First-tier Tribunal Grants Dispensation for Re-cladding Works
📌 In brief
The First-tier Tribunal allowed a landlord to skip certain consultation requirements for urgent re-cladding works at a property. The decision was made to ensure safety measures could be implemented quickly, despite the usual need for extensive consultations with tenants.
⚖️ Legal holding
A landlord is entitled to dispensation from consultation requirements under section 20ZA of the Landlord and Tenant Act 1985 where the consultation process does not facilitate necessary works and timelines.
📖 What the law says
The First-tier Tribunal can grant permission to skip certain consultation requirements if it finds it reasonable to do so, specifically when dealing with qualifying works or agreements. Qualifying works refer to work done on buildings or other premises, and the consultation requirements involve providing tenants with details about the works, obtaining estimates, considering tenant suggestions, and giving reasons for the works.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The tribunal granted dispensation from consultation requirements for re-cladding works under the Landlord and Tenant Act 1985.
📜 Headnote Official document
The First-tier Tribunal granted dispensation from the consultation requirements under section 20ZA of the Landlord and Tenant Act 1985 for re-cladding works at a property. The decision was based on the necessity to bypass traditional consultation processes to address urgent safety concerns.
📚 Full judgment Official document
OUTCOME: Allowed
FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case Reference :
LON/00BK/LDC/2021/0202
HMCTS code
Property :
: V: CVPRemote
Block D, [ADDRESS], 22 – [ADDRESS], [ADDRESS] and [ADDRESS], London SW1P Applicant : [redacted] Landlord”) Representative : Ms [COUNSEL] – Counsel Ms [COUNSEL] [NAME] Manager for [COMPANY] Respondents :
[redacted] (“the tenants”) and in particular Dr [NAME]; Prof [NAME]; [COUNSEL] and [COUNSEL] (the opposing lessees) Representative :
Dr [COUNSEL] for the opposing lessees Type of Application :
For dispensation from the consultation requirements under section 20ZA Landlord & Tenant Act 1985 Tribunal Member :
Tribunal Judge Dutton Mr R Waterhouse BSc (Hons) LLM Property Law MA FRICS
Date of Decision : 14 January 2022
DECISION
This has been a remote video hearing, which has been consented to by the parties. The form of remote hearing was CVPRemote. A face-to-face hearing was not held because it was not practicable and no one requested same.
The documents the Tribunal were referred to were in a bundle of some 299 pages, together with two witness statements the contents of which had been noted.
Decision
(1) We determine that dispensation should be granted from the consultation requirements under s20 of the Landlord and Tenant Act 1985 (the Act) and the Service Charges (Consultation Requirements)(England) Regulations 2003 in respect of the property Block D [ADDRESS], 22 – [ADDRESS], [ADDRESS] and [ADDRESS], London SW1p (the Property) for the reasons we have stated below. (2) We make no determination as to the reasonableness of the costs of same, these being matters which can be considered, if necessary, under the provisions of s27A and s19 of the Act. The application 1. The applicant landlord sought dispensation from the consultation provisions in respect of the re-cladding of parts and works to balconies and any associated fire prevention works at the Property. The Property is a modern purpose-built construction containing, we were told, 40 flats and commercial premises at ground floor level.
2. The application was dated 4 August 2021 and indicated an urgency. The reasons stated in the application are as follows. “Following guidance relating to the construction of the external wall system it has been discovered that the construction comprises combustible materials and poses a risk of fire spread. Accordingly works are required to the Premises (sic) in line with Government Guidelines (“the Works”). The Applicants agent began the consultation process in relation to the Works.
Due to the nature of the works and the Design & Build method due to be adopted, the Applicant is unable to complete the consultation process.” 3. The Directions provided for the tenants and sub lessees to be informed of the application and to be provided with copies and we are told by the managing agent that this was done. Indeed, that must be the case as four lessees responded by filing the questionnaire indicating they wished to be heard.
4. The tribunal did not consider that an inspection of the Building was necessary, nor would it have been proportionate to the issues in dispute.
