the legal effect of the Schedule to the Undertaking. The effect of the Undertaking on the 2024 Prior Approval is that although it remains valid it is no longer capable of implementation at the same time as the 2025 Prior Approval. [NAME_10] can proceed under the 2024 Prior Approval or the 2025 Prior Approval but not both. The Undertaking provides for an either/or approach. It does not have the legal effect of rendering the 2024 Prior Approval “unimplementable”.
15 40. We find that the Undertaking was a material consideration in the decision making process. It was a good planning strategy and increased [NAME_21] prospects of success. However, we find that lower weight should be accorded to the Undertaking as a planning benefit. At the time that the application was considered [NAME_10] already had the 2024 Prior Approval which potentially allowed for 3 masts at the [NAME_1] namely: the [NAME_10] [NAME_1], the [NAME_2] [NAME_1] and the [NAME_50] [NAME_1]. Siting and appearance were considered acceptable and consideration given to proliferation of masts. Whilst in the planning world the officer seems to have accepted that the 2025 Prior Approval would reduce the number of masts and therefore deliver a planning benefit the legal effect of the Undertaking was an either/or approach which meant that [NAME_10] could still implement the 2024 Prior Approval resulting in 3 masts at the [NAME_1].
Question 11 – [NAME_2] rights
41. Question 11: What, if any, permitted development rights does [NAME_2] currently enjoy in respect of its current installation?
Joint Statement
It is agreed that rights are granted under Part 16 of the Town and Country Planning (General Permitted Development) (England) Order 2015, as amended.
Under these rights [NAME_2] is entitled to undertake various forms of development, including (but not limited to) and also noting that there are conditions and criteria to comply with: • The installation, alteration, or replacement of electronic communications apparatus, including antennae and equipment cabinets; • The installation of additional antennae on existing masts; • The installation of equipment cabinets, provided they do not exceed 2.5 cubic metres in volume, particularly when located outside designated compounds; • The installation or replacement of a mast, where the mast (excluding antennae) would not exceed: •30 metres above ground level on unprotected land; or
16 •25 metres above ground level on Article 2(3) land or land which is on a highway; • The alteration or replacement of a mast, provided the new mast does not exceed the greater of the existing height or the above limits; • The installation of antennas on buildings, subject to various factors; • The installation of apparatus on masts, provided the total height (mast + apparatus) does not exceed the relevant limits; • Minor ancillary works reasonably necessary for the operation of the apparatus;
There is agreement between the experts that [NAME_87] enjoy permitted development rights at the [NAME_1].
There is limited agreement on the extent of the use of these rights, specifically with regards to where a replacement mast can be situated and still qualify as permitted development. [D134-135]
42. Planning permission for telecommunications sites is granted as permitted development by the General Permitted Development Order (“GDPO) under Class A of Part 16 of Schedule 2 to the GDPO:
“Development by or on behalf of an electronic communications code operator for the purpose of the operator’s electronic communications network in, on, over or under land controlled by that operator or in accordance with the electronic communications code, consisting of—
(a) the installation, alteration or replacement of any electronic communications apparatus …”
43. The grant of planning permission under Class A of Part 16 is subject to conditions and limitations. For present purposes a summary will suffice:
Mast up to 25m - outright permitted development subject to certain limitations on the width of the design. An operator is required to give a Code Notification to the LPA under Regulation 5 of the Electronic Communications Code (Conditions and Restrictions) Regulations 2003
17 Mast between 25m and 30m – prior approval of LPA required Mast above 30m – full planning permission required
44. The requirement for prior approval of LPA is set out in paragraph A 3(4) of Part 16 of Schedule 2 to the Town and Country Planning (General Permitted Development) (England) Order 2015 (“the GPDO”):
“Before beginning the development described in paragraph A.2(3), the developer must apply to the local planning authority for a determination as to whether the prior approval of the authority will be required as to the siting and appearance of the development.”
45. [NAME_33] ([NAME_2]’s planning expert) relies on the absence of any controls in Part 16 as to where the replacement mast may be located (see paragraphs 116-123 of his Expert Report [D117-119]. He contrasts this with the position in Scotland which provides that Permitted Development Rights do not apply where “the replacement mast would be situated more than 6 metres from the location of the original mast”. The Code of Practice for Wireless Development in England merely refers to the situation where “the existing coverage and capacity will be removed and as such a replacement [NAME_1] is needed within close proximity to where the existing [NAME_1] was located.” [NAME_86]’s approach is that the location of a replacement mast should be considered in the context of coverage and capacity. In his expert opinion it is the cell area which is the relevant geographic restriction. The purpose of the replacement is to provide coverage to the same customers in the same cell area. The current [NAME_2] mast provides coverage for local demand at the A5 road network, the villages of Yardley Gobion and Alderton as well as the collection of buildings at [ADDRESS] including the school. However, [NAME_86] accepts that his approach is not set out in the GDPO. In practice his approach has been accepted by a number of LPA’s. Nevertheless, [NAME_86] accepts “LPAs will interpret the GPDO differently. Some may accept the above interpretation of permitted development rights whilst others, not.” [D119]
46. [NAME_36] ([NAME_88]) accepted that [NAME_2] may wish to exploit the vagueness of the GDPO in respect of location of a replacement mast to its commercial
18 advantage. However, the requirement to give a Code Notification under Regulation 5 would undoubtedly raise alarm bells with the LPA. The LPA would want to understand further what was being proposed as outright development and would undoubtedly be concerned about proliferation and NPPF 120.
47. There is also a timing issue. Once the [NAME_2] mast has been removed and decommissioned [NAME_2] would lose any rights it may have in respect of replacement. In those circumstances [NAME_2] would be seeking to install a new mast. There is a clear distinction in the GDPO between the erection of a new mast and replacement of an existing mast. Prior approval would therefore be required for a new mast following decommissioning of the [NAME_2] [NAME_1].
48. We find that [NAME_2] only has outright permitted development rights for a replacement mast at the existing [NAME_2] [NAME_1]. [NAME_86]’s cell based approach is not supported by the GDPO and carries significant risk of being rejected by the LPA on receipt of a Regulation 5 Code Notification. We find that any replacement mast other than at the [NAME_2] [NAME_1] would require Prior Approval. In any event [NAME_2] could only erect a replacement mast prior to decommissioning of its existing mast. A new mast on another [NAME_1] would require Prior Approval.
49. [NAME_2] does not have outright permitted development rights other than in respect of a mast up to 25m at the existing [NAME_2] [NAME_1] prior to decommissioning. Any other replacement or new mast will require Prior approval. Any replacement or new mast above 30m will require full planning permission.
The Masts - Technical Telecommunications Experts
50. The parties’ respective experts have prepared Joint Expert Technical Statement dated 1st September 2025 setting out the parties’ respective positions in respect of Questions to Experts ordered by the Tribunal [D43-47].
51. As regards technical evidence, the parties are agreed that:
19
(1) Neither party will be calling the technical telecommunications experts. (2) Neither party will be relying on any part of the technical experts’ evidence which is not agreed. (3) Insofar as there are differences between the experts, the FTT need make no findings about them.
52. [NAME_2]’s mast is a 22.5m high modular design, open lattice structure. It is a [ADDRESS] Millenium New (SSTMN) designed by [COMPANY_77] (the former name of [NAME_2]). The current ECA is mounted on the upper headframe. The lower headframe is not in use. The current concrete foundation is 6.5m x 6.5 m and approximately 1.0m-1.2m deep. The mast is constructed of 112mm x 112mm x 10 mm galvanised steel angle. [NAME_2]’s mast provides coverage for local residential properties including [COMPANY_71]. The mast serves the broader area of the A5 transport corridor and the surrounding villages of Yardley Gobion, Potterspury, Paulerspury and Puxley. Typically, in rural areas signal travels up to about 4 miles.
53. [NAME_21] proposed tower is a 25m Swann 5SH lattice tower. It will sit on a 6.4m x 6.4 m x 1.0m concrete base within a 10m x 10m compound. The tower has two headframes capable of carrying between them 4 operators with 6 antenna and 18 RRU each plus two microwave dishes. The proposed tower has been analysed with that equipment load for a wind speed of 25 m/s at a hill height of 100m AMSL. The windspeed for the [NAME_1] is around 21.5 m/s and the hill height is 100m AMSL.
54. The agreed conclusions of [NAME_39] and [NAME_42] are [D44-47]:
[NAME_21] proposed new 25m mast can accommodate the existing ECA at the [NAME_1] and any future upgrades – Q1 The experts are not wholly aligned as to whether there any material difference in capacity between the [NAME_87] and [NAME_21] proposed mast – Q2 It is a reasonable assumption that the OT Mast (and the ECA installed thereon) currently facilitates network coverage – Q3
20 The likely timescale of building a mast on the [NAME_10] [NAME_1] pursuant to the 2024 Prior Approval is from 12 weeks for completion of naked tower to 9 months to include for rigging works, power and transmission – Q4 There is no technical reason why [NAME_10] could not build and operate a mast on the [NAME_10] [NAME_1] pursuant to the 2024 Prior Approval with the [NAME_87] remaining in situ and continuing to support active ECA – Q5 The likely timescale for [NAME_10] building its new mast on the [NAME_2] [NAME_1] pursuant to the 2025 Prior Approval is a total timescale of 12 weeks at best if re- using the existing base through to approximately 26 weeks if the foundation/base needs replacing and full decamp to temporary sites is not accepted by the [NAME_65] – Q6 Likely impact on [NAME_65] – Q7
o [NAME_10] [NAME_1] – 2024 Prior Approval New ECA & transmission - No impact on network. Moving existing ECA & transmission – Single outage up to 4 days impact on network. New ECA & reuse of transmission – Single outage up to 2 days impact. o [NAME_2] [NAME_1] – 2025 Prior Approval Temporary mast required. Two outages (onto temporary mast and back to replacement tower). Total outage duration to utilise existing ECA – up to 9 days impact on network (5 days & 4 days). New ECA & transmission is provided for temporary mast and replacement tower - No impact on network. o Replacement alternative [NAME_2] mast nearby New ECA & transmission - No impact on network. Moving existing ECA & transmission – Single outage up to 4 days impact on network. New ECA & reuse of transmission – Single outage up to 2 days impact on network.
