Tribunal Grants Urgent Roof Repairs Dispensation
📌 In brief
The First-tier Tribunal granted permission for a landlord to bypass formal consultation requirements for urgent roof repairs at a residential property, ensuring timely repairs to prevent further damage.
⚖️ Legal holding
A landlord may be granted dispensation from consultation requirements if the works are urgent and cannot wait for formal consultation.
📖 What the law says
The appropriate tribunal can grant dispensation from consultation requirements related to qualifying works if it determines that it is reasonable to do so.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The Tribunal granted dispensation from consultation requirements due to urgent roof repairs needed at the address.
📜 Headnote Official document
The Tribunal granted dispensation from consultation requirements for urgent roof repairs at a residential property, citing the need for immediate action to prevent further damage.
📚 Full judgment Official document
OUTCOME: Allowed
Page 1 of 5
FIRST – TIER TRIBUNAL
PROPERTY CHAMBER
(RESIDENTIAL PROPERTY)
Case Reference : BIR/00CN/LDC/2019/0004
Property : [ADDRESS] [POSTCODE]
Applicant : [redacted] : [COMPANY]
Respondents : [redacted] : An Application under Section 20ZA of the Landlord and Tenant Act 1985 for dispensation of the Section 20 consultation requirements.
Tribunal Members : [NAME] (Hons) FRICS
Judge David R Salter
Date of Decision : 3 July 2019
DECISION _____________________________________________________
© CROWN COPYRIGHT 2019
Page 2 of 5
BACKGROUND
1. The Application, received on 14 June 2019, requests the Tribunal to grant a dispensation from the consultation requirements contained within section 20 of the Landlord and Tenant Act 1985 (“the 1985 Act”) and the Service Charge (Consultation Requirements) (England) Regulations 2003 (“the 2003 Regulations”) in respect of repairs required to [ADDRESS] [POSTCODE].
2. The application form states that the Applicant, the Trustees of the [COMPANY], is the landlord of the subject property, whilst the Respondents are the lessees/[NAME] of the 15 apartments contained therein.
3. The works in question are the repair of the roof to the development. The Applicant advises that leaks have been reported into several apartments and also into the electrical systems relating thereto.
4. The Tribunal was advised that the matter was urgent and accordingly fast tracked the application.
5. Under the provisions of the 1985 Act and the 2003 Regulations, the Applicant is required to consult if the cost of the works is in excess of £250 including VAT per leaseholder.
6. The Applicant claims that dispensation is necessary as the works are urgently required and further it is not possible to carry out a lasting temporary repair whilst formal consultation procedures are carried out. The cost of a new roof is estimated at £70,000 and there are approximately £33,000 in reserve. The Landlord will loan the balance to the service charge account. The works proposed will therefore be qualifying works within the meaning of section 20ZA (2) of the 1985 Act.
7. Following Directions of the Tribunal, copies of the application form and ancillary information were forwarded to all [NAME].
8. The Tribunal received no representations from any lessee/leaseholder.
THE LEASE
9. Relevant provisions within the lease, dated 28 February 1986, submitted to the Tribunal on behalf of the Applicant are as follows
Paragraph 2 of the Second Schedule - Covenants by the Lessee states:
Page 3 of 5
“(2) To pay in addition to the rent hereby reserved and covenanted to be paid and by way of further or additional rent the expenses incurred by the Lessor under paragraphs 1 to 12 of the Third Schedule in such sum or sums and in the proportions specified in the Fourth Schedule hereto.”
The Fourth Schedule states:
“” Any expenses incurred by the Lessor under Paragraph 1 to 12 of the Third Schedule hereto shall be paid in the proportions of one Fifteenth by each Lessee except where the Lessor shall direct that any expenditure shall be divided in different proportions……..”.
The Third Schedule at Paragraph 4 states the following:
“”4. To repair and keep in good repair and condition the Building and each and every part thereof and the garages (other than such part of the Building or garages as are the responsibility of individual Lessees) including the roof thereover and the means of support thereof the Service Media the foundations thereof the brickwork thereof and other the support for the Building and garages and any communal television reception apparatus”.
THE INSPECTION
10. The Tribunal carried out an inspection of the subject property accompanied by Mr [APPELLANT] of [NAME], the Applicant’s representative and the recently appointed managing agents.
11. [ADDRESS], which is of brick construction surmounted by a flat roofing system, comprises a single structure incorporating 15 apartments arranged over ground, first and second floors. There are two communal entrance halls, one serving apartments 1 to 9 and the other serving the remainder, 10 to 16.
12. The Tribunal inspected the top floor communal areas of each stairwell and noted evidence of water ingress. The Tribunal also inspected apartment 9, by the courtesy of Mr [NAME] whose parents are the [NAME], and apartment 16, by the courtesy of the [NAME], Mr [NAME] and Mrs [NAME]. In both apartments, evidence of extensive water ingress was noted. The issues created by the water ingress had been exacerbated by the fact that water had run into the electrical installations of the apartments inspected.
13. The apartments inspected were at either end of the development and this coupled with the evidence of the ingress into the communal areas would indicate that the entire roof requires attention not just a portion of the same.
Page 4 of 5
14. The Applicant in their submissions stated that they had carried out some emergency repairs to the roof but these were not expected to last and a permanent repair was urgently required. The Tribunal was advised that a surveyor had been appointed to oversee the project. Initially, a core sample of the roof would be taken to assess the extent of the repair required and accordingly produce a specification. The specification would then be used to invite tenders.