5. The only issue for the tribunal is whether or not it is reasonable to dispense with the statutory consultation requirements of section 20 of the 1985 Act. This application does not concern the issue of whether any service charge costs will be reasonable or payable. Hearing 6. The matter came before us for hearing on 12 January 2022. The applicant was represented by Ms [COUNSEL] of counsel accompanied by Ms [COUNSEL], the operations manager of [COMPANY] ([COMPANY]). We had expected there to be representation on behalf of the opposing lessees, but no one attended.
7. It is fair to say that their initial concerns had been expressed in a Statement of Case by Dr [NAME] dated 27 August 2021. They confirmed that they were shared ownership leaseholders, their landlord being London & Quadrant (L&Q) and had not been provided with an initial notice under section 20 Landlord and Tenant Act 1985 (the Act). Further they complained that they had not been granted sufficient time to deal with issues by reference to the terms of the directions order dated 10 August 2021. This had provided for the matter to be dealt with on paper but was subsequently listed for a hearing, this was listed for a date in October, which was postponed until 12 January 2022. The applicants responded to the opposing lessees concerns on 3 September 2022. Nothing more has been heard from them. It is understood that Dr [NAME] may have been taken ill and we hope he has made a full recovery.
8. At the hearing we received written and verbal evidence from [NAME] [NAME] and a written statement, with exhibits from Mr [NAME] an executive Property Manager with [COMPANY]. We noted all that was said.
9. As Mr [NAME] could not attend the hearing Ms [NAME] spoke both for herself and for him. It appears she has been with [COMPANY] for a number of years and involved with the Property since 2015. She explained that the intention was proceed with the Works through a Design and Build contract with a lead consultant, initially thought to be [NAME] ([NAME]) but now it seems [COMPANY]. The reasons for this route were that following the s20 consultation process would not allow for the necessary steps to be taken as appropriate to ensure that the correct contractors for the works could be retained, as there were pressures on the industry at this time, following the Grenfell Tower fire, and there were a limited number of contractors available and further that the time scales of the application to the Building Safety Fund (BSF) could be pursued using this Design and Build route.
10. She told us budgeted figures had been utilised for the purposes of estimated service charge demands for the period July 2021 to June 2022 in the sum of £348,600. These demands were made of [NAME] who have paid the first tranche, the second being due at the end of this month and two lessees who had completed the staircase acquisition of their flats.
11. On the BSF route we were told that a neighbouring block, Block F, had been processed but had proven unsuccessful, as unlike the Property the block was below 18 metres in height. It had, however, highlighted issues with lessees that would be addressed in the procedure under the Design and Build contract for this block.
12. The steps to be taken by the lead consultant were set out in a letter dated 19 August 2021 exhibited to [NAME] statement, which set out under the heading ‘Pre-Contract Works what would be done for the initial fee, said to be slightly less for [NAME] than [NAME]. This would then lead to the ‘Contract Works’. It seems that further surveys are to be done in respect of matters highlighted in reports from [NAME] at page 167 and from [NAME] at page 106 para 5.4, the urgency for which is, to an extent explained in the [NAME] report of December 2020 at page 216.
13. Ms [NAME] submitted that it was reasonable to dispense. There were four reasons. The first was that there was no prejudice to the leaseholders. Neither the opposing lessees, nor [NAME], had produced alternative estimates. This was, Ms [NAME] said, not a straight forward process as was highlighted both in the applicant’s statement of case and Ms [APPELLANT] and Mr [APPELLANT] evidence. Further, and linked to her second submission, the consultation process did not sit with the need for the Design and Build approach and did not facilitate the application to BSF for funding. So far, we were told, the time limits under the BSF had been adhered to.
14. Ms [NAME] said there was urgency in that there were a number of hurdles to jump, and each took time. There was pressure on the industry, and it was difficult to instruct individual contractors. Fourthly, the Design and Build contract was the correct way forward as it would accommodate changes, which under the consultation route would require further referral to lessees and further delays, which could impact on the BSF application.