21 The Law
55. Paragraph 21(5) of the Code provides:
“The court may not make an order under paragraph 20 if it thinks that the relevant person intends to redevelop all or part of the land to which the code right would relate, or any neighbouring land, and could not reasonably do so if the order were made.”
56. In reaching our decision we have been greatly assisted by the decision of the Chamber President, Mr [NAME_89] TD MRICS in [ADDRESS]. That decision covers many of the legal issues arising before us. However, this Tribunal is not bound by what was said by the Upper Tribunal in making findings of fact. It is trite law that findings of fact are inadmissible in subsequent proceedings (Rogers v Hoyle [2015] Q.B. 265).
57. The Upper Tribunal considered Paragraph 21(5) in [COMPANY_52] and [COMPANY_145] v [NAME_92] and others as Trustees of the 1968 Combined Trust of [NAME_94] Estate Management [2019] UKUT 164 (LC) (“[NAME_94]”). At [38 and 39] the Upper Tribunal explained the approach to be taken to arguments based on the redevelopment provisions set out in the 1954 Act:
“38. Paragraph 21(5) was explicitly modelled, by the Law Commission, on s.30(1)(f); the difference in wording is trivial and is dictated by its context (see [32] above). However, we agree with Mr [NAME_95] QC that the case law associated with s.30(1)(f) is not binding authority in the context of the Code and of para.21(5). Clearly the Code, new as it is, must be looked at with a clean slate and as a fresh start. The principles applicable to the 1954 Act should be adopted where they are relevant, although we are mindful of the need to be aware of the different context in Code cases. Not all principles will be relevant and the factual background will have an effect on this; issues of timing, for example, need to be carefully considered. But we accept (as the respondents themselves argue) that where intentions have changed over time it is the intention at the date of the hearing that is relevant: Betty’s Cafes Ltd v Phillips Furnishing Stores Ltd [1959] A.C.
20. And it makes obvious sense to adopt the test imposed in [NAME_96]. Parliament’s intention would be frustrated if the defence in
22 para.21(5) could be made out where the relevant person did not have a firm intention to carry out the redevelopment plan, or where the plan was not something that that person has a reasonable prospect of being able to bring about of their own volition.
39.The test in [COMPANY_97] is likewise equally relevant…”
58. The same approach was adopted in [ADDRESS] at [233]:
“Applying this approach, it seems to us that it is legitimate to consider authorities on Paragraph (f), in relation to Paragraph (c), subject to keeping in mind that the principles applicable to the 1954 Act should only be adopted where they are relevant. One principle which does seem to us to be relevant is the following statement of Balcombe LJ in Palisade Investments Ltd v Collin Estates Ltd [1992] 2 EGLR 94, at 97D, as quoted by Auld LJ in his judgment in Dolgellau Golf Club v Hett [1998] L.&T.R. 217 at page 228 of the report:
"…. the Act was intended to be construed sensibly, so as to hold a fair balance between landlord and tenant. It is not…., to be construed so as to create a series of artificial hoops through which the landlord must jump before he must satisfy the necessary intention."
59. In [NAME_94] the Upper Tribunal adopted a two stage test for redevelopment [40] (following Cunliffe v Goodman [1950] 2 KB 237):
“Accordingly, whether the Respondents wish to build a mast or a housing estate, they can resist the Claimants’ application only if they can demonstrate both that they have a reasonable prospect of being able to carry out their redevelopment project and that they have a firm, settled and unconditional intention to do so.”
60. The two-stage test was confirmed in [ADDRESS] [279]:
“The test is very well-known and has been restated many times. There are two parts to the test, as it applies to Paragraph (c). The first part of the test is subjective. The [NAME_1] provider has to prove a firm and settled intention to carry out the relevant work
23 of redevelopment, which is not likely to be changed. The second part of the test is objective. The [NAME_1] provider has to prove a reasonable prospect of being able to bring about the relevant redevelopment by their own act or volition.”
61. It is common ground that [NAME_10] bears the burden of establishing the relevant intention under Paragraph 21(5). The principle was recently restated by Norris J (sitting in retirement) in MVL Properties (2017) Limited v The Leadmill Limited [2025] EWHC 349 (Ch.) at [10a]:
“The burden lies upon [NAME_98] to establish that it has the relevant intention: Cunliffe v Goodman [1950] 2 KB 237 at 254. Leadmill does not have to prove anything. Leadmill merely has to raise challenges which call for an answer from [NAME_98] in order that it may discharge the burden which lies upon it.”
62. Where intention has changed over time it is the intention at the date of the hearing that is relevant: Betty’s Cafes Ltd v Phillips Furnishing Stores Ltd [1959] AC 20 (see [38] of [NAME_94]). [ADDRESS] [282] the Upper Tribunal confirmed:
“This date is often referred to as the date of the relevant hearing held to determine whether the intention exists but it is, strictly, the date on which this question comes to be determined by the relevant court or tribunal; see the speech of Lord Denning in Betty’s Cafes Ltd v Phillips Furnishing Stores Ltd [1959] AC 20, at page 51 of the report.”
63. There are five issues for us to determine:
(1) Subjective test - intention (2) Objective test - reasonable prospects (3) Conditional intention – (S Franses v Cavendish Hotel (London) Limited [2018] UKSC 62 (“[COMPANY_97]”) (4) Reasonable time (5) The meaning of redevelop
Before determining those issues, we consider the evidence of the witnesses.
24 Evidence of [NAME_22]
64. [NAME_10] first looked at redevelopment opportunities at [NAME_70] in 2022. At that time there was no business case to upgrade infrastructure. In his evidence [NAME_99] told us that having regard to the rural nature of the [NAME_1] and the quality of the tower the [NAME_1] was not a good redevelopment opportunity. No coverage drivers were identified in terms of new housing or local infrastructure projects. At that time [NAME_10] reviewed the [NAME_46] portfolio of some 4,040 sites. As a result, 948 sites were identified as having potential, 170 sites got planning permission and 6 were built. [NAME_70] was not one of the 948 sites identified in 2022 as having potential. As [NAME_100] put it in cross examination at that time [NAME_70] ranked below 948th in the list. [NAME_10] had no intention to redevelop the [NAME_1] in 2022.
65. The potential of the [NAME_1] was revisited in 2024. [NAME_99] was very clear that the decision to look again at the [NAME_1] came from [NAME_46]’s lawyers. The Supreme Court had remitted the ongoing litigation back to the Upper Tribunal and the case was, to use [NAME_99]’s phrase “restarting”. There is no documentary evidence of what was said by the [NAME_46] lawyers, but [NAME_99]’s recollection was that most likely he was contacted by telephone.
66. The decision to look again was initiated by [NAME_46] lawyers in 2024 as a result of obtaining a “Telecommunications Infrastructure Calculation Report” dated 9th August 2022 prepared by [COMPANY_101] which had been prepared at the request of [NAME_45] [B328-358]. The report suggested that the [NAME_2] was nearing the end of its estimated 30 year life span. However, at the hearing [NAME_99] confirmed that it was now accepted by [NAME_10] that the [NAME_83] report was inaccurate and “discredited”. The report confirms the [NAME_2] as “Structure: ok” [B353].
67. In cross examination [NAME_99] was asked why [NAME_70] had been fast tracked. [NAME_99] described the decision as “obvious”. [NAME_46] owned the freehold of the [NAME_1] and tower was at the end of its life. [NAME_10] decided to “get cracking on”.
Accordingly, [NAME_10] decided that it would build the [NAME_1] out as the rent proposed by [NAME_2] in the litigation was only £1750 p.a. In fact, it does not appear that an offer of £1750 p.a. was actually made by [NAME_2]. That figure is the likely outcome of the reference based on the code rent for a greenfield [NAME_1], absent alternative use value, as determined by the
25 Upper Tribunal in Vache Farm. In any event [NAME_99] was clear that based on a rent of £1750 p.a. and allowing for inflation at 3% [NAME_10] would never recover its capital outlay.
68. [NAME_99] explained that [NAME_10] approaches redevelopment in three initial phases: (1) acquisition, (2) design and (3) planning.
69. In his First Witness Statement at Paragraph 23 [C20] [NAME_99] explains [NAME_21] criteria at stage (1) acquisition:
“[NAME_10] looks to identify opportunities/new portfolio sites by:
1. reviewing sites in the [NAME_46] portfolio which have additional vacant land next to the mast [NAME_1] which can be used for the provision of improved infrastructure. This provides us with a speed to market as [NAME_10] can avoid the acquisition stage and go straight to the planning permission stage; 2. reviewing sites in the [NAME_46] portfolio without additional land but where the existing operator’s passive infrastructure on the [NAME_1] is deemed to be limited. We would look to offer the [NAME_65] improved infrastructure (by way of a more sustainable [NAME_1] that can accommodate additional sharers and upgrades over a long period of time for improved coverage and capacity); and 3. considering sites which are not currently in the [NAME_46] portfolio where the existing operator’s passive infrastructure on the [NAME_1] is deemed to be limited and looking to offer the [NAME_65] improved infrastructure and therefore a more sustainable [NAME_1] that can accommodate additional sharers and upgrades”
Criteria 1 applied to [NAME_70] as there was additional vacant land. The [NAME_1] had already been acquired by [NAME_46] in 2014 for £175,000 [B87-95]. Phase (1) was completed when the [NAME_1] was transferred to [NAME_10] on 9th May 2024 for £96,780.09 [B96- 102].
70. Phase (2) began with a [NAME_1] dated 17th May 2024 [B496]. That document records:
26 “We need measurements for the two existing demises ([NAME_45] - to the east of the land and [NAME_50] in the middle). We then need a new demise to be marked out to the west of the land that needs to be at least 30m away from any of the other structures as not to interfere with signal.”
Accordingly, all three sites, the [NAME_10] [NAME_1], the [NAME_50] [NAME_1] and the [NAME_2] [NAME_1], were in play. As [NAME_99] told us “we hedged our bets at that stage”.
71. [COMPANY_102] was instructed on 22nd May 2024 [B415] and prepared a report dated 11th June 2024 [B386-414] producing “panoramic photographs [are] to provide the authority’s radio team with the assurance that the proposed [NAME_1] antenna locations are clear from any immediate clutter and to assist in the final selection of the antenna parameters such as heights and orientations.”
72. [NAME_10] carried out an MSV Survey on 11th June 2024 [B538-545] which covered the [NAME_10] [NAME_1] and [NAME_50] [NAME_1] [B543] and also the [NAME_2] [NAME_1] [B544].
