Tribunal Grants Dispensation for Urgent Roof Repairs
📌 In brief
The First-tier Tribunal allowed a landlord to bypass certain consultation requirements for urgent roof repairs to a block of flats. The decision was based on the urgency of the repairs and the lack of opposition from the leaseholders.
⚖️ Legal holding
A landlord may obtain dispensation from consultation requirements if it is reasonable to do so under section 20ZA of the Landlord and Tenant Act 1985.
📖 What the law says
Under this section, a landlord can apply to a tribunal for permission to skip certain consultation requirements related to building works or long-term agreements if the tribunal finds it reasonable to do so.
Plain-English explanation — does not replace advice from a solicitor.
📖 Technical summary
The tribunal granted dispensation from consultation requirements for urgent roof repairs.
📜 Headnote Official document
The First-tier Tribunal granted dispensation from consultation requirements for urgent roof repairs to the block containing flats 1-12, determining it was reasonable to do so under section 20ZA of the Landlord and Tenant Act 1985.
📚 Full judgment Official document
OUTCOME: Allowed
© CROWN COPYRIGHT 2020 FIRST-TIER TRIBUNAL PROPERTY CHAMBER (RESIDENTIAL PROPERTY) Case Reference : CAM/34UF/LDC/2023/0058 Property : [ADDRESS] [POSTCODE] Applicant : [redacted] Respondents : [redacted] property (including any of their sub- tenants of any such dwelling) who are liable to contribute to the cost of the relevant agreements Type of application : For dispensation from consultation requirements - Section 20ZA of the Landlord and Tenant Act 1985 Tribunal members : [APPELLANT] [NAME]([NAME]) Date of decision : 13 February 2024
DECISION Description of hearing This has been a remote determination on the papers which the parties are taken to have consented to, as explained below. A hearing was not held because it was not necessary, and all issues could be determined on paper. The documents that I was referred to are in an unpaginated bundle from the Applicant. I have noted the contents and my decision is below. The tribunal’s decision The tribunal determines under section 20ZA of the Landlord and Tenant Act 1985 to dispense with the consultation requirements in respect of qualifying works to repair the roof to the block containing Flats 1-12.
2 Reasons for the tribunal’s decision The application (1) The landlord has applied for dispensation from the statutory consultation requirements in respect of urgent works to repair the roof to the block containing Flats 1-12. (2) The relevant contributions of leaseholders through the service charge towards the costs under these agreements would be limited to a fixed sum unless the statutory consultation requirements, prescribed by section 20 of the Landlord and Tenant Act 1985 (the “1985 Act”) and the Service Charges (Consultation etc) (England) Regulations 2003: (i) were complied with; or (ii) are dispensed with by the tribunal. (3) In this application, the Applicant seeks a determination from the tribunal, under section 20ZA of the 1985 Act, to dispense with the consultation requirements. The tribunal has jurisdiction to grant such dispensation if satisfied that it is reasonable to do so. (4) The only issue here for the tribunal is whether it is satisfied that it is reasonable to dispense with the consultation requirements. (5) This application does not concern the issue of whether any service charge costs under the relevant agreements will be reasonable or payable or by whom they are payable. The Property and parties (6) The applicant says the property consists of a residential block of 36 units in total. (7) The application is made by [NAME] ([RESPONDENT] on behalf of the landlord, [RESPONDENT]. The application was made against the leaseholders of the relevant properties (the “Respondents”) Procedural history (8) The Applicant says that dispensation is sought, as explained below. (9) Initial case management directions were given on 12 December 2023. The directions included a reply form for any leaseholder who objected to the application to return to the tribunal and the Applicant, also indicating whether they wished to have an oral hearing. Any such objecting leaseholder was required to respond by 22 January 2024.