15. Ms [NAME] told us that [NAME] would be instructed within the next 7 days and the matter would then progress Findings 6. In making our decision we have borne in mind the various reports to which we were referred, which in our finding clearly indicate that works are required inter alia to the cladding and the balconies at the Property. We are satisfied that the Design and Build concept is reasonable and that this does not sit with the consultation process under s20 of the Act. Further there needs to be flexibility to accommodate the requirements, when they engage, of the BSF, which is clearly in the lessees’ interests.
7. The Law applicable to this application is to be found at s20ZA of the Act. The decision of the Supreme Court in [COMPANY] and Benson and others [2013] UKSC 14 has been taken into account by us in reaching our decision. There has not been any allegation of prejudice to the leaseholders as set out in the [NAME] case. We therefore find that it is reasonable to grant dispensation from the consultation requirements required under s20 of the Act.
8. Our decision is in respect of the dispensation from the provisions of s20 of the Act only. Any concern that a Respondent has as to the standard of works, the need for them and costs will need to be considered separately.
Andrew Dutton
Name: Tribunal Judge Dutton Date: 14 January 2022
ANNEX – RIGHTS OF APPEAL
1. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber) then a written application for permission must be made to the First-Tier at the Regional Office which has been dealing with the case.
2. The application for permission to appeal must arrive at the Regional Office within 28 days after the Tribunal sends written reasons for the decision to the person making the application.
3. If the application is not made within the 28-day time limit, such application must include a request to an extension of time and the reason for not complying with the 28-day time limit; the Tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed despite not being within the time limit.
4. The application for permission to appeal must identify the decision of the Tribunal to which it relates (ie give the date, the property and the case number), state the grounds of appeal and state the result the party making the application is seeking
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) Landlord Granted Permission to Skip Consultation for Urgent Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Fire Safety Works
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Roof Repairs Due to Water Ingress
- First-tier Tribunal (Property Chamber) Landlord Granted Permission to Skip Consultation for Urgent Drainage Works
- First-tier Tribunal (Property Chamber) Landlord Granted Permission to Skip Consultation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) Emergency Repairs Approved Without Leaseholder Consultation
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation from Consultation Requirements
- First-tier Tribunal (Property Chamber) Landlord Granted Dispensation for Urgent Boiler Repairs
- First-tier Tribunal (Property Chamber) Landlord Granted Dispensation from Consultation Requirements
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Drainage Works
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- Dispensation was granted because works were clearly required for the cladding and balconies.
- The Design and Build approach was reasonable and incompatible with the standard consultation process.
- Flexibility was needed to accommodate the requirements of the Building Safety Fund, which benefits leaseholders.
- There was no evidence of prejudice to the leaseholders from the lack of consultation.
- The consultation process would not allow for necessary steps to be taken to secure contractors due to industry pressures.
❌ Tends to be rejected
- The opposing leaseholders' concern about not receiving an initial notice was not upheld as a reason to deny dispensation.
- The leaseholders' complaint about insufficient time to respond to issues was not accepted as a reason to deny dispensation.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
The decision granted dispensation from consultation requirements for re-cladding works at a property.
Who was involved?
The landlord and the tenants of the property were involved.
How did the court decide, and why?
The court decided to grant dispensation because the consultation process would delay necessary safety works.
Which laws or rules were applied?
Section 20ZA of the Landlord and Tenant Act 1985 and the Service Charges (Consultation Requirements)(England) Regulations 2003 were applied.
What was the argument that mattered most?
The argument that mattered most was that the consultation process would hinder the timely implementation of necessary safety measures.
Was the decision for or against the person who brought the case?
The decision was for the person who brought the case, the landlord.
What does this mean for someone in a similar situation?
Someone in a similar situation might also be able to seek dispensation from consultation requirements if the works are urgent and necessary for safety.
What evidence or documents mattered?
Evidence included reports highlighting the urgency of the works and the need for a Design and Build approach.
Can a decision like this be appealed?
Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber) within 28 days.
Is it worth getting a solicitor for a case like this?
It is always recommended to seek advice from a qualified solicitor for cases involving complex legal issues.