73. Phase (3) was initiated by a decision to instruct planners on 5th July 2024 [B556]. At that stage [NAME_10] were still pursuing the [NAME_10] [NAME_1] – “there are two existing masts in the same field but we are going to be 30m away from both”. [NAME_99] told the Tribunal that [NAME_21] preferred option was to redevelop the [NAME_2] [NAME_1] but “didn’t think legally we could do that”. Accordingly in 2024 the only proposal that was being progressed was the [NAME_10] [NAME_1].
74. Planning application for the [NAME_10] [NAME_1] was made by [NAME_21] planning agents [NAME_104] on 12th July 2024 [B109-110]. The application was received by the LPA on 17th July 2024 and granted on 2nd September 2024 [B111-112]. [NAME_104] informed [NAME_99] and others of the LPA decision on the same day [B585]. The following day, 3rd September 2024, [NAME_104] confirmed that the Prior Approval related to “additional mast alongside the other two” [B608].
75. Following grant of Prior Approval costs for the redevelopment were estimated at £192,586.23 [B612]. Based on those costs [NAME_99] prepared a business plan [B678].
27 [NAME_10] refers to its business plan as a Tower Return Model (“TRM”) as explained by [NAME_99] at paragraph 19 of his Second Witness Statement [C34]:
“The Tower Return Model is a standard document with pre-populated formulas which we input figures into. This includes budget build costs and expected rental income to see if we want to progress with the investment. If the investment provides a worthwhile return, we complete a SCIP ([NAME_1]) and submit it to the Board for approval.”
Crucial to the TRM is the Internal Rate of Return (“IRR”):
“However, if the SCIP involves an existing [NAME_46] asset (including one which was previously acquired by [NAME_46] albeit now vested in [NAME_10]), we have to first ask the Underwriting Team to provide a blended figure for IRR before we complete a SCIP, as we must include the original transaction in our calculation, to provide an accurate return.”
In his evidence [NAME_99] explained that the IRR is based on costs of the redevelopment, period of return and rental income blended for acquisition costs. Taking a cautious approach [NAME_99] included a degree of “fat” in the budgeted costs. The Tribunal notes that whilst IRR is an entirely standard analysis tool it is usual to use other metrics as well which consider external factors which may impact on ultimate return.
76. [NAME_99] was very clear in his evidence that the proposed redevelopment was investment led and based on rates of return. At paragraphs 15 and 16 of his First Witness Statement dated 28th April 2025 [C18-19] [NAME_99] explains that the [COMPANY_105] continues to look to maximise its current investments and that [NAME_21] objective is to provide a long term investment for its overall parent company [NAME_146]. When asked about parameters for acceptable rates of IRR, [NAME_99] conceded that there was in fact no minimum level of IRR for the purposes of Board approval. [NAME_10] has built towers speculatively to show that it can do so, for marketing purposes. As a start-up [NAME_10] are trying to break into the market and “do not have parameters” in contrast to other parts of [NAME_46]. Despite the figures provided in TRM, SCIP and IRR the Board, in
28 effect, makes “a judgment call”. [NAME_100] asked [NAME_99] if [NAME_70] was a speculative build. [NAME_99] confirmed that [NAME_70] was not a speculative build.
78. On 20th February 2025 the Upper Tribunal handed down its judgement in [ADDRESS]. The [NAME_85] acted with alacrity and on 3rd March 2025 [B470-472]:
“[NAME_10] will review all Sites within litigation that are subject to renewal pursuant to the Code to determine whether there is a further ability for redevelopment as a result of the Steppes Judgment. In particular [NAME_10] should:
i. Look at any redevelopment opportunities that go over the top of the current operators compound as this has now been confirmed to be a viable legal position for a WIP to take ii. Where there is a viable option on a [NAME_1], [NAME_10] should submit a planning application to go over the top of a [NAME_1]; iii. If planning permission has already been obtained on a neighbouring piece of land, [NAME_10] should submit a second planning application and provide the necessary documentation to local planners to ensure that one of the planning applications (as opposed to both) are implemented.”
79.
Accordingly, [NAME_10] changed its plans. On 3rd April 2025 [NAME_10] instructed [NAME_103] that they intended to proceed to build over the [NAME_2] [NAME_1] [B706]. When asked about [NAME_21] change of plan, [NAME_99] agreed that [NAME_21] motivation was to get [NAME_2] off the [NAME_1]. [NAME_99] very candidly accepted that [NAME_21] motivation was “to remove competition off our land.” However, in his Second Witness Statement dated 27th August 2025, at paragraphs 34 and 35, [NAME_99] explains that there is very little difference in the budgeted costs for the TRM at the [NAME_10] [NAME_1] under the 2024 Prior Approval and the TRM for the [NAME_2] [NAME_1] under the 2025 Prior Approval. The advantage of ensuring the best chance of [NAME_65] migrating to the new [NAME_10] tower outweighed the negligible costs differences [C37-38].
80. On 1st May 2025 [NAME_104] made a further planning application [E208 -209] and [B133 - 137]. Objections were received from [NAME_4] [B781] and [NAME_45] [B774-780 and H85-
29 86]. On 24th July 2025 the LPA determined that Prior Approval was not required [B178-179].
81. [NAME_99] explained that [NAME_10] accepted that its revised proposal of “going over” the [NAME_2] would cause significant disruption to [NAME_106].
Accordingly, [NAME_10] decided that inducements should be offered to [NAME_65]. [NAME_99] told the Tribunal that incentive was initially £35,000 in total. On 4th August 2025 the [NAME_85] met to discuss [NAME_70] following the granting of 2025 Prior Approval [ B473-474]:
The Board was prepared to offer certain inducements at the [NAME_1] to attract operators. A revised set of figures, showing the proposed inducements and their impact on the investment return, would need to be prepared and submitted to the [NAME_107] as part of a tower submission call. Once approved, the Company would provide the necessary funding to [NAME_10] to build the [NAME_1] once vacant possession is obtained.
The Board resolved:
The board were happy to commit to the investment for [NAME_10] to redevelop the [NAME_1] at [NAME_70]. The Company will provide the funding subject to the submission and approval of a SCIP to show the impact of any proposed inducements on the investment return.
82. The TRM is a living document which is constantly updated. The last iteration of the TRM is dated 21st August 2025 [B441] and shows revised costs of £201,697. Return Analysis is based on:
[NAME_51] - £12,500 p.a. [NAME_66] - £12,500 p.a. [NAME_69] - £5,000 p.a.
[NAME_99]’s analysis works on three “carriers” – [NAME_51] ([NAME_51] and [NAME_53] combined), [NAME_66] ([NAME_55] and [NAME_59]) and [NAME_69]. This reflects the fact that at the [NAME_1] [NAME_51] and [NAME_53] share transmission equipment and [NAME_55] and [NAME_59] share antennas.
30
We are satisfied that [NAME_99]’s estimated returns are correct. [NAME_10] has not spoken to [NAME_84] it has a good idea of the present rents paid by the carriers. This is because the existing [NAME_2] agreement provides for “payaway” of the amounts received from sharers. [NAME_99] said that he had discounted any income from [NAME_50] because the emergency service contract had long since expired and, for investment purposes, future income could not be assumed beyond the next 2 or 3 years.
However, [NAME_99] has not taken into account the possible effects of the [NAME_55] and [NAME_53] merger.
[NAME_99] confirmed that the TRM was based on the assumption that all [NAME_65] would come across. Each transfer is staggered by 1 month to allow rigging for each carrier to take place in isolation for safety reasons.
83. The IRR shown on the TRM was supplemented by [NAME_1] Development Analysis prepared by underwriters at [NAME_10] [B442]. The blended IRR i.e. taking into account original transaction costs are:
1 carrier – 6.64% 2 carriers – 9.43% 3 carriers – 10.26%
84. The SCIP dated August 2025 (which takes the form of a PowerPoint presentation [B445-448]) shows IRR as follows:
[NAME_66] = £12,500 / [NAME_51] = £12,500 / [NAME_69] = £5,000, starting October 2025.
• IRR = 8.00% with £35k contribution to MNO rigging costs until Oct 2045 • IRR = 8.79% with no additional rig cost, until Oct 2045 • IRR = 9.37% with additional £35k rig costs, term completion Oct 2055
31 • IRR = 10.00% with no additional rig cost, term completion Oct 2055
[NAME_107] approval was given on 21st August 2025 [B449-450].
85. It is clear that [NAME_47] gave its approved to an investment led development based on IRR. The SCIP is a fully costed plan based on detailed figures for expenditure and return. The investment return shows the impact of the proposed inducement of £35,000 on the return. The SCIP was based on 3 carriers migrating across at 1, 2 and 3 month intervals starting in October 2025.
86. Based on [NAME_47] approval, the Board of [NAME_10] resolved on 22nd August 2025 that:
“following approval of the build costs, investment returns (including the proposed inducements) by the [NAME_107] on tonight’s tower submission call, the tower works at Queen’s [NAME_1] will commence as soon as vacant possession is obtained.” [B475-476]
87. In his second Witness Statement dated 15th September 2025, [NAME_81] on behalf of [NAME_2] suggested that temporary [NAME_1] and rigging costs for [NAME_65] as stated by [NAME_99] were inadequate and could be as much as £122,000 [H12-15]. Accordingly on 22nd September 2025 [NAME_46] held a further Board Meeting [H374-375]:
[NAME_87] has suggested that the costs to be incurred by the [NAME_65] could be in the range of £96,000 to £122,000. [NAME_10] does not agree the figures. It has previously factored into its calculations an incentive towards rigging costs of £35,000. [NAME_10] now wishes, in a worst case scenario, to provide an incentive of up to £122,000, and seeks additional funding for that purpose.
It was resolved:
That the Company will provide any additional funding that is required to allow [NAME_10] to offer an incentive of up to £122,000.
32 88. When asked by the Tribunal, [NAME_99] confirmed that, although incentives up to £122,000 was potentially available, he did not consider that anything like that sum would be needed. [NAME_99] was very careful to explain that the question any incentive, if at all, would be the subject of a business discussion once [NAME_21] new tower had been built.
89. [NAME_99] said that he had had a call with [NAME_108] (surname unknown) at [NAME_10] underwriters about the effect on IRR of the increased incentive but had not yet communicated that information to the [NAME_107]. [NAME_99] told us that on the basis of the telephone call IRR (20 years) was 6.15% and IRR (30 years) was 7.77%.