THE LAW
15. Section 20 of the 1985 Act, as amended by the Commonhold and Leasehold Reform Act 2002, sets out the procedures landlords must follow which are particularised, collectively, in the Service Charges (Consultation Requirements) (England) Regulations 2003. There is a statutory maximum that a lessee has to pay by way of a contribution to “qualifying works” (defined under section 20ZA (2) as works to a building or any other premises) unless the consultation requirements have been met. Under the Regulations, section 20 applies to qualifying works which result in a service charge contribution by an individual tenant in excess of £250.00.
16. There are essentially three stages in the consultation procedure, the pre tender stage; Notice of Intention, the tender stage; Notification of Proposals including estimates and in some cases a third stage advising the [NAME] that the contract has been placed and the reasons behind the same.
17. It should also be noted that the dispensation power of the First-tier Tribunal under section 20ZA of the 1985 Act only applies to the statutory consultation requirements and does not confer any power to dispense with any contractual consultation provisions which may be contained in the lease.
THE TRIBUNAL’S DETERMINATION
18. The provisions cited from the lease enable the cost of the works to be recovered from the lessees/[NAME] by way of the service charge.
19. It is clear to the Tribunal from the information supplied by the Applicant and the evidence gleaned from the inspection that extensive works are urgently required to the roof of the property.
20. Section 20ZA of the 1985 Act does not expand upon or detail the circumstances when it may be reasonable to make a determination dispensing with the consultation requirements. However, following the Supreme Court’s judgment in [COMPANY] v [NAME] et all [2013] UKSC 14, the Tribunal in considering whether dispensation should be granted in this matter should take
Page 5 of 5
into account the extent to which lessees/[NAME] were prejudiced by the landlord’s failure to consult.
21. In these circumstances, the delay caused by following the consultation procedures, at least two months, could exacerbate the situation. It is conceivable that if there were to be another period of heavy rain as occurred in early June, that some occupiers may have to move out of their apartments or at the very least more damage could be caused internally.
22. The Tribunal has been informed that the Applicant has appointed a surveyor to produce a specification and seek tenders for the repairs hence the Tribunal cannot see that the lessees/[NAME] will be prejudiced by the consultation procedures not being followed. In addition, no lessee/leaseholder has made representations of any kind to the Tribunal.
23. The Tribunal is satisfied that the works are required and that, on the evidence provided, it is reasonable to dispense with the consultation requirements of section 20 of the 1985 Act. Accordingly, dispensation is duly granted.
24. Parties should note that this determination does not prevent any later challenge by any of the respondent [NAME] under sections 19 and 27(A) of the 1985 Act on the grounds that the costs of the works when incurred had not been reasonably incurred or that the works had not been carried out to a reasonable standard.
25. In making its Determination, the Tribunal has had regard to its inspection, the submissions of the parties, the relevant law and its knowledge and experience as an expert Tribunal, but not to any special or secret knowledge.
APPEAL
26. A party seeking permission to appeal this decision must make a written application to the Tribunal for permission to appeal. This application must be received by the Tribunal no later than 28 days after this decision is sent to the parties. Further information is contained within Part 6 of The Tribunal Procedure (First-tier Tribunal) (Property Chamber) Rules 2013 (S.I. 2013 No. 1169).
[NAME]
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) Dispensation Granted for Urgent Works Without Consultation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Urgent Repairs Dispensation Without Hearing
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Urgent Roof Repairs Dispensation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs at Grimshaw…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Unconditional Dispensation for Urgent Works
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Roof Repairs at Green View Court
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Fire Safety Works
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Boiler Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Building Works
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Emergency Works Dispensation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Repairs
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The roof repairs were urgently needed because leaks were reported in several apartments and into electrical systems.
- The Tribunal's inspection confirmed extensive water ingress in communal areas and apartments, indicating the entire roof needed attention.
- Delaying the repairs for formal consultation could worsen the situation, potentially causing more damage or requiring residents to move out.
- The landlord had appointed a surveyor to manage the project and seek tenders, which meant the leaseholders would not be prejudiced by the lack of consultation.
- No leaseholder submitted any objections or representations to the Tribunal regarding the application for dispensation.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The Tribunal allowed the landlord to bypass formal consultation requirements for urgent roof repairs.
Who was involved?
The landlord of a residential property and the leaseholders of the apartments.
How did the court decide, and why?
The court decided to grant dispensation because the works were urgent and could not wait for formal consultation.
Which laws or rules were applied?
The Landlord and Tenant Act 1985 and the Service Charge (Consultation Requirements) (England) Regulations 2003.
What was the argument that mattered most?
The urgency of the repairs and the inability to perform a lasting temporary repair while consulting.
Was the decision for or against the person who brought the case?
The decision was for the landlord.
What does this mean for someone in a similar situation?
Someone in a similar situation may also be able to bypass consultation requirements if the works are truly urgent.
What evidence or documents mattered?
Evidence of water ingress and the risk of further damage if repairs were delayed.
Can a decision like this be appealed?
Yes, a decision like this can be appealed to a higher court.
Is it worth getting a solicitor for a case like this?
Yes, it is recommended to get a solicitor for a case like this.