3 (10) The directions further provided that this matter would be determined on or after 5 February 2024 based on the documents, without a hearing, unless any party requested an oral hearing. (11) On reviewing these documents, the tribunal considered that an inspection of the Property was neither necessary nor proportionate to the issues to be determined and that a hearing was not necessary. (12) No request for a hearing was made by the parties. The Applicant’s case. (13) The applicant seeks dispensation with the statutory consultation requirements in respect of qualifying works to replace the roof over flats 1-12. This includes provision of scaffolding, overboarding the flats, installing a 3-layer torch on felt roof system, flashing to pipework and upstanding areas and trim to perimeter of the roof. (14) Estimates were obtained from two contractors, one for £14,640 including VAT and the other for £19,530 including VAT. (15) Leaseholders were informed of these on 23 November 2023. The Respondents’ position. (16) As mentioned above, the directions provided for any Respondent who wished to oppose the application for dispensation to complete the reply form attached to the directions and send it to the tribunal and the Applicant. (17) The tribunal has not received any response or statement of case opposing the application, or comments on the Applicant’s statements in the application form. In the circumstances, the tribunal concluded that the application was unopposed. Determination (18) Following the Supreme Court decision of Daejan Investments Ltd. v Benson [2013] UKSC 14, the only issue for the Tribunal is whether the Respondents have suffered prejudice in dispensing with the consult This application for dispensation from the consultation requirements was not opposed by the Respondents, who have not challenged the information provided by the Applicant in the application form, identified any prejudice which they might suffer because of the non- compliance with the consultation requirements, nor asked to be provided with any other information. (19) The tribunal is satisfied that it is reasonable to dispense with the consultation requirements in relation to the roof works as described above.
4 (20) It therefore determines under section 20ZA of the 1985 Act to dispense with all relevant consultation requirements in relation to these works. (21) This is not an application for the tribunal to approve the reasonableness of the contracts or the reasonableness, apportionment or payability of any service charge demand. (22) I make no finding in that regard and the leaseholders will continue to be able to make an application under section 27A of the Act in respect of the reasonableness of the agreements and/or the reasonableness, apportionment or payability of the service charge demand for them. (23) There was no application to the tribunal for an order under section 20C of the 1985 Act. (24) The Applicant shall be responsible for serving a copy of this decision on all leaseholders. [NAME] [NAME]([NAME]) 13 February 2024 Rights of appeal By rule 36(2) of the Tribunal Procedure (First-tier Tribunal) (Property Chamber) Rules 2013, the tribunal is required to notify the parties about any right of appeal they may have. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber), then a written application for permission must be made to the First-tier Tribunal at the regional office which has been dealing with the case. The application for permission to appeal must arrive at the regional office within 28 days after the tribunal sends written reasons for the decision to the person making the application. If the application is not made within the 28-day time limit, such application must include a request for an extension of time and the reason for not complying with the 28-day time limit; the tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed, despite not being within the time limit. The application for permission to appeal must identify the decision of the tribunal to which it relates (i.e., give the date, the property and the case number), state the grounds of appeal and state the result the party making the application is seeking.
5 If the tribunal refuses to grant permission to appeal, a further application for permission may be made to the Upper Tribunal (Lands Chamber).
📊 How courts decide similar cases
Among 12 similar decisions in this collection:
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Cladding Works
- First-tier Tribunal (Property Chamber) Landlord Granted Dispensation for Fire Safety Works Without Consulting Tena…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Roof Repairs
- First-tier Tribunal (Property Chamber) Landlord Granted Dispensation for Boiler Installation Without Full Consulta…
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Walkway Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Environmental Work
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Urgent Pump Replacement Dispensation
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Skylight Repairs
- First-tier Tribunal (Property Chamber) First-tier Tribunal Grants Dispensation for Urgent Lift Repairs
- First-tier Tribunal (Property Chamber) Tribunal Grants Dispensation for Urgent Roof Repairs
A snapshot of this collection — not a prediction of your case's outcome.
⚖️ What tends to weigh in cases like this
✅ Tends to be accepted
- The works are urgent.
- There are no objections from leaseholders.
- There is no prejudice to the leaseholders.
- The works are necessary.
- It is reasonable to dispense from consultation requirements.
Patterns observed in similar cases in this collection — every case is unique.
❓ Frequently asked questions
What did this decision decide?
It decided to grant dispensation from consultation requirements for urgent roof repairs.
Who was involved?
The landlord and leaseholders of the relevant properties were involved.
How did the court decide, and why?
The court decided to grant dispensation because it was reasonable to do so given the urgency of the repairs and the lack of opposition from the leaseholders.
Which laws or rules were applied?
Section 20ZA of the Landlord and Tenant Act 1985 was applied.
What was the argument that mattered most?
The argument that mattered most was that the repairs were urgent and leaseholders had not objected to the application.
Was the decision for or against the person who brought the case?
The decision was for the person who brought the case.
What does this mean for someone in a similar situation?
Someone in a similar situation may also seek dispensation from consultation requirements if the repairs are urgent and there is no opposition from leaseholders.
What evidence or documents mattered?
Estimates from contractors and the lack of objections from leaseholders mattered.
Can a decision like this be appealed?
Yes, a decision like this can be appealed to the Upper Tribunal (Lands Chamber).
Is it worth getting a solicitor for a case like this?
It is always recommended to get advice from a qualified solicitor for a case like this.