90. [NAME_99] had completed his evidence and been released [NAME_10] obtained [NAME_107] approval, as evidenced by an email dated 2nd October 2025 from [NAME_109] containing “formal confirmation of the [NAME_107]’s approval for this [NAME_1], including the £122,000 incentive and corresponding reduction in IRR” [H475].
91. On 2nd October 2025 there was a further [NAME_46] Board meeting [H471-474]
Business of the Meeting:
e) It is understood that evidence was given in the proceedings that taking into account the Increased Incentive Sum, the IRR of the development would be 6.15% for 20 years and 7.77% for 30 years f) The Adjusted IRRs were approved by the [NAME_107] on 2 October 2025 as recorded in an email from Este on 2 October 2025 at 21:03. [NAME_125] was in attendance on the submission call and confirmed that it had been explained to the Committee that although the Adjusted IRRs vary by number of carriers and the term over which they are calculated, the Increased Incentive Sum would be deployed by [NAME_10] in its discretion. It is not commercially likely that the entirety of the Increased Incentive Sum would be dispensed only to one carrier over a 20-year term.
33 Resolved:
3. That the Board is content with how the Increased Incentive Sum and the Adjusted IRRs have been dealt with to date;
4. That the Board remains of the firm view that there is no reason not to proceed with the Queens Oak build out;
92. [NAME_100] put it to [NAME_99] that the driver behind [NAME_21] proposed redevelopment was to resist renewal proceedings. [NAME_99]’s response was that [NAME_10] was seeking a return on its investment and the best way for that to be achieved was to remove potential competition.
93. [NAME_99] has been clear in his evidence, both written and oral that [NAME_10] wants to ensure the best chance that [NAME_65] will come across to the new [NAME_10] tower. [NAME_99] was extremely frank in his evidence. He accepted that he did not know if the [NAME_65] would come across and that [NAME_10] could not force them to do so. He has not spoken to them. He thought that the [NAME_65] were keeping their options open but there was a risk that they would not come across. [NAME_99] accepted that there was a possibility that the [NAME_65] would find an alternative location. In such circumstances [NAME_99] said that [NAME_10] would proceed with its redevelopment even if none of the 3 carriers come across. It would do so as part of its plans to break into the market. There is also benefit in building a “naked” tower because the [NAME_1] is more valuable “if you own the steel sitting on it”.
94. In addition to the “naked tower” build [NAME_99] put forward a further business strategy during cross examination by [NAME_100]. [NAME_99] suggested that even if no tenant came onto the [NAME_1] for the first two years and then one of the carriers came across at a rent of £12,500 that would give an IRR of 5.72%. If a second carrier came on [NAME_1] in October 2029, also paying £12,500 p.a. IRR would increase to 8.25%. [NAME_99] confirmed that he had entirely discounted [NAME_4]/[NAME_69] in that scenario. [NAME_99]’s business case suggesting carriers only coming across after 2 and 4 years was raised for the first time in cross examination. It is not raised in the SCIP [B448] which is based on three carriers starting October 2025, staggered at 1, 2 and 3 monthly intervals for logistical reasons.
34
95. [NAME_99] was cross examined at length by [NAME_100] in respect of the [NAME_65] currently at the [NAME_1]. When asked about [NAME_65] [NAME_99] said that “we do speak generally”. However, [NAME_10] does not have [NAME_84] coming to them to ask for sites. [NAME_10] has yet to break into the market.
Accordingly, [NAME_99] agreed with [NAME_100] in cross examination that [NAME_10] is unaware of [NAME_84] specific requirements for the new [NAME_1]. [NAME_99] said that although neither [NAME_51] or [NAME_53] intended to upgrade or replace at the present time, he was satisfied that they would have to do so over the lifetime of the tower. [NAME_99] estimates that the new tower will last significantly longer than 30 years with good maintenance. He accepted that [NAME_21] proposals would cause significant disruption for the [NAME_84] but felt that once [NAME_10] had spoken to them and heard what [NAME_10] had to offer the position would change. In particular [NAME_10] can offer security of tenure up to 30 years if required. This is advantageous for [NAME_65] who are looking at “total costs of ownership”. [NAME_99] also took the view that disruption was something that occurs at all sites where upgrades were necessary. [NAME_100] suggested that [NAME_21] decision was not customer lead. [NAME_99] replied that “we are removing the only mast – that is competition.” [NAME_99] believed that all [NAME_65] would come across based on lower rents and also lack of an alternative [NAME_1]. There is in [NAME_99]’s opinion a clear driver. [NAME_68] need to maintain coverage and are known to be seeking an alternative [NAME_1] close by. Similarly, [NAME_66] have asked [NAME_2] to find an alternative [NAME_1]. There is clearly demand from [NAME_69] as they have, very recently, entered into a 20 year agreement at the existing [NAME_1].
96. When asked why he had not spoken to [NAME_65] [NAME_99] gave two reasons. The first relates to ongoing 1954 Act proceedings in the County Court concerning a [NAME_1] known as [ADDRESS] in which the parties are in dispute about, inter alia, the ownership of a mast. [NAME_10] accordingly notified all operators at that [NAME_1] that they should make payments directly to [NAME_10]. [NAME_2]’s legal team responded on 19th August 2024: “It is, of course, completely inappropriate for [NAME_10] to contact [NAME_2]’s customers and we have informed them of the situation.” The Tribunal finds that whilst there may be issues at one particular [NAME_1] that would not prevent [NAME_99] from, perfectly properly, speaking to [NAME_65] about proposals in respect of [NAME_70]. Indeed, he accepted later in his evidence that [NAME_10] does speak to [NAME_65] but not about [ADDRESS] or [NAME_70]. The second reason why [NAME_99] has not spoken to [NAME_84] is that
35 commercially [NAME_10] will be in a much stronger position to do so should they win this case.
97. [NAME_99] is not aware of a potential alternative [NAME_1] for the [NAME_65] to migrate to other than White Rose Farm which he said: “makes sense, keeps their options open”. [NAME_99] said that although he had not had any discussions with the [NAME_65], [NAME_10] checked planning applications daily and “without planning they do not have a [NAME_1]”. [NAME_99] explained that there are 6 dishes at the [NAME_1] for transmission links to other sites. If [NAME_2] move too far away those transmission links may be broken.
98. [NAME_99] was asked what would happen if [NAME_2] vacated the [NAME_1] voluntarily. [NAME_99] said that [NAME_10] would still build their tower. [NAME_99] said that the tower market is a difficult one to break into. It might take years. He accepted that the [NAME_65] may not come across, but [NAME_10] had the only [NAME_1] in the vicinity with planning, a tower and ownership of land. [NAME_99] said that at present operators were hedging their bets. Understandably they want to avoid disruption but once built they will come over. [NAME_99] was very clear that if the [NAME_65] shun [NAME_21] new tower that would be “hugely anti- competitive”. A new tower at [NAME_70] is well worth building. [NAME_10] knows the [NAME_1] is needed and they can provide operators with everything they need. [NAME_99] added: “easier to be the sole provider – competition in practice.” Later he said: “if we do not kick OT off, we cannot get tenants. It makes perfect sense. Competition in action.”
99. In [NAME_99]’s view [NAME_21] original plan to build on the [NAME_10] [NAME_1] is less attractive than going over the [NAME_2] [NAME_1]. The [NAME_2] [NAME_1] involves marginally higher costs and greater disruption. However, the prospects are far better as a new mast on the [NAME_2] [NAME_1] will be the only tower in the area. Ultimately a new mast on the [NAME_2] [NAME_1] is the best solution and long term investment.
100. [NAME_10] has built towers speculatively. It has built only 6 towers, 5 of which still stand unoccupied. Breaking into the market has proved difficult. Even where there are coverage gaps [NAME_65] will not come over. Only one of [NAME_21] towers is occupied. That occupier is [NAME_50]. [NAME_56] were going to come over to Tryst Sports Centre in Cumbernauld and Century Mill in Bolton. However, [NAME_56] have not done so. [NAME_99] believes that is as a result of the [ADDRESS] which “didn’t help our
36 relationship with [NAME_56]”. [NAME_68] have not expressed interest in Trysts Sports Centre as their [NAME_1] is not at risk. [NAME_68] have looked at other sites around Century Mill but have not indicated a wish to come onto that [NAME_1]. There has been no interest whatsoever in the other speculative builds.
Evidence of [NAME_25]
101. [NAME_114] is not a decision maker at [NAME_10]. He does not decide when to proceed with a [NAME_1] or undertake commercial analysis. His role relates to customer design needs. In simple terms how best to get kit onto a tower.
102. [NAME_114] confirmed that [NAME_10] has not yet had an MNO make contact and ask for a new [NAME_1]. The legacy portfolio transferred from [NAME_46] to [NAME_10] contains about 50 sites. [NAME_10] has not built a lot of sites. Only 6 have been built.
103. As [NAME_10] do not own the mast at [NAME_70] [NAME_114] has not carried out any investigations. He confirmed that [NAME_10] had built speculatively where there was a need for coverage but no mast. The Swann tower is [NAME_21] default structure for most [NAME_1] builds. The [NAME_1] at [NAME_70] is within the generic load case in terms of height and wind speeds. The Swann tower has headroom for upgrades. [NAME_114] has not had any contact with the [NAME_65] at the [NAME_1] and accordingly is not aware of any need for upgrades.
104. [NAME_114] said that he felt it inappropriate to talk to [NAME_115] customers during pending litigation. He would not like to guess what they might think. [NAME_114] accepted that the [NAME_65] might well go somewhere else. The choice is one for the [NAME_65] – they may not come over at all.
105. [NAME_114] has for that reason not undertaken any design work. [NAME_10] cannot specify antennas as discussions in terms of radio have not begun.
37 106. The works required to give effect to [NAME_21] proposed redevelopment, assuming power and fibre already installed, are set out at paragraph 32 of [NAME_114]’s Witness Statement [C29]:
(a) Removing active equipment from the existing tower (b) Installing temporary trackway (c) Removing the existing tower (d) Breaking out and removing the existing concrete base (e) Installing new foundations (f) Erecting new steel tower onto stub (g) Rigging for new antenna, feeder and fibre cabling.
[NAME_114] explained that [NAME_2] would carry out items (a) – (d). [NAME_10] will carry out items (e) and (f). [NAME_10] could also carry out rigging under item (g). However, it may be that [NAME_65] will use their own design teams in which case it would be more sensible for [NAME_65] to carry out rigging themselves.
107. Potentially agreement could be reached between the parties for the existing concrete base to remain. However, it may be difficult to accommodate the loading of the Swann tower using resin anchors attached to the existing concrete base. [NAME_10] has not carried out any analysis of the existing concrete base and there is “a lot of homework to do”, but the most likely scenario is replacement. [NAME_21] preference is for [NAME_2] to remove its concrete base so that [NAME_10] can install a new base with a stub on which to mount the Swann tower.
Evidence of [NAME_81]
108. [NAME_82] very helpfully talked the Tribunal through the active equipment presently on [NAME_1] by reference to the photograph at [B669]. There are 9 panel antennas. At the top of the headframe are 6 antennas, 3 each for [NAME_51] and [NAME_53]. [NAME_51] and [NAME_53] have their own antennas but share transmission equipment on the ground. At the bottom of the headframe are 3 more panel antennas. These are shared by [NAME_59] and [NAME_55] who share antennas and transmit through the same equipment. [NAME_4] has an omni antenna.
38 Rigging bundles are both coaxial and fibre. The bundle on the right-hand side of the photograph runs to the top of the tower and serves [NAME_51] and [NAME_53]. The rigging on the left serves [NAME_59] and [NAME_55].
109. [NAME_82] confirmed that [NAME_2] would remove the concrete base at the [NAME_1] unless any agreement to the contrary was reached with [NAME_10]. It would be unusual to remove fibre on decommissioning a [NAME_1]. The usual arrangement would be for it to be terminated and capped. Similarly, power would be terminated with the DNO. Fencing at the [NAME_1] would usually be a matter for discussion with the landlord as to removal or otherwise.
110. The [NAME_2] is made of galvanised steel and usually, on decommissioning, it would be cleaned, painted and put up at another [NAME_1]. If not capable of reuse it would be recycled. The concrete base could be crushed and used as subbase for roadbuilding or filling up quarries. [NAME_2] is responsible for any landfill. [NAME_2] would return the [NAME_1] to greenfield, if requested by the landowner, by covering with topsoil and planting with seed. Otherwise on removal of the concrete bases [NAME_2], with landowners’ agreement, would fill in the hole and make safe. [NAME_82] thought a trackway would probably not be necessary at this [NAME_1] given the proximity of the concrete farm road and the fact that the [NAME_1] is not in a boggy area.
111. [NAME_81] made a Second Witness Statement on 15th September 2025 [H12-15] which sets out the costs of the temporary [NAME_1] and the costs to be paid by the [NAME_65]. [NAME_10] proposes a temporary tower as close as possible to the existing [NAME_2] mast. [NAME_82] agrees that this is sensible as it allows ground based equipment to be reused and design costs will be lower. The disadvantage is that the temporary [NAME_1] will need to be rigged identically to the existing mast (4 sets of rigging – one per MNO). [NAME_82] indicates that for [NAME_55], [NAME_59], [NAME_51] and [NAME_53] 2,400m of coaxial feeder will be required costing in the region of £60,000-£75,000 to supply and fit. [NAME_82] also indicates that [NAME_65] will only use “Tier 1” subcontractors rather than “Tier 2” as proposed by [NAME_10]. [NAME_82] suggests further costs not taken into account by [NAME_99]:
Installation of new equipment - £10-15,000
39 Fibre and DC rigging - £15-18,000 Line of sight check - £5-6,000 [NAME_1] commissioning and integration - £6-8,000.
112. [NAME_65] at [NAME_70] still use coaxial cable. [NAME_51], however, has moved to fibre but still also has some coaxial cabling on [NAME_1]. Rigging with fibre is lower cost. Rigging costs are incurred in four stages – derig tower, rig temporary tower, rig new tower and derig temporary tower. Those rigging costs will be borne by [NAME_65].
(1) Subjective test – intention
113. The test of intention was formulated by Asquith LJ in [NAME_96] v [NAME_116] [253 and 254]:
An " intention " to my mind connotes a state of affairs which the party " intending "— I will call him X— does more than merely contemplate : it connotes a state of affairs which, on the contrary, he decides, so far as in him lies, to bring about, and which, in point of possibility, he has a reasonable prospect of being able to bring about, by his own act of volition.” “X cannot, with any due regard to the English language, be said to " intend " a result which is wholly beyond the control of his will.”
“This leads me to the second point bearing on the existence in this case of " intention " as opposed to mere contemplation. Not merely is the term " intention " unsatisfied if the person professing it has too many hurdles to overcome, or too little control of events: it is equally inappropriate if at the material date that person is in effect not deciding to proceed but feeling his way and reserving his decision until he shall be in possession of financial data sufficient to enable him to determine whether the project will be commercially worthwhile.
A purpose so qualified and suspended does not in my view amount to an " intention " or " decision " within the principle. It is mere contemplation until the materials necessary to a decision on the commercial merits are available and have resulted in such a decision.”
40
“Neither project moved out of the zone of contemplation—out of the sphere of the tentative, the provisional and the exploratory—into the valley of decision.”
[NAME_10] and [NAME_46] undertakings
114. [NAME_10] and its parent company [NAME_46] have both offered undertakings:
[NAME_10] undertakes to the Tribunal and also to [NAME_2] that it will commence the intended redevelopment of the [NAME_2] UK [NAME_1] at [NAME_70] and complete the same as soon as reasonably practicable upon vacant possession being obtained. [H476]
[NAME_46] undertakes to the Tribunal and [NAME_2] that it will make available all such funds as may be necessary to support the [NAME_10] even should the costs of so doing exceed the Estimated Costs (“Estimated Costs” means the total anticipated cost of undertaking the Queen’s Oak redevelopment, estimated to be not more than £332,697) [H477]
Those undertakings were approved by [NAME_21] Board on 22nd September 2025 [H376- 377] and by the [NAME_85] on 2nd October 2025 [H471-474]
115. [NAME_21] accounts for the year ending 31st December 2024 show a loss of £3,076,173 [H390-408]. [NAME_10] has fixed assets of £8,371,654. However, [NAME_21] current liabilities exceed its total assets by £3,129,771. The balance in [NAME_21] current account on 30th September 2025 was £257,805 [H409 – 422]. [NAME_46]’s accounts and bank statements [H423-470] show that it has more than sufficient funds to make available all such funds as may be necessary to support [NAME_21] undertaking.
116. The learned commentators in [NAME_12]: Renewal of Business Tenacies 6th Ed, helpfully summarise the position in respect of the use of undertakings in 1954 Act proceedings at 7-208 and 7-275:
41 “In the Betty’s Cafes case, the court accepted an undertaking from the landlord to carry out the proposed works. In [NAME_117] v [NAME_118] the court accepted an undertaking to carry out certain works and to occupy for business purposes under ground (g). It was stated that where a responsible landlord offers such an undertaking to the court it will be powerful evidence of fixity of intention, although not conclusive. There is some doubt as to the appropriateness of the court accepting an undertaking in a case falling under ground (g), although the same objections would not appear to extend to an undertaking given under ground (f)”
“It is common for a landlord to give an undertaking to the court under ground (f), but there may be some doubt as to the propriety of the court accepting an equivalent undertaking under ground (g). In [NAME_117] v [NAME_118] such an undertaking was accepted under both grounds (f) and (g). In [NAME_119] v [NAME_147], the Court of Appeal held that the giving of an undertaking to implement ground (g) “compelled fixity of intention” and “was decisive”. In [NAME_121] v [NAME_122] an undertaking was offered under ground (g) but the court declined to regard the offering of that undertaking as being conclusive either of the bona fides of the landlord’s intention or of its firmness. In [NAME_123] v [NAME_124], the Court of Appeal held that the giving of an undertaking under ground (g) did not create a legal presumption that the landlord’s stated intention was genuine and, if the judge had ground for doubting the landlord’s veracity, he was entitled to disregard the undertaking altogether.”
117. More recently Lord Briggs considered the position in [COMPANY_97] at [29]:
“The courts have until now restricted the forensic examination of the Landlord’s purpose or motive to a test of the genuineness of that intention. By genuineness I have no doubt that the court meant honesty. In practice, that examination has, for very many years, largely been overtaken by the common use of the undertaking to the court to carry out the works if a new tenancy is refused, as a reliable litmus test for genuine intention. But neither the undertaking to the court, nor the examination of the genuineness of the landlords intention, will reveal whether the landlord’s intention is of the disqualifying conditional kind, as this case demonstrates.”
42 118. [NAME_100] objects to the undertakings primarily on the basis that [NAME_10] itself does not have sufficient funds to support its undertaking but also because both undertakings lack specificity, are reactive in that they were provided during the course to the hearing and are given under the authority of [NAME_125] at [NAME_46] who has not been tendered for cross examination.
119. We have been referred to Nogueira v Westminster LBC [2014] UKUT 327 (LC). In that case it was held that the FTT could not accept undertakings. However, the Upper Tribunal was not referred, in that case, to the power of the FTT to accept an undertaking and subsequently to transfer to the Upper Tribunal for enforcement under FTT Rule 6(3)(n)(ii), the Upper Tribunal having all the powers of the High Court under s25 of the Tribunals, Courts and Enforcement act 2007. We are satisfied that we can accept the undertakings proffered on the basis of our powers to transfer to the Upper Tribunal for enforcement.
120. [NAME_10] is an operator pursuant to an OFCOM direction. We are satisfied that the proposed undertaking is backed financially by the [NAME_46] undertaking. We therefore accept both the [NAME_10] and [NAME_46] undertakings as evidence, although not conclusive evidence, of the genuineness of [NAME_21] intention to commence and complete its proposed redevelopment.
Conclusions – subjective intention
121. In determining [NAME_21] subjective intention, we must first determine what that intention actually is. Our finding is that [NAME_21] settled intention is investment led. It is based on the business plan contained in the TRM dated 21st August 2025 [B441], blended IRR [B442] and the SCIP of August 2025 [B445-448] which was approved by the [NAME_107] on 21st August 2025 [B449-50] and by the [NAME_10] Board on 22nd August 2025 [B475-476].
122. There is no suggestion from any of the [NAME_10], [NAME_46] or [NAME_47] decision makers that [NAME_21] redevelopment intention involves the building of “a naked” tower i.e. a tower with no carriers. There is no support from any of the [NAME_10], [NAME_46] or [NAME_47] decision makers that
43 [NAME_21] plans for the [NAME_1] are as a “start up” or “seed” capital. There is no support for [NAME_99]’s suggestion that there is benefit in building a “naked” tower because the [NAME_1] is more valuable “if you own the steel sitting on it.” We find no support in the Board minutes of [NAME_10] nor from the [NAME_107] that business plan was to build a naked tower for marketing purposes. There is no support for [NAME_99]’s suggestion that [NAME_10] will proceed with its redevelopment if the 3 carriers do not come across. Nor is there any support for the contention that the business case was based on a naked tower for 2 years with the first carrier coming on in 2027 and a second carrier in 2029. We find that there is no realistic prospect of [NAME_65], having decamped to a new [NAME_1], would seek to return to Queens Oak Farn after 2 or even 4 years. Those alternative business cases are mere contemplation on [NAME_21] part, containing too many hurdles and events outside of [NAME_21] control. Above all they lack any commercial merit. We find that [NAME_21] redevelopment is wedded to [NAME_84] migrating from [NAME_2].
123. At paragraph 308 of [ADDRESS] the Upper Tribunal made the following findings:
“The commercial objectives behind the construction of the New Tower emerged quite clearly from the evidence referred to in our previous paragraph and from the evidence generally. The New Tower is designed to accommodate the four [NAME_65] which currently use the [NAME_56] [NAME_1] and the [NAME_68] [NAME_1], at rents which we assume to be more advantageous to [NAME_10]. It is quite clear from the evidence that what [NAME_10] is seeking to achieve, in relation to the Sites, is a situation where the [NAME_56] [NAME_1] and the [NAME_68] [NAME_1] are decommissioned, thereby compelling [NAME_56], [NAME_61], [NAME_53] and [NAME_51] to migrate to the [NAME_1]. Indeed, if this was not the intention of [NAME_10], the Respondents’ investment in the construction of the New Tower on the [NAME_1] would make little commercial sense. If this investment is to be repaid, operators must be brought to the New Tower, which has been constructed with the intention that it should have plenty of spare capacity for additional operators to join the [NAME_1]. This commercial objective is, at the least, much more likely to be realised if there is no competition from the Masts. In these circumstances it seems quite clear to us from the evidence, and we so find, that [NAME_10] has demonstrated a decision to proceed with the removal of the Masts.”
44 124. Having discounted [NAME_126] “naked tower”, value of the land with steel on it and carriers not coming across until 2027 and 2029 we are left with the investment led business case set out in the SCIP. The SCIP is based on financial modelling based on 3 carriers coming across in 1 month, 2 months and 3 months. It is an investment led strategy to provide a return for [NAME_10], [NAME_46] and [NAME_47] on their investment. The commercial objectives behind the SCIP are clear and we find that [NAME_10] has established a firm and settled intention to carry out its redevelopment as set out in the SCIP approved by the [NAME_107].
(2) Objective test – reasonable prospects
125. The planning experts are agreed that there is no planning impediment to [NAME_21] redevelopment. [NAME_21] plans are backed by [NAME_46] and [NAME_47] and it is not disputed that it has funding in place.
126. [NAME_10] bears the burden of satisfying the Tribunal that it has reasonable prospects of being able to bring about the redevelopment. In a 1954 Act case, Gatwick Parking Services Ltd v Sargent [2002] EGLR 45, [NAME_128] LJ observed:
“the hurdle to be surmounted by the appellant under section 30(1)(g), in the light of the authorities on the subject, is by no means a high one. It does not have to demonstrate a balance of probability that [planning] permission will be granted. He has to show that there is a real, not merely a fanciful, chance."
127. The Tribunal is required to assess the objective element on the assumption that [NAME_10] is entitled to possession of the [NAME_1] and that [NAME_2]’s tenancy at will has determined. In Westminster City Council v British Waterways Board [1985] AC 676 at [680-682] Lord Bridge said that the 1954 Act requires that the landlord’s “prospect of success should be assessed on the footing that he is entitled to possession…”. The task before the Tribunal was set out in Humber Oil Terminals Trustee Limited v Associated British Ports [2012] EWCA Civ. 596 at [25]:
45 “The judge had to assess the objective element of ABP’s [Landlord] stated intention by making the required statutory assumption that it is ABP and not HOTT [Tenant] that is in possession of the premises; and therefore necessarily on the assumption that HOTT’s tenancies had determined. That is what he did and he made his findings of fact referred to above as to the probabilities of what would then happen.”
At first instance [NAME_129] held: “I do not need to decide what will happen, only on a balance of probabilities what is the most likely outcome” [see paragraph 19 of the Judgement of Rimer LJ].
The position of the [NAME_65]
128. [NAME_30] (Asset Protection Manager for [NAME_2]) has prepared two Witness Statements dated 28th April 2025 [C2-5] and 27th August 2025 [C41-45]. His evidence was agreed and [NAME_130] did not give oral evidence to the Tribunal. In his second Witness [NAME_130] confirmed that:
Paragraph 6 [C42]: “there are no customer demands for future upgrades at this [NAME_1] or any requirement to increase the height of the tower”.
129. At paragraphs 7-9 [C42-43] [NAME_130] explains the procedure [NAME_2] follows where it receives a notice to quit (“NTQ”) from a [NAME_1] provider:
Stage 1: Receipt of NTQ and initial strategy review Stage 2: Inform customers and serve notice to terminate Stage 3: [NAME_1] search and nomination process Stage 4: Acquisition and design Stage 5: Build and decommissioning
130. [NAME_2] has served termination notices on its customers at the [NAME_1]:
[NAME_51] 19th November 2024 [H143-149] [NAME_53] 19th November 2024 [H150-156] [NAME_61] 1st May 2025 [H157-163]
46 [NAME_4] 21st August 2025 [H164-168]
131. A potential alternative [NAME_1] at White Rose Farm has been nominated:
[NAME_59] [NAME_1] 1st July 2025 [H113] and [NAME_59] demand for the QOF replacement [NAME_1] [H120-125]
[NAME_51] and [NAME_53] email from [NAME_131] ([NAME_68] copied in) to [NAME_2] dated 18th February 2025 and Nomination file (redacted) [H280-283]
[NAME_4]: Emails between [NAME_132] of [NAME_4] and [NAME_135] of [NAME_87] 18th September 2025 – 30th September 2025 [H384-386]
132. At paragraphs 10 and 11 of his Second Witness Statement [C43-44] [NAME_130] explains that [NAME_2] has identified an alternative [NAME_1] at White Rose Farm. He also explains that [NAME_68] (not [NAME_2]) have made a planning application for White Rose Farm:
“10. I can confirm that the same process has been followed in this case. [NAME_2]’s Licensing team served termination notices on our customers and we have identified a potential alternative [NAME_1] at White Rose Farm which has been nominated by [NAME_51] and [NAME_53] (via [NAME_68], their managing agent). We are therefore progressing this as a back up to the [NAME_1] if [NAME_10] is successful in these proceedings.
11. Our customers don’t necessarily want to put all their eggs in one basket and sometimes they will also run their own processes as a back up in case the alternative [NAME_1] fails in the acquisition and design process or we fail in remaining in occupation of the current [NAME_1]. Each customer has its own processes and they often pursue a parallel process to ours so they can minimise the risk of having a dead cell and have a back up option in case [NAME_2] cannot provide a replacement, such as White Rose Farm. As mentioned in paragraph 7 above, I am aware [NAME_68] has made a planning application in relation to White Rose Farm, but I don’t have any information about the planning application or its withdrawal.”
47 133. The only other information that the Tribunal has in respect of the White Rose Farm nomination is contained at paragraph 49 of [NAME_99]’s second Witness Statement [C40]:
“I am told by [NAME_46]’s legal team that on 21 May 2025 they became aware from a check of the planning portal that [NAME_51] and [NAME_53] submitted a prior approval application on 17 April 2025 in relation to the installation of a telecoms mast at White Rose Farm, which is located near the [NAME_2] [NAME_1]. This was subsequently withdrawn on 1 May but the reasons for this are not known.”
Our finding of fact is that [NAME_68], independently of its nomination to [NAME_2], made a planning application in respect of White Rose Farm on 17th April 2025 which it withdrew on 1st May.
134. At paragraphs 314-317 of [ADDRESS] the Upper Tribunal considered the position of the [NAME_65]:
314. So far as concerns the question of whether [NAME_56] or any of the other [NAME_65] would migrate to the New Tower, if the Masts were removed, we will briefly express our views. The Respondents' counsel drew our attention to the decision of [NAME_129] (as he then was) at first instance in Humber Oil Terminals Trustee Ltd v Associated British Ports [2011] EWHC 20243 (Ch), as authority for the point that a landlord may rely on predicted actions of their tenant, in establishing that there is a reasonable of achieving a particular result. In [NAME_129] found that the tenant, following the termination of its leases of parts of the Immingham Oil Terminal on the Humber Estuary, would have negotiated new terms with its landlord for the use of the relevant facilities. The Respondents' counsel submitted that the position was the same in the present case, and that "once all the posturing is over" (to use the language of [NAME_129] in his judgment at [122]) the [NAME_65], including [NAME_56], could be expected to agree terms with [NAME_10] for their use of the New Tower.
315. So far as the [NAME_65] other than [NAME_56] who are using the Masts are concerned, we are not able to say what they would do. In closing submissions [NAME_138] argued that we were entitled to infer, from the available evidence, that other [NAME_65] would wish to stay in the location. [NAME_138] also submitted that [NAME_56] could have called
48 evidence from the other [NAME_65] but had not done so. It was submitted that we could infer from this that [NAME_56] was seeking to insinuate that there were difficulties with the other [NAME_65] migrating to the New Tower, without being able to demonstrate this by evidence.
316. We were not persuaded by these arguments, in the case of the [NAME_65] other than [NAME_56]. The burden of demonstrating that there is a reasonable prospect that the other [NAME_65] would migrate to the New Tower, in the event of the removal of the Masts, lies upon the Respondents. This is simply a function of the burden which is upon the Respondents to prove that [NAME_10] has the required intention for the purposes of Paragraph (c). We have heard no evidence from any of the other [NAME_65]. We do not know their particular circumstances, or requirements, or commercial options if the Masts were to become unavailable. We do not consider that we are able, on the available evidence, to make a finding to make a finding that there would be a reasonable prospect of the other [NAME_65] moving to the New Tower, if the Masts were removed.
317. This leaves [NAME_56] itself. Here, the position is different. In the case of [NAME_56] there was evidence from [NAME_140] that [NAME_10]'s conduct had called into question whether [NAME_56] would wish to engage with [NAME_10] moving forward. There was also evidence from [NAME_56] that it had no need of an upgrade to the facilities provided by the [NAME_56]. We are however, in the case of this particular issue, required to consider a scenario in which the Masts are to be removed, leaving the New Tower as the only existing option, in terms of mobile communications sites in this location. On this hypothesis it seems to us that the most likely outcome would be that [NAME_56] would agree terms with [NAME_10] for the use of the New Tower and would migrate from the [NAME_56] [NAME_1]. On this hypothesis we find that there would be a reasonable prospect of [NAME_10] achieving this result. We also consider that the position would be the same if one assumes a situation where only the [NAME_56] was to be removed. We heard no evidence to support the case that [NAME_56] relocating to the [NAME_68] [NAME_1] would be a realistic option.”
135. We have the advantage over the Upper Tribunal in [ADDRESS] in that because of the way the case has been run before us we have some material about the likely
49 actions of the [NAME_65]. We approach that material with caution because we do not have any direct evidence from the [NAME_65]. However, we do have sufficient secondary evidence from which we can safely infer the likely actions of the [NAME_65].
136. In support of the [NAME_10] that once all the posturing is over the [NAME_65] will migrate:
Commercial pragmatism will prevail. The [NAME_65] will want to avoid detriment to their customers and will not “set their faces” against migration [NAME_10] is providing a brand-new tower which is future proofed and can support all future upgrades and sharers The [NAME_1] at [NAME_70] works in terms of network coverage and transmission links There is clear demand. The [NAME_65] are known to be looking at alternative sites close by. [NAME_4]/[NAME_69] have very recently come onto the [NAME_1]. [NAME_65] will need to maintain coverage. The [NAME_65] will want at all costs to avoid a “dead cell” or “not spot”. The rent offered is competitive and based on existing payaway figures [NAME_10] is prepared to offer incentives of up to £122,000 to cover additional rigging costs [NAME_10] is the freeholder of the [NAME_1] and can offer long term agreements of 20 or 30 years allowing [NAME_65] certainty as to total costs of ownership [NAME_2] do not have planning permission for alternative sites. [NAME_68] have withdrawn their application at White Rose Farm. [NAME_2] will require Prior Approval for any new mast up to 25m and full planning permission for a mast above 30m Without planning [NAME_2] do not have an alternative [NAME_1]
137. In support of the [NAME_2] position in respect of the [NAME_65]:
[NAME_10] have not spoken to the [NAME_65] at all about this case [NAME_10] has not had any discussions with [NAME_65] about their technical requirements.
50 All 3 carriers are working with [NAME_2] to find an alternative [NAME_1] and have made nominations. [NAME_68] and [NAME_4] have both objected to [NAME_21] 2025 planning application. [NAME_10] has built 6 “naked towers”. None of the [NAME_106] has come onto those towers. [NAME_10] does not have an established relationship with [NAME_65] seeking new sites [NAME_99], in his candid evidence, accepts the there is a real risk that NMO’s may not come across until 2027, 2029 or at all. Similarly. [NAME_114] accepted that [NAME_65] may well go somewhere else. This is clear evidence that [NAME_10] themselves have very real doubts as to viability of its business plan. The offer of incentives to attract [NAME_65] suggests that [NAME_10] is well aware of MNO reluctance The manner in which the Respondents have conducted this litigation will have damaged their relationship with the [NAME_84] as [NAME_99] accepted had happened with [NAME_56] following [ADDRESS] As explained by [NAME_130], [NAME_2] has a well established existing procedures to move to a new [NAME_1] when served with an NTQ by a [NAME_1] provider [NAME_2] is able to use the Prior Approval procedure to obtain planning permission for a new tower up to 30m at an alternative [NAME_1] [NAME_2] as an operator has expropriatory powers under the Code, where the public benefit likely to result outweighs prejudice, to obtain new sites under Part 4 of the Code.
138. The proposed [NAME_10] tower is future proof, the rent competitive and [NAME_10] can offer a long term deal. The [NAME_1] at [NAME_70] works and there is clearly demand. [NAME_10] is prepared to compensate [NAME_65] for the costs of migration by way of substantial incentives. However, [NAME_10] has not spoken to the [NAME_65]. [NAME_65] are actively seeking alternative sites. [NAME_10] has no existing relationship with [NAME_65]. [NAME_65] have not migrated to any of [NAME_21] new towers. This litigation will have damaged any future relationship [NAME_10] may have had with [NAME_65].
We find on the balance of probabilities that the most likely outcome is that the [NAME_65] will not migrate to [NAME_21] new tower. [NAME_10] has failed to demonstrate that there is a
51 reasonable prospect that [NAME_65] will migrate to its new tower. We therefore find that [NAME_10] does not have a reasonable prospect of being able to carry out its redevelopment.
(3) Conditional Intention
139. In [COMPANY_97] at [19] Lord Sumption JSC set out the test to be applied:
“…the landlord’s intention to demolish or reconstruct the premises must exist independently of the tenant’s statutory claim to a new tenancy, so that the tenant’s right of occupation under a new lease would serve to obstruct it. The landlord’s intention to carry out the works cannot therefore be conditional on whether the tenant chooses to assert his claim to a new tenancy and to persist in that claim. The acid test is whether the landlord would intend to do the same works if the tenant left voluntarily.”
140. Conditionality in the context of Code rights was considered in [NAME_94] at [37]:
“… the respondents cannot satisfy the requirements of para.21(5) if their intention to redevelop is conditional on whether the claimants assert their claim to Code rights. The acid test is whether the respondents would intend to do the same works if the claimants did not seek Code rights.”
141. [NAME_100] relies on the way in which [NAME_21] case has pivoted in response to the ongoing litigation. In 2022 the [NAME_1] was discounted in a review of 4,040 sites in the [NAME_46] portfolio. At that time 948 sites were better and 170 went forward for planning. No coverage drivers were identified in 2022 and that position has not changed. The decision to look again in 2024 was entirely lawyer led in response to the renewal proceedings and the claim for Code rights. [NAME_70] was simply “fast tracked” in response to the restarting of litigation. In 2025, in the aftermath of [ADDRESS], [NAME_10] pivoted from building on the [NAME_10] [NAME_1] to going over the [NAME_2] [NAME_1]. The evidence of [NAME_99] is that IRR for the [NAME_10] [NAME_1] was similar to IRR for going over the [NAME_2] [NAME_1]. The explanation given by [NAME_10] is that the change of strategy in was made in the face of an offer (never actually made) of a renewal at a rent of £1750 p.a. [NAME_100]
52 submits that the pivot in 2025 was solely to defeat Code rights. At the hearing [NAME_10] pivoted yet again to a naked tower strategy which [NAME_100] characterises as opportunism to shore up a failing investment led case. [NAME_21] strategy, [NAME_100] submits, is entirely lawyer-led. [NAME_10] would do whatever is necessary to get [NAME_2] off the [NAME_1] and defeat its claim for Code rights.
142. The finding in [ADDRESS] is at [328-330]:
328. It is easy, in the present case, to become caught up in the question of the merits of what the Respondents have done in relation to the [ADDRESS]. On the one hand, it may be said that the Respondents have, by their conduct of the planning process, engineered a situation where it can be said that the Masts have to be removed as a condition of the construction of the New Tower, thereby putting the Respondents into a position where they can exploit Paragraph (c) in an attempt to defeat [NAME_56]’s Code rights. It may be said that this is not a legitimate way of proceeding and that a device of this kind should not succeed. On the other hand, it may be said that it is perfectly legitimate for the Respondents to have used their common ownership of the [ADDRESS] and their lawful use of the planning process to enable the demolition of the Masts and the construction of the New Tower. In our view, and so far as Paragraph (c) is concerned, it is largely irrelevant which of these views is correct, or indeed whether the correct view lies somewhere between these competing scenarios. We do not regard it as necessary to decide what is the correct view. In our view what is important is that the construction of the New Tower was clearly consistent with the commercial objectives of the Respondents, as explained by their witnesses, regardless of whether Code rights existed or did not exist in relation to the [ADDRESS].
329. …
330. … Applying Lord Sumption’s “acid test” in the present case, we find that [NAME_10] would proceed with the removal of the Masts, even in circumstances where [NAME_56] was not seeking Code rights and, together with [NAME_61], was willing voluntarily to vacate the [NAME_56] [NAME_1].
53 143. We accept [NAME_142]’s arguments that [NAME_10] makes no secret of its desire to better it’s position by removing a competitor from the [NAME_1]. [NAME_99] said as much in his evidence. That is a perfectly legitimate business aim and recognised as such in [ADDRESS]. The consequence of [NAME_21] redevelopment is that [NAME_2] is prevented from acquiring Code rights – but that is a merely collateral effect. The pivot by [NAME_10] in 2025 to going over the [NAME_2] [NAME_1] was entirely consistent with its investment led strategy as set out in the SCIP. Applying the acid test as adopted in [NAME_94] we find that [NAME_10] would intend to do the same works even if [NAME_10] did not seek Code rights.
144. At this point we would wish to say something about the [NAME_10] legal team. We are quite satisfied that any implied criticism made by [NAME_2] is entirely unintentional. For our part, solicitors and counsel who have represented [NAME_10] before us have done so entirely professionally.
(4) Reasonable time
145. [ADDRESS] at [277] it was held that redevelopment must be commenced within a reasonable time of termination of the code agreement:
“Any such reasonable time will have to take account of the time likely to be required to secure the removal of the ECA from the relevant land, but subject to that and any other such consideration, it seems to us that there is a requirement that the relevant work must be commenced within a reasonable time of the code agreement coming to an end. What that reasonable time is in any particular case is a fact sensitive question, but we do not consider that it is open to the [NAME_1] provider to allege an intention to carry out the relevant work at any point in the future, however distant from the termination of the code agreement. The time between the termination of the code agreement and the intended commencement date of the relevant work must be a reasonable one.”
146. The joint consensus of the technical experts is that the redevelopment will take 12 weeks at best if re-using the existing base and approximately 26 weeks if new foundations/base are required and a temporary [NAME_1] is not acceptable to the [NAME_65] [Q6 at D45].
54
147. [NAME_10] have not contacted the [NAME_65] to discuss their requirements for the [NAME_1]. No commercial or technical conversations have taken place. As [NAME_114] told us there are many “ifs, when’s and maybes”. It is clear that final technical and design discussions will only start once vacant possession has been obtained. No final decision has been made in respect of who will rig, the fate of the existing concrete base, whether operator cabinets will remain and details of the temporary [NAME_1]. However, we find that it is likely that technical issues will be resolved during the 12/26 week period proposed by the technical experts.
148. We find that construction of the new tower can be completed within a reasonable time.
(5) The meaning of Redevelop
149. [NAME_142] refers to “the irreducible minimum works” that [NAME_10] will carry out. Those works include excavation, concrete foundations and the installation of the new tower. [NAME_114] told us that the most likely scenario is that [NAME_10] will replace the concrete base. However, it remains an open question as no analysis of the existing concrete base has been carried out. In particular design work needs to be carried out as to whether resin anchors attached to the existing base would be sufficient or whether a new base with a stub will be required. Our finding is that although [NAME_10] have expressed a preference for a new base no final decision as to the “minimum works” of excavation and new concrete foundations has yet been made. Similarly, [NAME_10] has not yet had any discussions with [NAME_2] as to fencing and the capping off of fibre and power. We adopt [NAME_82]’s evidence that it would be unusual for fibre to be removed and that power would be terminated with the DNO (Distribution Network Operator). We find that trenching work is unlikely to be required.
150. [NAME_100]’s submits that that the natural meaning of the word “redevelopment” connotes a change to what was on the land before. [NAME_10] is merely replacing existing ECA. The net result is the same. Replacement is not redevelopment.
151. [NAME_100] also relies on paragraphs 5, 101 and 108 of the Code:
55
5 Electronic communications apparatus, lines and structures
(1) In this code “electronic communications apparatus” means –
(a) apparatus designed or adapted for use in connection with the provision of an electronic communications network, (b) apparatus designed or adapted for a use which consists of or includes the sending or receiving of communications or other signals that are transmitted by means of an electronic communications network, (c) lines, and (d) other structures or things designed or adapted for use in connection with the provision of an electronic communications network.
(2) References to the installation of electronic communications apparatus are to be construed accordingly.
101 Ownership of property
The ownership of property does not change merely because the property is installed on or under, or affixed to, any land by any person in exercise of a right conferred by or in accordance with this code.
108 General Interpretation
“land” does not include electronic communications apparatus;
152. In [NAME_100]’ submission, to hold that replacement of ECA constitutes redevelopment of land is inconsistent with paragraphs 5, 101 and 108 which clearly distinguish between land and ECA and also between the redevelopment of land and the installation of ECA. For that reason, [NAME_21] redevelopment relating to a mast, cabinets and concrete bases (which as structures for use in connection with a network fall within Paragraph 5(1)(d)) cannot be redevelopment of land.
56 153. [NAME_100] also relies on the policy drivers behind the Code. As Judge Cook observed in [NAME_94] at [5]:
“It is unlikely that the Law Commission contemplated redevelopment of this nature when it recommended a provision to the effect of para.21(5).”
The balance to be struck between operator’s business needs, the public interest and the interests of [NAME_1] owners was set out by Fancourt J in the oft quoted passage in EE v Stephenson [2021] UKUT 167 (LC) at [53]:
“The purpose underlying the Code is to ensure that operators can use and exploit sites more flexibly, quickly and cheaply than had previously been the case, at lower than open market rents, in furtherance of the public interest of providing access to a choice of high quality electronic communications networks, while providing a degree of protection to [NAME_1] owners' legitimate interests”
In [NAME_100] submission the tearing down and replacement of ECA does not support rollout and does not encourage investment. Competition would be better fostered by [NAME_10] continuing with its 2024 plan of building on the [NAME_10] [NAME_1]. In addition, [NAME_21] proposed redevelopment would come at a significant environment cost.
154. A different view was taken by the Deputy Chamber President, when considering inclusion of a redevelopment break clause, in EE Ltd v. AP Wireless II (UK) Ltd [2024] UKUT 216 (“Vache Farm”) at [21]:
“…. as Stephenson shows, it is not the policy of the Code to stand in the way of redevelopment of sites. Provided the intention is genuine, we can see no reason why a different approach should be taken where the intended redevelopment is for a telecommunications use, even if the net result is that a particular operator may in the future enjoy less favourable terms at that [NAME_1] than if its previous lease of the land had continued…. If, at the end of the …term of the new lease, [NAME_46] opposed a renewal because it intended to redevelop the [NAME_1] with a new mast, [NAME_51]/[NAME_53] would not be entitled to complain that the new mast would be owned and managed by [NAME_46] or an
57 associated company. All that would matter would be whether [NAME_46] could prove the necessary intention.”
155. As [NAME_142] rightly submits [NAME_10] is also a WIP and there is no justification for treating one WIP differently from another. The fact that [NAME_2] is the WIP operating from the [NAME_1] does not entitle it to greater consideration in policy terms than [NAME_10] as freeholder WIP. Competition sits front and centre in Paragraph 21 of the Code which requires the Tribunal to have regard to: “the public interest in access to a choice of high quality electronic communications services”. [NAME_21] ambition to break into the market undoubtedly promotes competition and encourages investment.
156. [NAME_100] has sought to distinguish [ADDRESS], we follow what was said in that case, albeit that [ADDRESS] was concerned with paragraphs 31(4)(c) and (d) rather than paragraph 21(5), at [260]:
“Our third general point is that the intention referred to in Paragraph (c) must be an intention to redevelop all or part of the land to which the code agreement relates or any neighbouring land. The requirement is for redevelopment of land. This is material because "land" is defined in Paragraph 108(1) not to include ECA. We accept however that this definition does not necessarily mean that any work done to the ECA on a particular [NAME_1], including work to the relevant mast or tower, cannot qualify as redevelopment work. We have already stated our view that the concept of redevelopment implies some kind of change in the land which is the subject of the redevelopment, so that what was there before is replaced by something new. Consistent with this view it seems to us that [NAME_138] was right to submit that the taking down of one mast and the construction of another mast is capable of constituting work of redevelopment. The land is changed and can, in our view, be described as redeveloped where one mast is taken down and replaced by a new mast. That such work can qualify as work of redevelopment appears to have been accepted by the Tribunal in [COMPANY_143] v [NAME_93], although it is not clear in that case that there was any argument on the point. It will however be noted that, in the conclusion which we have just expressed, we are referring to a case where one mast is taken down and a new mast is erected on the same land.”
58 157. We find that taking down of one mast and the construction of another mast is redevelopment under Paragraph 21(5) of the Code.
Decision
158. Preliminary Issues (a) and (b) have been withdrawn.
159. In respect of Preliminary Issue (c) [NAME_10] has failed to establish that it has an intention to redevelop within the meaning of Paragraph 21(5) of the Electronic Communications Code (Schedule 3A to the Communications Act 2003). Accordingly, [NAME_10] cannot rely upon Paragraph 21(5).
160. The test under Paragraph 21 of the Code for the imposition of a code agreement is met.
D Jackson Judge of the First-tier Tribunal
Either party may appeal this Decision to the Upper Tribunal (Lands Chamber) but must first apply to the First-tier Tribunal for permission. Any application for permission must be in writing, stating grounds relied upon, and be received by the First-tier Tribunal no later than 28 days after the Tribunal sends its written reasons for the Decision to the party seeking permission.
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) Tribunal Rejects Claim for Telecoms Equipment on Hotel Roof Due to Redevelo…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules on Mobile Home Site Services
- First-tier Tribunal (Property Chamber) First-tier Tribunal Decides on Reasonableness of Service Charges
- First-tier Tribunal (Property Chamber) Landlord's Request for Dispensation Rejected by First-tier Tribunal
- First-tier Tribunal (Property Chamber) First-tier Tribunal Determines Tenant's Service Charge Liability
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rejects Claimant's Request for Holding Deposit Return
- First-tier Tribunal (Property Chamber) Tribunal Upholds Refusal to Vary HMO Licence Due to Non-Compliance with Sta…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rejects Rent Repayment Claim
- First-tier Tribunal (Property Chamber) Tribunal Rules on Service Charges and Management Agreements
- First-tier Tribunal (Property Chamber) First-tier Tribunal Rules Service Charges Reasonable and Payable
- First-tier Tribunal (Property Chamber) First-tier Tribunal Denies Right to Buy for Elderly Suitable Property
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- A tenant must provide evidence to support their claim regarding the reasonableness of service charges.
- A tenant is entitled to a determination of whether service charges are reasonable and payable.
- A tenant is entitled to challenge the reasonableness of service charges under Section 19 of the Landlord and Tenant Act 1985.
❌ Tends to be rejected
- The tenant did not meet the conditions specified in Paragraph 21 to impose a code agreement.
- The tenant failed to establish loss or damage caused by the exercise of Code rights.
- Service charges are considered reasonable if they are for services of a reasonable standard and are not excessive.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The decision rejected the claimant's request to impose a code agreement under the Electronic Communications Code.
Who was involved?
The case involved a claimant seeking to impose a code agreement and a respondent claiming redevelopment intentions.
How did the court decide, and why?
The court decided that the respondent did not meet the criteria for redevelopment under the Electronic Communications Code.
Which laws or rules were applied?
The Electronic Communications Code (Schedule 3A to the Communications Act 2003) was applied.
What was the argument that mattered most?
The argument that mattered most was whether the respondent had a genuine intention to redevelop the site.
Was the decision for or against the person who brought the case?
The decision was against the person who brought the case.
What does this mean for someone in a similar situation?
Someone in a similar situation should ensure they have strong evidence of redevelopment intentions if they wish to oppose a code agreement.
What evidence or documents mattered?
Evidence of the respondent's intention to redevelop the site was crucial.
Can a decision like this be appealed?
Yes, either party may appeal this decision to the Upper Tribunal (Lands Chamber) but must first apply to the First-tier Tribunal for permission.
Is it worth getting a solicitor for a case like this?
It is always recommended to get advice from a qualified solicitor for cases involving complex legal matters.
